The decision
2022-07-19 · Toronto City Council · adopted
As filed
City Council on July 19, 20, 21 and 22, 2022, adopted the following: 1. City Council approve the Project Agreement and income participation model governance approach set out in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, and the proposed Project Term Sheet set out in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, for the Enwave Geothermal District Energy System - Bloor Kipling; and a.
Show the rest of As filed, 3,083 more characters as filed
authorize the Executive Director, Corporate Real Estate Management, or designate, to negotiate and enter into a Customer Term Sheet and a Customer Agreement between the City of Toronto and Enwave Energy Corporation or its affiliate to provide heating and cooling to the Etobicoke Civic Center, based on the terms and conditions in Schedule B of the Project Term Sheet in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, that are acceptable to the Executive Director, Corporate Real Estate Management and in a form satisfactory to the City Solicitor; b. authorize the Executive Director, Corporate Real Estate Management to provide all City payments required by the Customer Agreement and the Project Agreement, once executed, including without limitation the Upfront Payment for Hot and Chilled Water, the Fixed Charge for Hot and Chilled Water, and the Consumption Charge for Hot and Chilled Water, all as further described in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, with subsequent payments to be made to Enwave Energy Corporation on a payment schedule agreed upon by the City and Enwave Energy Corporation; c. authorize the Deputy City Manager, Corporate Services, or designate to negotiate and enter into such leases, licenses, easements and other agreements as may be required to convey to Build Toronto Incorporated or its subsidiary such lease, license, easement or other interests as may be required to give effect to the transactions contemplated in the Project Term Sheet in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, and the Project Agreement in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, on terms and conditions acceptable to the Deputy City Manager, Corporate Services, in consultation with the Executive Director, Corporate Real Estate Management, and in a form satisfactory to the City Solicitor; and d. authorize the Deputy City Manager, Corporate Services to transfer at nominal value the lease, license, easement and other interests described in Part 1.c. above to Build Toronto Inc. or its subsidiary. 2. City Council authorize the public release of Confidential Attachments 1 and 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, after the expiry of the Project Agreement, at the discretion of the Chief Executive Officer, CreateTO. Confidential Attachments 1 and 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO remain confidential at this time in accordance with the provisions of the City of Toronto Act, 2006, as they pertain to a proposed or pending acquisition or disposition of property belonging to the City, or one of its Agencies, or Corporations. Confidential Attachments 1 and 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO will be made public after the expiry of the Project Agreement, at the discretion of the Chief Executive Officer, CreateTO.
On the agenda
As the city filed it
At its meeting on June 20, 2022, the Board of Directors of CreateTO considered item RA32.1 and RA32.1a and made recommendations to City Council. Summary from CreateTO report (June 6, 2022): The City of Toronto signed a joint development agreement with Enwave Energy Corporation on April 4, 2018 at the direction of City Council after selecting Enwave in a competitive process aimed at finding a revenue partner to deliver district energy systems across Toronto at little risk to the City.
Show the rest of As the city filed it, 879 more characters as filed
The joint development agreement provided Enwave certain preferred rights in respect of opportunities for a joint development and operation of district energy systems with the City of Toronto. Such systems include a central heating and cooling plant including geothermal or other renewable energy sources that services a group of buildings through a distributed pipe network. At its meeting on June 20, 2022 the Built Toronto Inc. Board of Directors will be considering a Project Term Sheet (the "Term Sheet") which Management has negotiated with the Enwave. The purpose of this report is to advise the Board that, subject to the decision of the Build Toronto Inc. Board of Directors, the Chief Executive Officer will provide a further report to the June 20, 2022 CreateTO Board meeting with additional information, and a recommendation to City Council on the proposed Term Sheet.
Staff recommended
The Board of Directors of CreateTO recommends that: 1. City Council endorse the proposed Project Agreement and income participation model and related Project Term sheet outlined in the report (June 13, 2022) from the Chief Executive Officer, CreateTO and: a. Authorize the Deputy City Manager, Corporate Services, or designate, to negotiate and enter into a Customer Term Sheet and a Customer Agreement between the City of Toronto and Enwave Energy Corporation or its affiliate to provide heating and cooling to the Etobicoke Civic Center, based on the terms and conditions in Schedule "B" of the Project Term Sheet that are acceptable to the Executive Director, Corporate Real Estate Management and in a form acceptable to the City Solicitor.
