Amendment to Purchase Order Number 6052669 EBC Bessac Canada (FSPSTT) Joint Venture for the Construction of the Fairbank Silverthorn Storm Trunk Tunnel and Micro-Tunneled Storm Collectors for Basement Flooding Protection Program Study Area 3

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2025-04-07 · General Government Committee · adopted

As filed

The General Government Committee: 1. In accordance with section 71-11.1C of the City of Toronto Municipal Code Chapter 71 (Financial Control Bylaw), authorized the amendment of Purchase Order 6052669 with EBC Bessac Canada (FSPSTT) Joint Venture, for the Construction of the Fairbank Silverthorn Storm Trunk Tunnel and Micro-Tunneled Storm Collectors for Basement Flooding Protection Program Study Area 3 by increasing the

Show the rest of As filed, 335 more characters as filed

value by $6,000,000 net of all applicable taxes and charges ($6,105,600 net of Harmonized Sales Tax recoveries), from $202,217,400 net of all applicable taxes and charges ($205,776,426 net of Harmonized Sales Tax recoveries) to $208,217,400 net of all applicable taxes and charges ($211,882,026 net of Harmonized Sales Tax recoveries).

On the agenda

As the city filed it

This report requests authority to amend Purchase Order Number 6052669, awarded under Doc2793902914, issued to EBC Bessac Canada (FSPSTT) Joint Venture, for construction of the Fairbank Silverthorn Storm Trunk Tunnel and Micro-Tunneled Storm Collectors in the Basement Flooding Protection Program Study Area 3, Assignment Number 3-03, which is bounded by Black Creek Drive, Vaughan Road, Rogers Road and Castlefield Avenue.

Show the rest of As the city filed it, 1,029 more characters as filed

The requested amendment is for settlement of claims related to additional construction services. The total value of the Purchase Order Amendment being requested is $6,000,000 net of all applicable taxes and charges ($6,105,600 net of Harmonized Sales Tax recoveries), revising the current Purchase Order value from $202,217,400 net of all applicable taxes and charges ($205,776,426 net of Harmonized Sales Tax recoveries) to $208,217,400 net of all applicable taxes and charges ($211,882,026 net of Harmonized Sales Tax recoveries). Approximately half of the requested amendment, $2,999,180.87 net of all applicable taxes and charges ($3,051,966.45) net of Harmonized Sales Tax recoveries), is allocated for the settlement of claims related to additional construction services. These costs arose from unforeseen challenges, including delayed utility relocations by Bell, Rogers, and Toronto Hydro, access constraints imposed by Metrolinx, and modifications to the adit method to accelerate work and minimize community disruption.

Staff recommended

The Chief Engineer and Executive Director, Engineering and Construction Services, and the Chief Procurement Officer recommend that: 1. The General Government Committee, in accordance with section 71-11.1C of the City of Toronto Municipal Code Chapter 71 (Financial Control Bylaw), grant authority to amend Purchase Order 6052669 with EBC Bessac Canada (FSPSTT) Joint Venture, for the Construction of the Fairbank Silverthorn

Show the rest of Staff recommended, 462 more characters as filed

Storm Trunk Tunnel and Micro-Tunneled Storm Collectors for Basement Flooding Protection Program Study Area 3 by increasing the value by $6,000,000 net of all applicable taxes and charges ($6,105,600 net of Harmonized Sales Tax recoveries), from $202,217,400 net of all applicable taxes and charges ($205,776,426 net of Harmonized Sales Tax recoveries) to $208,217,400 net of all applicable taxes and charges ($211,882,026 net of Harmonized Sales Tax recoveries).

    On the record