NY33.26amended
Metrolinx’s Ontario Line Construction within the North York District - Second Quarter 2026 Update
City Council, at its meeting in December 2025, directed the Transit Expansion Division to report to North York Community Council by second quareter 2026 with an update on Metrolinx's Ontario Line construction within North York. The purpose of this report is to provide updates and project details on the three Ontario Line stations and the elevated guideway located in North York, and includes updates on: - Construction Updates and Impacts; - Metrolinx's Community Benefits and Supports Program; and, - Public Engagement.
North York Community Council: 1. Requested the General Manager, Transportation Services, in consultation with the Executive Director, Transit Expansion, work with Metrolinx to develop a plan to manage rush hour traffic along Brentcliffe Road from Wicksteed Avenue to Eglinton Avenue East, caused by volume impacts resulting from the Beth Nealson Drive long term closure, including but not limited to measures such as the hiring of traffic agents.
Staff recommendation as filed
The Executive Director, Transit Expansion recommends that: 1. North York Community Council receive this report for information.
NY33.27deferred
This report provides an overview of Metrolinx's planned construction activities for the Yonge North Subway Extension Steeles Station at the intersection of Yonge Street and Steeles Avenue. The report outlines the key construction stages, anticipated timelines, and associated long-term temporary lane closures, turning restrictions, pedestrian and cycling impacts, transit adjustments, and access considerations required to facilitate construction. Construction of Steeles Station requires excavation of a large underground station box within the existing Yonge Street right-of-way. Due to the scale and location of the work, it is not feasible to maintain traffic operations within the existing roadway during key stages of construction. To maintain north-south connectivity, Yonge Street will be temporarily realigned onto a newly constructed diversion road west of its existing alignment. Following implementation of the diversion road, Yonge Street, between Steeles Avenue and Madawaska Avenue, will be fully closed to vehicular traffic during the main construction phase. This report seeks City Council approval for the temporary full closure of Yonge Street, the temporary designation of the diversion road as a public highway and associated temporary traffic and pedestrian by-law amendments required to support construction of Steeles Station. In addition, this report seeks to extend the delegated authority of the General Manager, Transportation Services, to implement long-term temporary road closures and associated traffic modifications to December 31, 2030, to allow flexibility to respond to refinements in construction staging and scheduling without the need for subsequent reports to Council. Approval of the recommendations in this report will enable Metrolinx to proceed with critical construction activities while ensuring that impacts to the transportation network, local communities, and road users are effectively managed through coordinated traffic control, access management, and construction mitigation measures.
North York Community Council: 1. Deferred the consideration of Item NY33.27 to the July 7, 2026 meeting of North York Community Council, to allow Metrolinx additional time to undertake community consultation and engagement, in collaboration with the local Councillor's office, regarding the proposed construction staging, traffic impacts, pedestrian and business access, and associated mitigation measures related to the Yonge North Subway Extension Steeles Station construction works.
Staff recommendation as filed
The Interim Deputy General Manager, Transportation Services recommends that: Steeles Station: Public Laneway (Ln E Yonge S Steeles): 1. City Council approve the temporary closure of the public laneway (Ln E Yonge S Steeles), between Steeles Avenue and Nipigon Avenue, from June 25, 2027 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. Yonge Street Detour Road: 2. City Council authorize public highway designation and dedicate the lands, described as Parts 1, 2, 5, 7, 8, and 9 on Reference Plan 66R-34930, being part of PIN 10139-0289 (LT) set out as Attachment 1 of the report (May 7, 2026), to be known as "Yonge Street Diversion Road", to become effective upon the transfer to the City of the required interest in lands forming the diversion road and the registration of the highway dedication bylaw on those lands. 3. City Council authorize public highway designation and dedicate the lands, described as Part 1 on Reference Plan 66R-34927, being part of PIN 10139-0230 (LT) set out as Attachment 2 of the report (May 7, 2026), to be known as "Yonge Street Diversion Road", to become effective upon the transfer to the City of the required interest in lands forming the diversion road and the registration of the highway dedication bylaw on those lands. 4. City Council authorize public highway designation and dedicate the lands, described as Part 1 on Reference Plan 66R-34408, being part of PIN 10139-0230 (LT) set out as Attachment 3 of the report (May 7, 2026), to be known as "Yonge Street Diversion Road", to become effective upon the transfer to the City of the required interest in lands forming the diversion road and the registration of the highway dedication bylaw on those lands. 