City Council to award contract to replace raw water pumps and travelling screens at Island Water Treatment Plant
City Council will consider awarding a $34 million construction contract to Alberici Constructors Ltd. for replacement of equipment at the Island Water Treatment Plant, along with additional consulting services and a schedule extension to 2029-2031. The project expands scope to include control systems and instrumentation while maintaining continuous water service during construction.
Also in this item
• Project schedule extended from 33 months to accommodate continuous operation of Island Water Treatment Plant and Deep Lake Water Cooling services during construction, delaying completion to 2029-2031
• Scope expanded to include additional instrumentation, control systems, equipment testing, and repairs beyond original specification
• Project cost reallocation of $10.07 million within Toronto Water's approved capital budget for 2026 and 2027-2035 plan requested