Amendment to engineering contract for R.L. Clark Water Treatment Plant standby generation project

Toronto Water seeks $1.04 million to extend engineering design work on the R.L. Clark treatment plant's standby power and new building, following a four-year project pause and subsequent reactivation. The work addresses design changes driven by equipment manufacturer updates, regulatory changes, and labour cost increases, with completion now expected in mid-2029.

adoptedGeneral Government Committee · Mon, Jul 20

Also in this item

Project paused in 2022 due to capital budget constraints; reactivated in 2026 after four-year gap.

Design changes required by manufacturer discontinuing supported Selective Catalytic Reduction system.

Delivery extension to June 29, 2029 spans three years from reactivation.

The journey

Mon, Jul 20 · General Government Committee · adopted

Decision

Authority granted to amend Purchase Order 6048845 with CH2M HILL Canada Limited, increasing the contract value from $3,317,372 to $4,356,960 and extending the delivery date to June 29, 2029.

On video

Jump to this item in the meeting video

Why is this story here?
ContainedA single municipal facility's design engineering contract amendment: genuine financial and scheduling decision ($1M addition, three-year extension), but bounded to one project within Toronto Water's capital program. Hard to reverse without cost, but does not change institutional capacity or constrain future councils. Meets real-but-contained test: something happens, future council could redirect or delay without a serious fight.Invisible to residentsNo resident experiences the engineering design phase of a water treatment plant. The eventual infrastructure outcome (standby power, new building) will matter to operational resilience, but the design work itself is internal procurement with no present-week effect on any household. This is an internal administration decision.

Stories are ordered by how much weight a decision carries and how directly it reaches daily life. They rise as a decision date approaches and fall as they age.

Share this

Official title: Amendment to Purchase Order 6048845 with CH2M HILL Canada Limited for Design Engineering Services for the R.L. Clark Water Treatment Plant Standby Generation and New Building Project · meeting video