908 St. Clair Avenue West - Construction Staging Area
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-01-24 · Toronto and East York Community Council · adopted
As filed
The Toronto and East York Community Council: 1. Authorized the closure of the west sidewalk and a 5.5 metre wide portion of the southbound curb lane on Alberta Avenue, between a point 7.5 metres north of St. Clair Avenue West and a point 73 metres further north, from January 31, 2024 to January 3, 2026 inclusive to accommodate construction staging operations. 2. Directed the applicant to sweep the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of As filed, 2,840 more characters as filed
3. Directed the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act. 4. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 6. Directed the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 10. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 11. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 12. Directed the applicant to cooperate with and provide all necessary assistance to the City engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 13. Directed that Alberta Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.
On the agenda
As the city filed it
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. 908 St. Clair West Limited Partnership is constructing a 12-storey residential condominium building at 908 St. Clair Avenue West. The site is located at the north-west corner of St. Clair Avenue West and Alberta Avenue. Transportation Services is requesting approval to close the west sidewalk, and a 5.5 metre wide portion of the west side southbound traffic lane on Alberta Avenue for a period of 23 months, from January 31, 2024 to January 3, 2026 to facilitate construction staging operations.
Show the rest of As the city filed it, 235 more characters as filed
Pedestrian movements on the west side of Alberta Avenue abutting the site will be restricted and pedestrians will be directed to the east side sidewalk of Alberta Avenue. Two-way traffic operations will be maintained on Alberta Avenue.
Staff recommended
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the closure of the west sidewalk and a 5.5 metre wide portion of the southbound curb lane on Alberta Avenue, between a point 7.5 metres north of St. Clair Avenue West and a point 73 metres further north, from January 31, 2024 to January 3, 2026 inclusive to accommodate construction staging operations.
Show the rest of Staff recommended, 3,417 more characters as filed
2. Toronto and East York Community Council direct the applicant to sweep the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 3. Toronto and East York Community Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 4. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. Toronto and East York Community Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 8. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 10. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 11. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 12. Toronto and East York Community Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 13. Toronto and East York Community Council direct that Alberta Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- Naming of an existing Public Lane North of St. Clair Avenue West, extending between Raglan Avenue and Vaughan RoadFiled record
- 7 Laxton Avenue - Official Plan and Zoning By-law Amendment Applications - Decision Report - ApprovalFiled record
- 440, 444, 450 and 462 Front Street West; 425, 439, 441 and 443 Wellington Street West; 6-18 Spadina Avenue and 1 and 19 Draper Street - The Well - Extension of Part Lot Control Exemption Application - ApprovalFiled record
- 914 Bathurst Street - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 33 Davisville Avenue and 60 Balliol Street - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 111 and 141 Davisville Avenue - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record