5. City Council prohibit stopping on both sides of the Yonge Street Diversion Road, between Steeles Avenue and Madawaska Avenue, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 6. City Council authorize the installation of temporary traffic control signals at the intersection of Yonge Street Diversion Road and Athabaska Avenue, from December 10, 2026 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 7. City Council designate a 40 kilometres per hour speed limit on Yonge Street Diversion Road, between Steeles Avenue and Madawaska Avenue, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. Yonge Street: 8. City Council designate a 40 kilometres per hour speed limit on Yonge Street, between Steeles Avenue and Madawaska Avenue, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 9. City Council prohibit stopping at all times on both sides of Yonge Street, between Steeles Avenue and Madawaska Avenue, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 10. City Council approve the temporary closure of the west sidewalk to pedestrian traffic on Yonge Street, between Madawaska Avenue and Athabaska Avenue, from December 10, 2026 to June 24, 2027, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 11. City Council approve the temporary closure of the west sidewalk to pedestrian traffic on Yonge Street, between Nipigon Avenue and Athabaska Avenue, from June 25, 2027 to January 19, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 12. City Council approve the temporary closure of the west sidewalk to pedestrian traffic on Yonge Street, between Steeles Avenue and Athabaska Avenue, from January 20, 2028 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 13. City Council approve the temporary closure of the east sidewalk to pedestrian traffic on Yonge Street, between Abitibi Avenue and Otonabee Avenue, from September 12, 2028 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 14. City Council authorize the temporary closure of the existing easterly northbound and westerly southbound reserved lanes to vehicular traffic on Yonge Street, between Steeles Avenue and Madawaska Avenue, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 15. City Council approve the temporary closure of the east crosswalk to pedestrian traffic on Yonge Street at Athabaska Avenue, from September 12, 2028 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 16. City Council approve the temporary closure of the northbound and southbound curb lanes to vehicular traffic on Yonge Street, between Steeles Avenue and Madawaska Avenue, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 17. City Council approve the temporary full closure to vehicular traffic on Yonge Street, between Steeles Avenue and Madawaska Avenue, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 18. City Council prohibit northbound left-turn movement at the intersection of Yonge Street and Athabaska Avenue, from June 25, 2027 to January 19, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 19. City Council prohibit northbound right-turn, southbound left-turn and eastbound through traffic movements at the intersection of Yonge Street and Athabaska Avenue, from September 12, 2028 to March 16, 2029, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 20. City Council prohibit westbound right-turns on red signal at the intersection of Yonge Street and Athabaska Avenue, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. Yonge Street and Steeles Avenue: 21. City Council authorize the alteration of the south-west corner of Yonge Street and Steeles Avenue, to remove the east-to-southbound right-turn channel. 22. City Council approve the temporary closure of the south crosswalk to pedestrian traffic on Yonge Street at Steeles Avenue, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 23. City Council prohibit eastbound, westbound, northbound, and southbound right-turns on red signal at the intersection of Yonge Street and Steeles Avenue, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. Side Streets: 24. City Council approve the temporary closure to vehicular traffic on Nipigon Avenue at Yonge Street, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 25. City Council approve the temporary closure to vehicular traffic on Abitibi Avenue at Yonge Street, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 26. City Council approve the temporary closure to vehicular traffic on Otonabee Avenue at Yonge Street, from September 12, 2028 to July 22, 2030, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 27. City Council approve the temporary closure to vehicular traffic on Athabaska Avenue at Yonge Street, from September 12, 2028 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. Steeles Avenue: 28. City Council approve the temporary closure of the westbound right-turn lane to vehicular traffic on Steeles Avenue, between Yonge Street and a point approximately 85 metres, from June 25, 2027 to September 11, 2028, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 29. City Council approve the temporary closure of the westbound curb lane to vehicular traffic on Steeles Avenue, between a point approximately 200 metres west of Yonge Street and a point approximately 150 metres east of Yonge Street, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 30. City Council approve the temporary closure of the westbound median lane to vehicular traffic on Steeles Avenue, between