400-420 King Street West - Construction Staging Area Time Extension
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2024-04-17 · Toronto City Council · adopted
As filed
City Council on April 17 and 18, 2024, adopted the following: 1. City Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane from September 1, 2024 to December 31, 2026. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of As filed, 404 more characters as filed
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 4. City Council direct that King Street West be returned to its pre-construction traffic regulations when the project is completed.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on King Street West City Council approval of this report is required. TMG Builders is constructing a 49-storey mixed use residential condominium development at 400-420 King Street West. The north sidewalk on King Street West and the east sidewalk on Charlotte Street is currently closed for construction staging operations. City Council, at its meeting on December 15, 2021, approved the closure of the east sidewalk on Charlotte Street until December 31, 2026 and the north sidewalk and a 2.6 metre-wide portion of the westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east, from July 1, 2022 to August 31, 2024.
Show the rest of As the city filed it, 266 more characters as filed
Transportation Services is requesting authorization to extend the duration of the construction staging area on King Street West for an additional 28 months, from September 1, 2024 to December 31, 2026 to allow for the construction of the development to be completed.
Staff recommended
The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from September 1, 2024 to December 31, 2026. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of Staff recommended, 404 more characters as filed
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 4. City Council direct that King Street West be returned to its pre-construction traffic regulations when the project is completed.
Considered
2024-04-03 · Toronto and East York Community Council · adopted
Decision as filed
The Toronto and East York Community Council recommends that: 1. City Council authorize the continuation of the closure of the north sidewalk and westbound curb lane on King Street West, between Charlotte Street and a point 66 metres east and provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from September 1, 2024 to December 31, 2026. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
Show the rest of Decision as filed, 404 more characters as filed
3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor 4. City Council direct that King Street West be returned to its pre-construction traffic regulations when the project is completed.
2024-04-17 · Toronto City Council · adopted
On the record
More from this meeting
- Naming of an existing Public Lane North of St. Clair Avenue West, extending between Raglan Avenue and Vaughan RoadFiled record
- 2453-2469 Bloor Street West - Zoning Amendment - Decision Report - ApprovalFiled record
- 350-396 Queens Quay West - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 350 Bloor Street East - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 171-175 Lowther Avenue - Official Plan and Zoning By-law Amendment Application - Decision Report - ApprovalFiled record
- 931 Yonge Street - Zoning By-law Amendment Application - Decision Report - ApprovalFiled record