development
Upper Yonge Daycare Centre rehabilitation cost overruns approved; structural work adds $1.2 million
City Council approved additional spending of $1.2 million to address unforeseen structural deficiencies discovered during rehabilitation of the heritage-designated Upper Yonge Village Daycare Centre on St. Clement Avenue. The daycare serves the Upper Yonge community and was limited in pre-construction assessment because it remained operational. The overruns cover additional design services and structural remediation work needed to meet code compliance and ensure the facility's long-term viability.
Who did what
- Councillor Jon Burnside (Ward 16, Don Valley East) movedMoved the amendment to approve both purchase order increases
Also in this item
• The daycare centre, originally constructed in 1908 and heritage-designated, was limited in pre-construction assessment because it remained fully operational during the investigation and design phases, preventing intrusive structural evaluation that would have discovered the deficiencies earlier.
The journey
Decision
Amendment approved: Purchase Order 6048204 with Read Jones Christoffersen increased by $251,266 (34 per cent increase) for additional design and contract administration services; Purchase Order 6056498 with Pegah Construction increased by $969,257 (16 per cent increase) for structural remediation and remaining construction work. Total combined increase: approximately $1.22 million.