The filed record
Getting the Gardiner Right: Moving Forward with a New Study on Better Options for the Gardiner East - by Councillor Josh Matlow, seconded by Councillor Amber Morley
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-05-10 · Toronto City Council · not adopted
As filed
City Council on May 10, 11 and 12, 2023, did not adopt Item DM6.4.
The vote
Adopt Item as Amended · Lost, 10-15
The whole record, all 25 members
- Alejandra BravoFor
- Amber MorleyFor
- Anthony PerruzzaAgainst
- Ausma MalikFor
- Brad BradfordAgainst
- Chris MoiseFor
- Dianne SaxeAgainst
- Frances NunziataAgainst
- Gary CrawfordAgainst
- Gord PerksFor
- Jamaal MyersFor
- James PasternakAgainst
- Jaye RobinsonAgainst
- Jennifer McKelvieAgainst
- Jon BurnsideAgainst
- Josh MatlowFor
- Lily ChengAgainst
- Michael ThompsonAgainst
- Mike ColleFor
- Nick MantasAgainst
- Paul AinslieFor
- Paula FletcherFor
- Shelley CarrollAgainst
- Stephen HolydayAgainst
- Vincent CrisantiAgainst
Every name opens that member’s record.
On the agenda
As the city filed it
No construction on the Gardiner East of Cherry street is scheduled to being until 2026. Moreover, Staff revealed in committee that the current cost estimate provided to Council last month does not include inflation or ongoing maintenance costs. This represents a potential jump in costs of hundreds of millions of dollars over the original 2016 estimate. While this delay and cost escalation is frustrating for residents, there is time for the City to re-evaluate the decision made to rebuild this least-used section of the Gardiner as an elevated expressway.
Show the rest of As the city filed it, 444 more characters as filed
It is incumbent upon Council to explore the feasibility of a plan that could maintain the connection between the DVP and Gardiner with a new road on the ground, or in another configuration, that could save hundreds of millions of dollars. According to a report done by Colliers for the Globe & Mail, a new configuration could also open up over 5 acres of City land with a value of $450M with enough space to build 8,000 homes for 15,000 people.
Staff recommended
Councillor Josh Matlow, seconded by Councillor Amber Morley, recommends that: 1. City Council request the General Manager, Transportation Services, to temporarily pause entering the City of Toronto into new contractual obligations regarding the Gardiner East of Jarvis, given that no new construction is scheduled until 2026, to allow for a comprehensive report, in consultation with the City Planning, Housing Secretariat, Parks, Forestry and Recreation, Waterfront Toronto, and CreateTO, is provided to the Infrastructure and Environment Committee, including: a.
Show the rest of Staff recommended, 552 more characters as filed
updated costs for the construction of the "Hybrid" and "Boulevard" options that consider inflation and supply chain issues; b. updated lifecycle maintenance costs of the "Hybrid" and "Boulevard" options that consider inflation and supply chain issues; c. a detailed analysis of the land value and additional housing that could be realized by opting for the at-grade boulevard; and d. contemplation of any alternative option that maximizes existing investment and achieves a Hybrid that opens up more City land and minimizes lifecycle maintenance costs.
On the record
More from this meeting
- Introduction of General Bills and Confirming BillsFiled record
- Ombudsman Toronto 2022 Annual ReportFiled record
- Claim to Recover Damages - Toronto Police Service Data CentreFiled record
- Letter of Intent between the City and Maple Leaf Sports and Entertainment regarding the 2026 World CupFiled record
- Supporting Small Businesses: Calling on the Federal Government to Forgive a Portion of the Canada Emergency Business Account Loans - by Councillor Paula Fletcher, seconded by Councillor Alejandra BravoFiled record
- Call to OrderFiled record