The decision

2021-02-02 · Toronto City Council · amended

As filed

City Council on February 2, 3 and 5, 2021, adopted the following: 1. City Council endorse the Recommended Design Concept of the yongeTOmorrow Municipal Class Environmental Assessment outlined in Attachment 8 to the report (December 18, 2020) from the General Manager, Transportation Services. 2. City Council authorize the General Manager, Transportation Services to publish a Notice of Completion and file the Environmental Study Report for the yongeTOmorrow Schedule "C" Municipal Class Environmental Assessment on the public record for a minimum 30 days in accordance with the requirements of the Municipal Class Environmental Assessment Act.

Show the rest of As filed, 1,000 more characters as filed

3. City Council direct the General Manager, Transportation Services, as part of the ongoing consultations with main street businesses and other stakeholders, to report back, as part of the process, on the feasibility of: a. new opportunities for patio extensions, parklets and other significant public realm improvements, as well as measures to enhance pedestrian and cyclist safety, before and after the construction; and b. creating a special area by-law to ensure effective maintenance, community safety and special event activation for the new street, in partnership with the local Business Improvement Area. 4. City Council direct the General Manager, Transportation Services, as part of the detailed design process, to continue engagement with business stakeholders along Yonge Street, and in the immediate area, regarding, but not limited, to: a. pedestrian drop off and pick up areas, and taxi stands; b. locations of turning lanes and laybys; and c. spaces for tour buses on Victoria Street.

The vote

Adopt Item as Amended · Carried, 21-5

Against (5)Cynthia Lai, Denzil Minnan-Wong, James Pasternak, Michael Ford, Stephen Holyday
The whole record, all 26 members

Every name opens that member’s record.

On the agenda

As the city filed it

Yonge Street is Toronto's most iconic street and it plays a symbolic role in the cultural identity of Toronto. The section between Queen Street and Carlton / College Street has a distinct character within the broader downtown context - it has a high concentration of pedestrians, street-related retail, and entertainment uses. This area attracts a large number of events, visitors, and tourists. While the number of pedestrians on Yonge Street has somewhat lessened during the COVID-19 pandemic, in the last several years, Yonge Street has been struggling to serve the growing pedestrian demand which has resulted from more people living and working downtown.

Show the rest of As the city filed it, 3,193 more characters as filed

There is overcrowding and insufficient clearway on some sections of sidewalk. The number of pedestrians on the street is expected to continue to grow due to a projected doubling in population and employment in the surrounding area by 2041 along with a continued mode shift towards walking. Without improvement, the sidewalks will become critically deficient, risk pedestrian safety, and deter significant economic and cultural investment. Yonge Street also lacks space for seating, sidewalk cafes, and plantings which support enjoyment of the street as a destination. With a limited right-of-way of 20 metres there are many demands being placed on the street by people walking, cycling, and driving. Prioritization and management of the interactions between all modes is critical. Consideration must also be given to the operation of surface transit, as well as curbside activities like deliveries and ride hailing which support the local economy. The Downtown Plan (TOcore) adopted by City Council in May 2018 identified Yonge Street as one of Toronto's Great Streets, a Cultural Corridor, and a Priority Retail Street. The goals set for Yonge Street in TOcore, along with consultation feedback, have guided the evaluation of alternatives for yongeTOmorrow and the prioritization of space within a physically limited public right-of-way. yongeTOmorrow is a Municipal Class 'C' Environmental Assessment focused on the development and evaluation of design alternatives for Yonge Street from Queen Street to College / Carlton Street. A number of opportunities have been considered to increase pedestrian space and improve the way people move through and experience downtown Yonge Street. This report summarizes the yongeTOmorrow Environmental Assessment process and the resulting Recommended Design Concept which proposes shifting the existing curb alignment to increase sidewalk widths by removing two driving lanes on Yonge Street from College / Carlton Street to Queen Street. While the design of the street recommended through the yongeTOmorrow Environmental Assessment process would be consistent for the entire stretch, the study also evaluated various traffic operational strategies and proposes a flexible approach that would change the way the street functions from day to night. During the day, the one kilometre long stretch of Yonge Street between College / Carlton Street and Queen Street would be prioritized for people walking, cycling, and experiencing the street, while still providing for access and delivery routing needs through pedestrian priority zones, one-way and two-way driving access combined strategically to reduce traffic volumes. Overnight all blocks would have two-way driving access to support Toronto Transit Commission night bus service, deliveries, and general traffic. A cast iron watermain constructed in 1889 exists beneath Yonge Street from Queen Street to College / Carlton Street. This watermain is due for replacement and Yonge Street will need to be reconstructed to facilitate replacement of the watermain. There is an urgency to arrive at a long term design solution for Yonge Street so that road works can be bundled with the watermain replacement.

Staff recommended

The General Manager, Transportation Services recommends that: 1. City Council endorse the Recommended Design Concept of the yongeTOmorrow Municipal Class Environmental Assessment outlined in Attachment 8 to the report (December 18, 2020) from the General Manager, Transportation Services. 2. City Council authorize the General Manager, Transportation Services to publish a Notice of Completion and file the Environmental

Show the rest of Staff recommended, 220 more characters as filed

Study Report for the yongeTOmorrow Schedule "C" Municipal Class Environmental Assessment on the public record for a minimum 30 days in accordance with the requirements of the Municipal Class Environmental Assessment Act.

Considered

  • 2021-01-11 · Infrastructure and Environment Committee · amended

    Decision as filed

    The Infrastructure and Environment Committee recommends that: 1. City Council endorse the Recommended Design Concept of the yongeTOmorrow Municipal Class Environmental Assessment outlined in Attachment 8 to the report (December 18, 2020) from the General Manager, Transportation Services. 2. City Council authorize the General Manager, Transportation Services to publish a Notice of Completion and file the Environmental

    Show the rest of Decision as filed, 220 more characters as filed

    Study Report for the yongeTOmorrow Schedule "C" Municipal Class Environmental Assessment on the public record for a minimum 30 days in accordance with the requirements of the Municipal Class Environmental Assessment Act.

    Clerk’s note

    The Infrastructure and Environment Committee: 1. Requested the General Manager, Transportation Services to provide a supplementary report to the February 2 and 3, 2021 City Council meeting that: a. clarifies the timelines, requirements and recommendations of the Environmental Assessment; b. summarizes next steps for detailed design, operations planning and construction; and c. summarizes next steps for consultation and engagement with main street businesses and other stakeholders.

    Show the rest of Clerk’s note, 231 more characters as filed

    2. Requested the General Manager, Transportation Services to brief stakeholders, including the Downtown Yonge Business Improvement Area, about the Environmental Assessment, before the City Council meeting on February 2 and 3, 2021.