Bid Award Panel · 2022-06-29 · 2022.BA194.3

The filed record

Award of Ariba Document Number 3364372302 to Clearwater Structures Inc. for the Emergency Relief or Assessment of Blocked Drain and Sewer Service Connection Trenchless Rehabilitation by Cured-In-Place-Pipe for Toronto Water

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-06-29 · Bid Award Panel · adopted

As filed

The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (June 23, 2022) from the Acting Chief Procurement Officer: Solicitation Number: Request for Tender, Ariba Document Number 3364372302, Contract Number 22TW-DC-311OCS Description: Emergency Relief or Assessment of Blocked Drain and Sewer Service Connection Trenchless Rehabilitation by Cured-In-Place-Pipe for Toronto Water Operation and Maintenance Section - Various Locations in Toronto from date of award to June 30, 2023 with the option to renew the Contract for two (2) additional separate one (1) year periods at the sole discretion of the City and subject to budget approval(s).

Show the rest of As filed, 1,259 more characters as filed

Should the option year(s) be exercised then the General Manager of Toronto Water will request the Chief Procurement Officer to process the renewal under the same terms and conditions. Recommended Supplier: Clearwater Structures Inc. Contract Award Value: $3,179,780 net of all applicable taxes and charges $3,593,151 including HST and all applicable charges $3,235,744 net of HST recoveries Contract is expect to start on date of award and end on June 30, 2023. Option Period 1 - July 1, 2023 to June 30, 2024 $3,275,173 net of all applicable taxes and charges $3,700,946 including all applicable taxes and charges $3,332,816 net of HST recoveries Option Period 2 - July 1, 2024 to June 30, 2025 $3,373,429 net of all applicable taxes and charges $3,811,974 including all applicable taxes and charges $3,432,801 net of HST recoveries The total potential contract award including all option years is $9,828,382 net of all taxes and charges and $11,106,072 including all applicable taxes and charges. The total potential cost to the City including the optional period is $10,001,362 net of HST recoveries. The above cost calculations reflect a 3 percent Consumer Price Index adjustment applied annually to each year's cost after the initial one (1) year period.

On the agenda

As the city filed it

Solicitation Issued: March 8, 2022 Solicitation Closed: April 5, 2022 Number of Addenda Issued: One (1) Number of Bids: Two (2) Table 2: Summary of Bids Received including bid price: Supplier Name Bid Price (excluding H.S.T.) Clearwater Structures Inc. $3,029,780.00* Capital Sewer Services Inc. $3,592,700.00 *Pursuant to the Request for Tender document the contract award value includes contingency.

Staff recommended

The Acting Chief Procurement Officer recommends that the Bid Award Panel grant authority to award the following contract: Solicitation Number: Request for Tender, Ariba Document Number 3364372302, Contract Number 22TW-DC-311OCS Description: Emergency Relief or Assessment of Blocked Drain and Sewer Service Connection Trenchless Rehabilitation by Cured-In-Place-Pipe for Toronto Water Operation and Maintenance Section - Various Locations in Toronto from date of award to June 30, 2023 with the option to renew the Contract for two (2) additional separate one (1) year periods at the sole discretion of the City and subject to budget approval(s).

Show the rest of Staff recommended, 1,259 more characters as filed

Should the option year(s) be exercised then the General Manager of Toronto Water will request the Chief Procurement Officer to process the renewal under the same terms and conditions. Recommended Supplier: Clearwater Structures Inc. Contract Award Value: $3,179,780 net of all applicable taxes and charges $3,593,151 including HST and all applicable charges $3,235,744 net of HST recoveries Contract is expect to start on date of award and end on June 30, 2023. Option Period 1 - July 1, 2023 to June 30, 2024 $3,275,173 net of all applicable taxes and charges $3,700,946 including all applicable taxes and charges $3,332,816 net of HST recoveries Option Period 2 - July 1, 2024 to June 30, 2025 $3,373,429 net of all applicable taxes and charges $3,811,974 including all applicable taxes and charges $3,432,801 net of HST recoveries The total potential contract award including all option years is $9,828,382 net of all taxes and charges and $11,106,072 including all applicable taxes and charges. The total potential cost to the City including the optional period is $10,001,362 net of HST recoveries. The above cost calculations reflect a 3 percent Consumer Price Index adjustment applied annually to each year's cost after the initial one (1) year period.

    On the record

    The item as the City filed it