Amendment to Bennett Mechanical contract for Ashbridges Bay Treatment Plant adds $4.9 million and delays completion to 2028
General Government Committee approved a $4.9 million amendment to Bennett Mechanical Installations' contract for wastewater treatment infrastructure upgrades at Ashbridges Bay, plus $3.1 million in additional engineering services from GHD Limited. The amendment covers unforeseen site conditions and delays, pushing the project completion from December 2026 to March 2028. This is a routine capital project cost overrun within a multi-year infrastructure commitment.
From the floor
“I have a mover. Councilor Chang. All in favour.”An accountability officer
Also in this item
• Project completion delayed 15 months, from December 2026 to March 2028, due to unforeseen site conditions and construction delays.
• Total contract value increase of $8.1 million across both vendors (Bennett Mechanical and GHD engineering), representing approximately 10% of the original combined contract value.
The journey
Decision
Amendment approved. Bennett Mechanical contract increased from $75.3 million to $80.2 million ($4.9 million net addition); GHD engineering contract increased from $4.9 million to $8.0 million ($3.1 million net addition). Both delivery dates extended from December 31, 2026 to March 31, 2028.