The filed record
Accommodation of Alternate Subway Access - Toronto Transit Commission Lansdowne Station: Toronto Parking Authority Site, Portion of 695 Lansdowne Avenue (Municipal Car Park 81)
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2019-03-22 · Toronto Parking Authority · adopted
As filed
The Board of Directors of the Toronto Parking Authority: 1. Authorized staff to enter into a Memorandum of Understanding, or other form of agreement as may be acceptable to the City Solicitor, with the Toronto Transit Commission to accommodate the construction of the elevators at the Lansdowne Subway Station located at 695 Lansdowne Avenue (Municipal Car Park 81), in accordance with the parameters outlined in the "Terms
Show the rest of As filed, 254 more characters as filed
and Conditions" section of the report (March 8, 2019) from the Acting President, Toronto Parking Authority, and on such other or amended terms and conditions as may be acceptable to the Acting President, Toronto Parking Authority, and the City Solicitor.
On the agenda
As the city filed it
The Toronto Transit Commission (TTC) is undertaking the construction of three new elevators at its Lansdowne Subway Station as part of their Easier Access Phase III Program, providing an additional exit access for customers. The TTC has approached the Toronto Parking Authority (TPA) and requested the TPA's permission to enter, occupy, and use portions of TPA land located at 695 Lansdowne Avenue (Municipal Car Park 81) ("Construction Premises"), as shown in Appendix 1, both temporarily during construction and permanently following the completion of construction.
Show the rest of As the city filed it, 813 more characters as filed
The project will result in the permanent loss of two parking stalls to accommodate the new infrastructure. In addition, the TTC will occupy different sections of the Subject Property on a temporary basis over the approximate three-year construction period. It is anticipated that, during stage four of the construction, the entire car park will be closed for resurfacing and landscaping for a three-month period. This report seeks approval from the TPA Board of Directors to establish a Memorandum of Understanding, or other form of agreement as may be acceptable to the City Solicitor, with the TTC, to permit the temporary loss of up to 40 spaces and a permanent loss of no more than two parking spaces at Municipal Car Park 81 to accommodate the Easier Access Phase III Program at the Lansdowne Subway Station.
Staff recommended
The Acting President, Toronto Parking Authority recommends that: 1. The Board of Directors of the Toronto Parking Authority authorize staff to enter into a Memorandum of Understanding, or other form of agreement as may be acceptable to the City Solicitor, with the Toronto Transit Commission to accommodate the construction of the elevators at the Lansdowne Subway Station located at 695 Lansdowne Avenue (Municipal Car Park
Show the rest of Staff recommended, 260 more characters as filed
81), in accordance with the parameters set out in the "Terms and Conditions" section of this report (March 8, 2019) and any such other amended terms and conditions as may be acceptable to the Acting President, Toronto Parking Authority, and the City Solicitor.