Yonge Street and a point approximately 85 metres west of Yonge Street, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 31. City Council approve the temporary closure of the eastbound curb lane to vehicular traffic on Steeles Avenue, between a point approximately 305 metres west of Yonge Street and a point approximately 150 metres east of Yonge Street, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 32. City Council approve the temporary closure of the eastbound median lane to vehicular traffic on Steeles Avenue, between Yonge Street and a point approximately 200 metres west of Yonge Street, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 33. City Council approve the temporary closure of the two-way left-turn only lane to vehicular traffic on Steeles Avenue, between a point approximately 125 metres west of Yonge Street and a point approximately 180 metres further west, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 34. City Council designate a 40 kilometres per hour speed limit on Steeles Avenue, between Dumont Street and a point 360 metres west of Yonge Street, from June 25, 2027 to March 16, 2029, inclusive, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. 35. City Council prohibit stopping on Steeles Avenue, between Dumont Street and a point 360 metres west of Yonge Street, from June 25, 2027 to March 16, 2029, to facilitate construction of the Steeles Station as part of the Yonge North Subway Extension. General: 36. City Council authorize the appropriate City officials to take all steps necessary to implement the proposed dedications referred to in Recommendations 2, 3, and 4 above, including requesting the City solicitor to prepare and submit the relevant Bills and to pay any costs necessary to register the resultant by-laws, if required. 37. City Council authorize the General Manager, Transportation Services, to negotiate, enter into and execute an agreement with Metrolinx on terms and conditions satisfactory to the General Manager, Transportation Services, in relation to, among other things, the construction, maintenance, and warranty work of the diversion road, as well as to negotiate, enter into and execute any necessary agreements and documents, and take steps and measures necessary, on behalf of the City, to temporarily exercise the City's authority. 38. City Council authorize the General Manager, Transportation Services, in issuing any requisite permits to include additional permit terms and conditions as the General Manager, Transportation Services deems necessary and appropriate. 39. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary Bills to amend the appropriate City of Toronto Municipal Code and / or Chapters, and any Schedules to the Chapters, to reinstate the traffic and parking regulations to what they were immediately prior to the by-law amendments made in connection with the report (May 7, 2026) from the Interim Deputy General Manager, Transportation Services. 40. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary Bills to amend the effective date of any dedication by-law(s) and / or traffic and parking by-law(s) made in connection with the report (May 7, 2026) from the Interim Deputy General Manager, Transportation Services to, among other things, insert a specific effective date, in order to give effect to Recommendations 1 to 35, inclusive, above. 41. City Council authorize the City Solicitor to introduce the necessary Bills to give effect to City Council's decision and City Council authorize the City Solicitor to make any necessary clarifications, refinements, minor modifications, technical amendments, or by-law amendments as may be identified by the City Solicitor or the General Manager, Transportation Services in order to give effect to Recommendations 1 to 40, inclusive, above.
NY33.28adopted
Ianhall Road - U-Turn Prohibition
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is requesting approval to prohibit northwest-bound U-turn movements at all times on Ianhall Road, between Victory Drive and a point 95 metres northwest to improve traffic flow and safety for students and all road users in proximity to St. Raphael Catholic School.
North York Community Council: 1. Prohibited northwest bound U-turn movements at all times on Ianhall Road, between Victory Drive and a point 95 metres northwest.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. North York Community Council prohibit northwest bound U-turn movements at all times on Ianhall Road, between Victory Drive and a point 95 metres northwest.
NY33.29adopted
Shaftesbury Street - Parking Amendments
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending that parking be prohibited between 8:00 a.m. to 4:00 p.m., Monday to Friday on both sides of Shaftesbury Street, between Clifton Avenue and Combe Avenue. The proposed regulation will deter excessive long-term parking on the street and will improve vehicle movements by maintaining a clear passage for vehicles.
North York Community Council: 1. Prohibited parking in effect from 8:00 a.m. to 4:00 p.m., Monday to Friday, on both sides of Shaftesbury Street, between Clifton Avenue and Combe Avenue.
Staff recommendation as filed
The Director, Enforcement and Street Management, Transportation Services recommends that: 1. North York Community Council prohibit parking in effect from 8:00 a.m. to 4:00 p.m., Monday to Friday, on both sides of Shaftesbury Street, between Clifton Avenue and Combe Avenue.
