The Public GalleryToronto

Executive Committee · 2019-09-18 · 2019.EX8.17

The filed record

Project Cost Adjustments and Deferrals / Accelerations to the Parks, Forestry and Recreation 2019 Capital Budget and 2020-2028 Capital Plan (Third Quarter)

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2019-10-02 · Toronto City Council · adopted

As filed

City Council on October 2 and 3, 2019, adopted the following: 1. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $10.811 million, as included in Appendix 1 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact. 2. City Council increase

Show the rest of As filed, 307 more characters as filed

project costs and cash flows within the Parks, Forestry and Recreation's 2019 Council-Approved Capital Budget and future year commitments in the amount of $2.143 million, as included in Appendix 2 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact.

On the agenda

As the city filed it

The purpose of this report is to request authority from City Council to amend the 2019 Council-Approved Capital Budget and 2020-2028 Capital Plan for Parks, Forestry and Recreation by adjusting project costs and cash flows contained within the 10-Year Capital Plan. These adjustments will align cash flows for capital project delivery schedules and program requirements and as a result, will have no impact to the timing of debt requirements.

Show the rest of As the city filed it, 202 more characters as filed

Reallocations to cash flows and project costs are also requested where recent project bids exceed the current approved cash flow or alternatively to advance projects into 2019 that are ready to proceed.

Staff recommended

The Budget Committee recommends to the Executive Committee that: 1. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $10.811 million, as included in Appendix 1 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact. 2. City Council

Show the rest of Staff recommended, 340 more characters as filed

authorize amendments to increase project costs and cash flows within the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $2.143 million, as included in Appendix 2 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact.

Considered

  • 2019-09-18 · Executive Committee · adopted

    Decision as filed

    The Executive Committee recommends that: 1. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $10.811 million, as included in Appendix 1 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact. 2. City Council authorize amendments to

    Show the rest of Decision as filed, 316 more characters as filed

    increase project costs and cash flows within the Parks, Forestry and Recreation's 2019 Council Approved Capital Budget and future year commitments in the amount of $2.143 million, as included in Appendix 2 to the report (August 19, 2019) from the General Manager, Parks, Forestry and Recreation, with no debt impact.

  • 2019-10-02 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting

The whole meeting