Show the rest of Staff recommended, 1,662 more characters as filed
b. Authorize the Executive Director, Corporate Real Estate Management to provide all City payments required by the executed Customer Agreement and the executed Project Agreement, including without limitation the Upfront Payment for Hot and Chilled Water, the Fixed Charge for Hot and Chilled Water, and the Consumption Charge for Hot and Chilled Water, all as further described in the report (June 13, 2022) from the Chief Executive Officer, CreateTO with subsequent payments to be made to Enwave Energy Corporation on a payment schedule agreed upon by the City and Enwave Energy Corporation. 2. City Council authorize the Deputy City Manager, Corporate Services, or designate to negotiate and enter into such leases, licenses, easements and other agreements as may be required to convey to Build Toronto Inc. or its subsidiary such lease, license, easement or other interests as may be required to effect the transactions contemplated in the Project Term Sheet and the Project Agreement, on terms and conditions acceptable to Deputy Director, Corporate Services, in consultation with the Executive Director, Corporate Real Estate Management, and in a form satisfactory to the City Solicitor. 3. City Council authorize the Deputy City Manager, Corporate Services to transfer at nominal value the lease, license, easement and other interests described in (2) above to Build Toronto Inc. or its subsidiary. 4. City Council authorize the public release of Confidential Attachments 1 and 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, after the expiry of the Project Agreement, at the discretion of the Chief Executive Officer, CreateTO.
Considered
2022-07-04 · General Government and Licensing Committee · amended
Decision as filed
The General Government and Licensing Committee recommends that: 1. City Council approve the Project Agreement and income participation model governance approach set out in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, and the proposed Project Term Sheet set out in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, for the Enwave Geothermal District Energy System - Bloor Kipling; and a.
Show the rest of Decision as filed, 2,509 more characters as filed
Authorize the Executive Director, Corporate Real Estate Management, or designate, to negotiate and enter into a Customer Term Sheet and a Customer Agreement between the City of Toronto and Enwave Energy Corporation or its affiliate to provide heating and cooling to the Etobicoke Civic Center, based on the terms and conditions in Schedule "B" of the Project Term Sheet in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, that are acceptable to the Executive Director, Corporate Real Estate Management and in a form satisfactory to the City Solicitor; b. Authorize the Executive Director, Corporate Real Estate Management to provide all City payments required by the Customer Agreement and the Project Agreement, once executed, including without limitation the Upfront Payment for Hot and Chilled Water, the Fixed Charge for Hot and Chilled Water, and the Consumption Charge for Hot and Chilled Water, all as further described in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, with subsequent payments to be made to Enwave Energy Corporation on a payment schedule agreed upon by the City and Enwave Energy Corporation; c. Authorize the Deputy City Manager, Corporate Services, or designate to negotiate and enter into such leases, licenses, easements and other agreements as may be required to convey to Build Toronto Incorporated or its subsidiary such lease, license, easement or other interests as may be required to give effect to the transactions contemplated in the Project Term Sheet in Confidential Attachment 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, and the Project Agreement in Confidential Attachment 1 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, on terms and conditions acceptable to Deputy City Manager, Corporate Services, in consultation with the Executive Director, Corporate Real Estate Management, and in a form satisfactory to the City Solicitor; and d. Authorize the Deputy City Manager, Corporate Services to transfer at nominal value the lease, license, easement and other interests described in Recommendation 1c above to Build Toronto Inc. or its subsidiary. 2. City Council authorize the public release of Confidential Attachments 1 and 2 to the report (June 13, 2022) from the Chief Executive Officer, CreateTO, after the expiry of the Project Agreement, at the discretion of the Chief Executive Officer, CreateTO.
2022-07-19 · Toronto City Council · adopted
On the record
More from this meeting
- Supplementary Report - No Fault Grant for Basement Flooding DamagesFiled record
- Apportionment of Property Taxes - July 4, 2022 HearingFiled record
- Cancellation, Reduction or Refund of Property Taxes - July 4, 2022 HearingFiled record
- Amendment to Contract 47023290 with CBCI Telecom Canada Incorporated for the Supply, Delivery, Installation and Warranty of Audio-Visual related Products and ServicesFiled record
- Amendment to Blanket Contract Number 47022854 with Geotab Incorporated for the Provision of Telematics SolutionFiled record