NY33.30adopted
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. CBW Eglinton Phase #2 Inc., is constructing an eight-storey condominium building at 1886-1920 Eglinton Avenue West. The site is located on the north side of Eglinton Avenue West, between Shortt Street and Fairbank Avenue. By way of background, North York Community Council at its meeting on April 2, 2025, approved closure of the west sidewalk and the southbound traffic lane on Shortt Street, as well as full closure of Fairbank Village Lane abutting the site, from May 1, 2025 to July 1, 2026 to accommodate construction staging operations. The developer is now requesting an extension of the duration of the construction staging area on Shortt Street and Fairbank Village Lane. Due to delays resulting from severe winter conditions, supply chain disruptions, shortages of skilled labour, and site-related constraints, which collectively slowed or periodically halted construction activities and extended the overall project timeline. In view of the above, Transportation Services is requesting authorization to extend the duration of the construction staging area on Shortt Street and on Fairbank Village Lane for an additional 13 months, from July 2, 2026 to July 31, 2027 to allow for the construction of the development to be completed.
North York Community Council: 1. Authorized the continuation of the closure of the west sidewalk and the southbound traffic lane on Shortt Street, between Eglinton Avenue West and Fairbank Village Lane, from July 2, 2026 to July 31, 2027 inclusive. 2. Continued to authorize a full closure of Fairbank Village Lane, between Shortt Street and a point 45 metres west, from July 2, 2026 to July 31, 2027 inclusive. 3. Continued to designate Shortt Street, between Eglinton Avenue West and Fairbank Village Lane, as one-way for northbound traffic only, from July 2, 2026 to July 31, 2027 inclusive. 4. Continued to rescind the existing maximum 1-hour parking regulation in effect 8:00 a.m. to 6:00 p.m., Monday to Saturday, except public holidays, on the east side of Fairbank Avenue, between a point 26.5 metres north of Eglinton Avenue West and a point 7 metres further north. 5. Continued to rescind the existing permit parking regulation in effect 12:00 midnight to 6:00 a.m. on the east side of Fairbank Avenue, between Fairbank Village Lane and a point 7 metres north. 6. Continued to prohibit stopping at all times on the east side of Fairbank Avenue, between Fairbank Village Lane and a point 7 metres north. 7. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. Directed the applicant to continue to cooperate with and provide all necessary assistance to the City engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 10. Directed that Shortt Street and Fairbank Village Lane be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.
Staff recommendation as filed
The Director, Congestion and Network Management, Transportation Services recommends that: 1. North York Community Council authorize the continuation of the closure of the west sidewalk and the southbound traffic lane on Shortt Street, between Eglinton Avenue West and Fairbank Village Lane, from July 2, 2026 to July 31, 2027 inclusive. 2. North York Community Council continue to authorize a full closure of Fairbank Village Lane, between Shortt Street and a point 45 metres west, from July 2, 2026 to July 31, 2027 inclusive. 3. North York Community Council continue to designate Shortt Street, between Eglinton Avenue West and Fairbank Village Lane, as one-way for northbound traffic only, from July 2, 2026 to July 31, 2027 inclusive. 4. North York Community Council continue to rescind the existing maximum 1-hour parking regulation in effect 8:00 a.m. to 6:00 p.m., Monday to Saturday, except public holidays, on the east side of Fairbank Avenue, between a point 26.5 metres north of Eglinton Avenue West and a point 7 metres further north. 5. North York Community Council continue to rescind the existing permit parking regulation in effect 12:00 midnight to 6:00 a.m. on the east side of Fairbank Avenue, between Fairbank Village Lane and a point 7 metres north. 6. North York Community Council continue to prohibit stopping at all times on the east side of Fairbank Avenue, between Fairbank Village Lane and a point 7 metres north. 7. North York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 8. North York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 9. North York Community Council direct the applicant to continue to cooperate with and provide all necessary assistance to the City engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure within the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 10. North York Community Council direct that Shortt Street and Fairbank Village Lane be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.
