The decision
2023-09-15 · Exhibition Place · adopted
As filed
The Board of Governors of Exhibition Place: 1. Concurred with the action taken by the Vice Chair, Board of Governors of Exhibition Place and the Chief Executive Officer, Exhibition Place in approving the award of Contract No. 23-075-37525 (RFT No. EP108-2023) to Superior Boiler Works and Welding Limited for the Generators Replacement at Mid-Arch and Horse Palace in the amount of $715,244.16 which includes a cash allowance
Show the rest of As filed, 140 more characters as filed
of $50,000.00 but excludes Harmonized Sales tax; this being the lowest acceptable tender submission received following the public tendering.
On the agenda
As the city filed it
This report recommends approving a contract with Superior Boiler Works and Welding Limited ("Superior") for the Generators Replacement at Mid-Arch and Horse Palace. The tender call was issued on June 14, 2023 through Exhibition Place Purchasing and Materials Stores via Bonfire Online Procurement System, and the recommendation is to award the contract to the lowest compliant bidder meeting tender requirements and specifications within the available budget.
Show the rest of As the city filed it, 591 more characters as filed
This project is time sensitive to meet stakeholders and operational requirements, the generators in these buildings are approximately 40 years old and require extensive ongoing service, replacement generators can have lead times of over a year and the work to replace them must be scheduled to avoid disruption of any show and events. On August 1, 2023, the Vice Chair of the Board in consultation with the Chief Executive Officer of Exhibition Place approved this contract award pursuant to their authority under the Board Financial By-law 2-18, Article X and seek concurrence of the Board.
Staff recommended
The Chief Executive Officer recommends that: 1. The Board concur with the action taken by the Vice Chair and Chief Executive Officer in approving the award of Contract No. 23-075-37525 (RFT No. EP108-2023) to Superior Boiler Works and Welding Limited for the Generators Replacement at Mid-Arch and Horse Palace in the amount of $715,244.16 which includes a cash allowance of $50,000.00 but excludes HST; this being the lowest acceptable tender submission received following the public tendering.
On the record
More from this meeting
- Lighting Retrofit at Various BuildingsFiled record
- Elevators Modernization at Enercare Centre and Beanfield CentreFiled record
- Fan Motors Replacement at Enercare Centre - Phase IIFiled record
- Participation in the AIPC Canadian Academy 2023 ConferenceFiled record
- Implementation of Virtual Reality Technology at Beanfield CentreFiled record
- Billboard Sign Agreement - Astral Media Outdoor L.P.Filed record