The filed record
Rooftop Make-up Air Units at BLC Casino and QE Exhibit Hall
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-10-29 · Board of Governors of Exhibition Place · adopted
As filed
The Board of Governors of Exhibition Place: 1. Concurred with the action taken by the Chair of the Board of Governors of Exhibition Place and the Chief Executive Officer, Exhibition Place in approving the award of Contract 21-073-17380 (RFT EP107-2021) to Servocraft Limited of Toronto, Ontario for replacement of the rooftop make-up air units at BLC Casino and QE Exhibit Hall in the amount of $514,500.00, which includes
Show the rest of As filed, 156 more characters as filed
a cash allowance of $50,000.00, but excludes HST; this being the lowest acceptable tender submission received following the public tendering of the project.
On the agenda
As the city filed it
This report recommends approving a contract with Servocraft Limited of Toronto, Ontario for replacement of the rooftop make-up air units at Better Living Centre (BLC) Casino and Queen Elizabeth (QE) Exhibit Hall. The tender call was issued on August 19, 2021 through Exhibition Place Purchasing and Materials Stores via Merx Online Procurement System, and the recommendation is to award the contract to the lowest compliant bidder meeting tender requirements and specifications within the available budget.
Show the rest of As the city filed it, 424 more characters as filed
In order to meet timelines for construction due to supply chain delivery challenges, weather and operational needs as well as the window of opportunity for site availability in the wake of fewer events this fall, the Chair of the Board in consultation with the CEO of Exhibition Place, approved this contract award pursuant to the authority under the Board Financial By-law 2-18, Article X and seek concurrence of the Board.
Staff recommended
The Chief Executive Officer, Exhibition Place recommends that: 1. The Board of Governors of Exhibition Place concur with the action taken by the Chair of the Board and the Chief Executive Officer in approving the award of Contract 21-073-17380 (RFT EP107-2021) to Servocraft Limited of Toronto, Ontario for replacement of the rooftop make-up air units at BLC Casino and QE Exhibit Hall in the amount of $514,500.00, which
Show the rest of Staff recommended, 165 more characters as filed
includes a cash allowance of $50,000.00, but excludes HST; this being the lowest acceptable tender submission received following the public tendering of the project.
On the record
More from this meeting
- Exhibition Place Hotel X Development - Phase 2 LandsFiled record
- North Corridor, East and West Garage, and Loading Dock Ramps Retrofit at Enercare CentreFiled record
- Northwest Elevator Modernization at Beanfield CentreFiled record
- Sidewalk Concrete Upgrade at Enercare CentreFiled record
- Gardiner Expressway RehabilitationFiled record
- Ontario Line Early WorksFiled record