Construction Manager - Community Conservation Centre (TZC3) - NRFP Award

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2023-04-20 · Toronto Zoo · adopted

As filed

The Board of Management of the Toronto Zoo: 1. Approved the award of the Negotiated Request for Proposals NRFP-08 - Construction Manager for Conservation Centre project to PCL Constructors Canada Inc., in the amount of $2,713,909.15, excluding applicable taxes.

On the agenda

As the city filed it

This report recommends the award of the Negotiated Request for Proposals for Construction Manager for the Community Conservation Centre project.

Staff recommended

The Chief Executive Officer, Toronto Zoo, recommends that: 1. The Board of Management of the Toronto Zoo approve the award of the Negotiated Request for Proposals NRFP-08 - Construction Manager for Conservation Centre project to PCL Constructors Canada Inc. in the amount of $2,713,909.15, excluding applicable taxes.