Port Lands Flood Protection - Don Roadway - Construction Staging Area
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-10-01 · Toronto City Council · adopted
As filed
City Council on October 1 and 4, 2021, adopted the following: 1. City Council authorize the temporary full closure of Don Roadway to all road users, between Lake Shore Boulevard East and Villiers Street, from October 1, 2021 to December 31, 2023. 2. City Council authorize the continuation of the standing prohibition in effect all times on both sides of Commissioners Street, between a point 120 metres east of Don Roadway and Saulter Street South as enacted in Part 15 of City Council's decision on Item TE10.29 entitled "Construction Staging - Port Land Flood Protection and Enabling Infrastructure Project", set to expire on May 16, 2022, to be in effect till December 31, 2023 to accommodate the requirements of this new closure.
Show the rest of As filed, 379 more characters as filed
3. City Council direct that Don Roadway and Commissioners Street be returned to pre-construction traffic and parking regulations when the project is completed. 4. City Council direct the Director, Traffic Management, Transportation Services and the Director, Waterfront Secretariat to review the signage plan and communications plan with the Ward Councillor prior to the closure.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on Don Roadway, which is being rerouted along Commissioners Street, City Council approval is required. As part of the Port Lands Flood Protection Project and Enabling Infrastructure Project, Waterfront Toronto is planning to create two new additional outlets for the Don River and widen the mouth of the river at Keating Channel. In order to facilitate the flood protection and the new configuration of the river path, a new dockwall along the west side of Don Roadway will be constructed.
Show the rest of As the city filed it, 381 more characters as filed
Additionally, the elevation of Don Roadway will be increased by 3.5 metres to match the height of the new dockwall. Transportation Services is requesting authorization to temporarily close Don Roadway, between Lake Shore Boulevard East and Villiers Street, for a period of up to 27 months (i.e. October 1, 2021 to December 31, 2023), to accommodate construction staging operations.
Staff recommended
The Acting Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the temporary full closure of Don Roadway to all road users, between Lake Shore Boulevard East and Villiers Street, from October 1, 2021 to December 31, 2023. 2. City Council authorize the continuation of the standing prohibition in effect all times on both sides of Commissioners Street, between a point 120 metres east of Don Roadway and Saulter Street South as enacted at TE10.29 in Recommendation 15, set to expire on May 16, 2022, to be in effect till December 31, 2023 to accommodate the requirements of this new closure.
Show the rest of Staff recommended, 159 more characters as filed
3. City Council direct that Don Roadway and Commissioners Street be returned to pre-construction traffic and parking regulations when the project is completed.
Considered
2021-09-09 · Toronto and East York Community Council · amended
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council authorize the temporary full closure of Don Roadway to all road users, between Lake Shore Boulevard East and Villiers Street, from October 1, 2021 to December 31, 2023. 2. City Council authorize the continuation of the standing prohibition in effect all times on both sides of Commissioners Street, between a point 120 metres east of Don Roadway and Saulter Street South as enacted at TE10.29 in Recommendation 15, set to expire on May 16, 2022, to be in effect till December 31, 2023 to accommodate the requirements of this new closure.
Show the rest of Decision as filed, 379 more characters as filed
3. City Council direct that Don Roadway and Commissioners Street be returned to pre-construction traffic and parking regulations when the project is completed. 4. City Council direct the Director, Traffic Management, Transportation Services and the Director, Waterfront Secretariat to review the signage plan and communications plan with the Ward Councillor prior to the closure.
2021-10-01 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of Private Walkway adjacent to Wellesley Subway StationFiled record
- Naming of an existing Public Lane south of Gerrard Street East, extending easterly from Wayland AvenueFiled record
- Naming of an existing Public Lane north of Queen Street East, extending between Wineva Avenue and Hammersmith AvenueFiled record
- 109-125 George Street and 231 Richmond Street East - Official Plan and Zoning By-law Amendment Application - Final ReportFiled record
- 2494 Danforth Avenue - Zoning Amendment Application - Final ReportFiled record
- 717 Church Street, and 85-97 Collier Street - Zoning Amendment Application - Request for Direction ReportFiled record