The decision
2021-12-15 · Toronto City Council · adopted
As filed
City Council on December 15, 16 and 17, 2021, adopted the following: 1. City Council endorse facilitating the use of the City's wastewater infrastructure, right-of-way, and property where feasible to facilitate renewable thermal energy projects aimed at significantly reducing greenhouse gases emissions and moving the City closer to achieving its net zero emissions goal. 2. City Council direct the Deputy City Manager,
Show the rest of As filed, 949 more characters as filed
Corporate Services, and the Deputy City Manager, Infrastructure and Development Services, to establish a working group consisting of the Division Heads or their designates from the Environment and Energy, Toronto Water, Corporate Real Estate Management, Transportation Services, Engineering and Construction Services, Legal Services, Financial Planning and any other necessary Divisions, to develop an implementation plan for Part 1 above that includes, without limitation, post-screening application review process and procedures, design and technical standards, template agreements, real estate valuations, and project revenue allocations. 3. City Council direct the Director, Environment and Energy to report to the Infrastructure and Environment Committee in the second quarter of 2022 with details about the implementation plan for the Wastewater Energy Transfer Program and with recommendations for authority needed to launch the full program.
On the agenda
As the city filed it
This report proposes the launch in First Quarter of 2022 of the first stage of a new, city-wide evaluation framework for initial connection requests for potential Wastewater Energy Transfer projects, as was requested by Council in 2019. Wastewater Energy Transfer projects involve a connection to City wastewater (sewer) infrastructure for the non-contact exchange of renewable thermal energy to displace fossil fuel use in buildings, which is Toronto's largest source of greenhouse gas emissions.
Show the rest of As the city filed it, 1,506 more characters as filed
Enabling Wastewater Energy Transfer projects is therefore a key part of implementing the TransformTO Net Zero Strategy. Toronto's sanitary trunk sewer network is estimated to have the capacity to potentially support well over twenty Wastewater Energy Transfer projects. Once in operation, these projects would reduce approximately 200,000 tonnes of greenhouse gas emissions annually while unlocking value for the City through the sale of thermal energy. An evaluation framework is necessary for timely processing of connection requests and to ensure projects do not negatively affect operation/integrity of Toronto Water infrastructure. Stage 1 - Launch First Quarter of 2022 for project intake to gauge interest, size/types of projects, and specific locations/timelines. - Renewable energy developers/building owners visit a City webpage to undertake self-serve project screening and submit a preliminary application. - Environment and Energy Division staff review the application for completeness so that Toronto Water staff can provide the applicant with information needed for preliminary design/business case. Prior to launching Stage 2 in Second Quarter/Third Quarter of 2022, which would enable full applications to the program, staff will establish an efficient back-office process for post-screening detailed application review with other key Divisions, including: Toronto Water, Transportation Services, Engineering and Construction Services, Corporate Real Estate Management, and Legal Services.
Staff recommended
The Interim Director, Environment and Energy recommends that: 1. City Council endorse facilitating the use of the City's wastewater infrastructure, right-of-way, and property where feasible to facilitate renewable thermal energy projects aimed at significantly reducing greenhouse gases emissions and moving the City closer to achieving its net zero emissions goal. 2. City Council direct the Deputy City Manager, Corporate
Show the rest of Staff recommended, 959 more characters as filed
Services, and the Deputy City Manager, Infrastructure and Development Services, to establish a working group consisting of the Division Heads or their designates from the Environment and Energy, Toronto Water, Corporate Real Estate Management, Transportation Services, Engineering and Construction Services, Legal Services, Financial Planning and any other necessary Divisions, to develop an implementation plan for Recommendation Number 1 that includes, without limitation, post-screening application review process and procedures, design and technical standards, template agreements, real estate valuations, and project revenue allocations. 3. City Council direct the Interim Director, Environment and Energy, to report to the Infrastructure and Environment Committee in the Second Quarter of 2022 with details about the implementation plan for the Wastewater Energy Transfer Program and with recommendations for authority needed to launch the full program.
Considered
2021-12-02 · Infrastructure and Environment Committee · adopted
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council endorse facilitating the use of the City's wastewater infrastructure, right-of-way, and property where feasible to facilitate renewable thermal energy projects aimed at significantly reducing greenhouse gases emissions and moving the City closer to achieving its net zero emissions goal. 2. City Council direct the Deputy City Manager, Corporate
Show the rest of Decision as filed, 939 more characters as filed
Services, and the Deputy City Manager, Infrastructure and Development Services, to establish a working group consisting of the Division Heads or their designates from the Environment and Energy, Toronto Water, Corporate Real Estate Management, Transportation Services, Engineering and Construction Services, Legal Services, Financial Planning and any other necessary Divisions, to develop an implementation plan for Part 1 above that includes, without limitation, post-screening application review process and procedures, design and technical standards, template agreements, real estate valuations, and project revenue allocations. 3. City Council direct the Director, Environment and Energy to report to the Infrastructure and Environment Committee in the second quarter of 2022 with details about the implementation plan for the Wastewater Energy Transfer Program and with recommendations for authority needed to launch the full program.
Clerk’s note
Infrastructure and Environment Committee considered items IE26.16 and IE26.18 together.
2021-12-15 · Toronto City Council · adopted
On the record
More from this meeting
- Amendment to Purchase Order Number 6050693 with Ecosystem Energy for the Comprehensive Energy Retrofit Project at Emergency Services HeadquartersFiled record
- Award of Request for Proposal Document Number 2913757955 to Black and Veatch Canada Company for the Preliminary Design of the Black Creek Class Environmental Assessment Solution and Detailed Design, Construction Services and Post Construction Services for Phase One WorksFiled record
- Amendment to Purchase Order Number 6043932 with Drainstar Contracting Limited for Construction Services for the Basement Flooding Protection Program Storm and Sanitary Sewer Improvements and Watermain Replacement on Bestview Drive, Goldenwood Road, Harrington Crescent and Kentland CrescentFiled record
- Award of Negotiated Request for Proposals to Various Suppliers for the Provision of Winter Maintenance ServicesFiled record
- Non-Competitive Contract for Two-Way Radio Supply and Service with BearCom Canada CorporationFiled record
- Actions to Reaffirm Toronto's Tree Canopy TargetFiled record