Project Cost Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2019 Capital Budget and 2020-2028 Capital Plan (Second Quarter)

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2019-05-29 · Budget Committee · adopted

As filed

The Budget Committee recommends that: 1. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $3.750 million, as included in Appendix 1 to the report (May 8, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact. 2. City Council authorize amendments to project costs and cash flows within the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $5.356 million, as included in Appendix 2 to the report (May 8, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact.

Show the rest of As filed, 862 more characters as filed

3. City Council approve an amendment to the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and Plan to create a new capital sub-project known as East Bayfront Community Centre, in the Community Centre project, with a project cost of $7.000 million and cash flow in 2021 with funding from the following sources: $6.300 million from Development Charges (XR2114) and $0.700 million from South District Parkland Development Reserve Fund (XR2209). 4. City Council authorize the closure of two (2) sub-projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget in the amount of $0.345 million, as included in Appendix 3 to the report (May 8, 2019) from the General Manager, Parks, Forestry and Recreation to reduce 2019 cash flow, and release commitments on development related funding sources to the appropriate accounts.

On the agenda

As the city filed it

The purpose of this report is to request authority from City Council to amend the 2019 Council Approved Capital Budget and 2020-2028 Capital Plan for Parks, Forestry and Recreation by adjusting project costs and cash flows contained within the Budget and Plan. These adjustments will align cash flows for capital project delivery schedules and program requirements and as a result, will have no impact to the timing of debt requirements.

Show the rest of As the city filed it, 607 more characters as filed

Reallocations to cash flows and project costs are also requested where recent project bids exceed the current approved cash flow or alternatively to advance projects into 2019 that are ready to proceed. In addition, this report seeks Council approval to create a new sub-project for the East Bayfront Community Centre with future year cash flow to supplement funding for the East Bayfront project included in the Waterfront Revitalization Initiative's 2019 Ten-Year Capital Plan; and for the closure of two projects that will reduce 2019 cash flow and release the remaining funds for other capital purposes.

Staff recommended

The General Manager, Parks, Forestry and Recreation recommends that: 1. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $3.750 million, as included in Appendix 1 to this report, with no debt impact. 2. City Council authorize amendments to project costs and cash flows within the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $5.356 million, as included in Appendix 2 to this report, with no debt impact.

Show the rest of Staff recommended, 788 more characters as filed

3. City Council approve an amendment to the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and Plan to create a new capital sub-project known as East Bayfront Community Centre, in the Community Centre project, with a project cost of $7.000 million and cash flow in 2021 with funding from the following sources: $6.300 million from Development Charges (XR2114) and $0.700 million from South District Parkland Development Reserve Fund (XR2209). 4. City Council authorize the closure of two (2) sub-projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget in the amount of $0.345 million, as included in Appendix 3 (attached) to reduce 2019 cash flow, and release commitments on development related funding sources to the appropriate accounts.