NY33.31amended
83 Forest Heights Boulevard - Encroachment Appeal
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. The purpose of this report is for North York Community Council to consider an appeal submitted by the property owner of 83 Forest Heights Boulevard regarding their encroachment application. The encroachment consists of a wooden privacy fence that does not comply with City of Toronto Municipal Code Chapter 743, Streets and Sidewalks, Use Of. The property owner is seeking authority from North York Community Council to construct and maintain a wooden fence within the public right-of-way at 83 Forest Heights Boulevard, despite its non-compliance with the provisions of Chapter 743.
North York Community Council: 1. Refused the appeal of the encroachment agreement, and required that City lands currently encroached upon are restored to their previous condition.
Staff recommendation as filed
The Acting Director, Street Permits, Transportation Services recommends that: 1. North York Community Council authorize the General Manager of Transportation Services to enter into an encroachment agreement with the property owner of 83 Forest Heights Boulevard, to permit a wooden fence, subject but not limited to, the following conditions: a. The property owner will indemnify the City from and against all actions, suits, claims or demands and from all loss, costs, damages, and expenses that may result from such permission granted; b. The property owner shall, at their owner expense, maintain the fence in a state of good repair to the satisfaction of the General Manager of Transportation Services and will not make any additions or modifications to the encroachment beyond what is allowed under the terms of the Agreement; c. The property owner will accept such additional conditions as the City Solicitor or the General Manager of Transportation Services may deem necessary in the interest of the City; d. The property owner will remove the fence upon receiving written notice from Transportation Services to do so; e. The fence shall not include spikes or pointed elements; and f. The property owner will enter into an encroachment agreement with the City of Toronto, at the applicant's expense, and assume all liability and damages related to the encroachment.
NY33.32adopted
Erskine Avenue at Redpath Avenue - Parking Amendments
This report is about parking regulations for which Community Council has delegated authority from City Council to make a final decision. Transportation Services recommends that parking be prohibited at all times on the south side of Erskine Avenue, to support proposed geometric safety improvements and maintain vehicle maneuverability at the Erskine Avenue and Redpath Avenue intersection. The proposed changes align with the City's Midtown Infrastructure Implementation Strategy, City's Vision Zero Road Safety Plan and are planned to be constructed as part of the planned resurfacing of Erskine Avenue in 2026.
North York Community Council: 1. Prohibited parking at all times on the south side of Erskine Avenue, between Redpath Avenue and a point 49.5 metres east. 2. Prohibited parking at all times on the south side of Erskine Avenue, between Redpath Avenue and a point 21 metres west.
Staff recommendation as filed
The Acting Deputy General Manager, Transportation Services recommends that: 1. North York Community Council prohibit parking at all times on the south side of Erskine Avenue, between Redpath Avenue and a point 49.5 metres east. 2. North York Community Council prohibit parking at all times on the south side of Erskine Avenue, between Redpath Avenue and a point 21 metres west.
NY33.33adopted
7 St. Dennis Drive - Construction Staging Area
As St. Dennis Drive is classified as a collector street, City Council approval of this report is required. Osmington Gerofsky Development Corp. is constructing a 37-storey residential building at 7 St. Dennis Drive. The site is located on the south side of St. Dennis Drive, between Don Mills Road and Deauville Lane. Transportation Services is requesting authorization to temporarily close the south sidewalk, a portion of the eastbound bicycle lane and a portion of the eastbound traffic lane on St. Dennis Drive for a period of 25 months, from September 1, 2026 to September 30, 2028, facilitate construction of the development. The proposed construction staging area will result in the removal of one westbound traffic lane. Pavement markings will be adjusted to maintain the bicycle lanes on both sides of the roadway, with one eastbound and one westbound traffic lane. Pedestrian movements will be maintained through a 1.5 metre wide covered and protected walkway located within the closed portion of the eastbound lane on the south side of St. Dennis Drive.
