Provincial LRT Program - Line 5 Eglinton Update

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2025-06-23 · Toronto Transit Commission Board · adopted

As filed

The TTC Board: 1. Received this report for information. 2. Authorized that the information contained in Confidential Attachment 1 remain confidential, as it contains information supplied in confidence to the TTC by a Crown agency, Metrolinx.

On the agenda

As the city filed it

The TTC, Metrolinx and Crosslinx Transit Solution continue to work together to get Line 5 ready for revenue service. On June 16, 2025, train operations were transferred into the TTC's Transit Control Centre from a temporary control centre as testing, training and construction continue. There are, however, still more phases and milestones to be safely completed before final handover to the TTC occurs. Handover comes only

Show the rest of As the city filed it, 241 more characters as filed

after substantial completion is achieved, which requires that the Project's Independent Certifier has certified that CTS has demonstrated the successful delivery of Line 5 in accordance with the requirements set out in its Project Agreement.

Staff recommended

It is recommended that the TTC Board: 1. Receive this report for information. 2. Authorize that the information contained in Confidential Attachment 1 remain confidential, as it contains information supplied in confidence to the TTC by a Crown agency, Metrolinx.