North York Community Council recommends that: 1. City Council authorize the closure of the south sidewalk, the southerly eastbound designated bicycle lane, and a 5.6 metre wide portion of the eastbound curb lane on St, Dennis Drive, between a point 65 metres east of Don Mills Road and a point 60 metres further east, and a provision of a temporary 1.8 metre wide pedestrian walkway and 1.5 metre wide bicycle lane within the closed portion of St. Dennis Drive, from September 1, 2026 to September 30, 2028, inclusive. 2. City Council prohibit stopping at all times on the north side of St. Dennis Drive, between a point 105 metres east of Don Mills Road and a point 57 metres further east. 3. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 4. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 5. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists, and motorists' safety is considered at all times. 8. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. City Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the bicycle lanes. 14. City Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 15. City Council direct that the occupation permit for construction staging on St. Dennis Drive be conditional, subject to there being no conflicts with Metrolinx transit project construction. 16. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to City Council's direction, and to reinstate the traffic and parking regulations to what they were immediately prior to the date of this report from the General Manager, Transportation Services once the project is complete. 17. City Council direct that St. Dennis Drive be returned to its pre-construction traffic and parking regulations when the project is complete.
Staff recommendation as filed
The Director, Congestion and Network Management, Transportation Services, recommends that: 1. City Council authorize the closure of the south sidewalk, the southerly eastbound designated bicycle lane, and a 5.6 metre wide portion of the eastbound curb lane on St, Dennis Drive, between a point 65 metres east of Don Mills Road and a point 60 metres further east, and a provision of a temporary 1.8 metre wide pedestrian walkway and 1.5 metre wide bicycle lane within the closed portion of St. Dennis Drive, from September 1, 2026 to September 30, 2028, inclusive. 2. City Council prohibit stopping at all times on the north side of St. Dennis Drive, between a point 105 metres east of Don Mills Road and a point 57 metres further east. 3. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 4. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 5. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists, and motorists' safety is considered at all times. 8. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. City Council direct the applicant, in consultation with Transportation Services, to maintain any bicycle lanes, and install appropriate signage to inform drivers and cyclists of any changes to the bicycle lanes. 14. City Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 15. City Council direct that the occupation permit for construction staging on St. Dennis Drive be conditional, subject to there being no conflicts with Metrolinx transit project construction. 16. City Council authorize the appropriate City officials to submit directly to City Council at the appropriate time any necessary bills to amend the appropriate City of Toronto Municipal Code Chapters to give effect to City Council's direction, and to reinstate the traffic and parking regulations to what they were immediately prior to the date of this report from the General Manager, Transportation Services once the project is complete. 17. City Council direct that St. Dennis Drive be returned to its pre-construction traffic and parking regulations when the project is complete.
NY33.34deferred
Havenbrook Boulevard and George Henry Boulevard - Traffic Calming (Speed Humps)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of speed humps on Havenbrook Boulevard, between Elfindale Crescent (east intersection) and Manorpark Court and on George Henry Boulevard, between Manorpark Court and Farmview Crescent. Staff's assessment indicates the criteria as set out in the Traffic Calming Policy has been satisfied. Therefore, speed humps should be installed on Havenbrook Boulevard and George Henry Boulevard.
North York Community Council: 1. Deferred the consideration of this item until the July 7, 2026 meeting of North York Community Council.
Staff recommendation as filed
The Director, Enforcement and Street Management, Transportation Services recommends that: 1. North York Community Council authorize the installation of traffic calming (six speed humps) on Havenbrook Boulevard, between Elfindale Crescent (east intersection) and Manorpark Court, generally as shown in Attachments 3 and 4, Drawing Numbers TC684 and TC-684-1, dated April 2026, from the Director, Enforcement and Street Management, Transportation Services. 2. North York Community Council authorize the installation of traffic calming (fourteen speed humps) on George Henry Boulevard, between Manorpark Court and Farmview Crescent, generally as shown in Attachments 5, 6 and 7, Drawing Numbers TC685, and TC685-1 and TC685-2 respectively, dated April 2026, from the Director, Enforcement and Street Management, Transportation Services.
NY33.35amended
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of speed humps on: - Bogert Avenue, between Frizzell Road and Pewter Road - Poyntz Avenue, between Beecroft Road and Pewter Road - Johnston Avenue, between Yonge Street and Pewter Road - Cameron Avenue, between Yonge Street and Pewter Road - Franklin Avenue, between Yonge Street and Bassano Road Staff's assessment indicates the criteria as set out in the updated Traffic Calming Policy has been satisfied and recommend speed humps on the streets listed above.
North York Community Council: 1. Authorized the installation of traffic calming (four speed humps) on Bogert Avenue, between Frizzell Road and Pewter Road, generally as shown in Attachment 7, Drawing Number TC-676 and TC-676-1, dated April 2026, to the report (May 7, 2026) from the Director, Enforcement and Street Management, Transportation Services. 2. Authorized the installation of traffic calming (four speed humps) on Poyntz Avenue, between Beecroft Road and Pewter Road, generally as shown in Attachment 8, Drawing Number TC-677 and TC-677-1, dated April 2026, to the report (May 7, 2026) from the Director, Enforcement and Street Management, Transportation Services. 3. Authorized the installation of traffic calming (six speed humps) on Johnston Avenue, between Yonge Street and Pewter Road, generally as shown in Attachment 9, Drawing Number TC-678 and TC-678-1, dated April 2026, to the report (May 7, 2026) from the Director, Enforcement and Street Management, Transportation Services. 4. Authorized the installation of traffic calming (five speed humps) on Cameron Avenue, between Yonge Street and Pewter Road, generally as shown in Attachment 10, Drawing Number TC-679 and TC-679-1, dated April 2026, to the report (May 7, 2026) from the Director, Enforcement and Street Management, Transportation Services. 5. Authorized the installation of traffic calming (four speed humps) on Franklin Avenue, between Yonge Street and Bassano Road, generally as shown in Attachment 11, Drawing Number TC-680 and TC-680-1, dated April 2026, to the report (May 7, 2026) from the Director, Enforcement and Street Management, Transportation Services. 6. Authorized the installation of traffic calming (five speed humps) on Florence Avenue, between Yonge Street and Pewter Road generally as shown in Attachment 1 and Attachment 2 to the motion by Councillor Lily Cheng, Drawing Numbers TC-687 and TC-687-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 7. Rescinded the existing speed limit of 40 kilometres per hour on Franklin Avenue, Between Gwendolen Crescent and the east end of Franklin Avenue. 8. Rescinded the existing speed limit of 40 kilometres per hour on Franklin Avenue, Between Gwendolen Crescent and Yonge Street. 9. Requested the Director, Enforcement and Street Management, Transportation Services report to the July 7, 2026 on the feasibility of relocating speed humps from 70 Poyntz Avenue to 60 Poyntz Avenue.
Staff recommendation as filed
The Director, Enforcement and Street Management, Transportation Services recommends that: 1. North York Community Council authorize the installation of traffic calming (four speed humps) on Bogert Avenue, between Frizzell Road and Pewter Road, generally as shown in Attachment 7, Drawing Number TC-676 and TC-676-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 2. North York Community Council authorize the installation of traffic calming (four speed humps) on Poyntz Avenue, between Beecroft Road and Pewter Road, generally as shown in Attachment 8, Drawing Number TC-677 and TC-677-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 3. North York Community Council authorize the installation of traffic calming (six speed humps) on Johnston Avenue, between Yonge Street and Pewter Road, generally as shown in Attachment 9, Drawing Number TC-678 and TC-678-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 4. North York Community Council authorize the installation of traffic calming (five speed humps) on Cameron Avenue, between Yonge Street and Pewter Road, generally as shown in Attachment 10, Drawing Number TC-679 and TC-679-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 5. North York Community Council authorize the installation of traffic calming (four speed humps) on Franklin Avenue, between Yonge Street and Bassano Road, generally as shown in Attachment 11, Drawing Number TC-680 and TC-680-1, dated April 2026 from the Director, Enforcement and Street Management Transportation Services. 6. North York Community Council not authorize the installation of speed humps on Florence Avenue, between Yonge Street and Pewter Road. 7. North York Community Council rescind the existing speed limit of 40 kilometres per hour on Franklin Avenue, Between Gwendolen Crescent and the east end of Franklin Avenue. 8. North York Community Council rescind the existing speed limit of 40 kilometres per hour on Franklin Avenue, Between Gwendolen Crescent and Yonge Street.
NY33.36adopted
North York Community Council will introduce bills.
General Bills North York Community Council passed By-laws 548-2026 to 553-2026, subject to Section 226.9 of the City of Toronto Act, 2006. Confirmatory Bill North York Community Council passed a Confirmatory Bill as By-law 554-2026, subject to Section 226.9 of the City of Toronto Act, 2006.