Union Station Revitalization Project - Status Report
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-04-26 · General Government and Licensing Committee · adopted
As filed
The General Government and Licensing Committee received the report (April 12, 2021) from the Executive Director, Corporate Real Estate Management for information.
On the agenda
As the city filed it
In 2009, the City of Toronto began the construction-related work of the Union Station Revitalization Project. The revitalization work included areas such as the East Wing, the creation of the Bay retail area, restoration of the Great Hall, among others, and has prepared this historic landmark to be a multi-modal destination point, focusing on retail and commercial uses, and serving as a gateway to the waterfront and surrounding community.
Show the rest of As the city filed it, 1,387 more characters as filed
The overall project remains both a technical marvel and an important revitalization initiative that will act as the centrepiece of the downtown core and transit. A major centre piece of the City of Toronto is now renewed and revitalized. The Union Station Revitalization Project continues to progress towards the final stage of construction within the current approved budget. Financial pressures and schedule risks continue to exist, which are typical on a project of this size and complexity, however, staff continue to actively manage these risks and have taken substantial measures to minimize the impacts to the project. In addition, despite challenges stemming from the COVID-19 pandemic, a number of major milestones are now complete and the project is expected to be substantially complete by the end of April 2021. This report also provides an update on the installation of a new security barrier system outside Union Station, as requested by the General Government and Licensing Committee. This work is separate from the Union Station Revitalization Project and is being coordinated with other stakeholders to ensure that the new barrier system integrates properly with existing sub-surface infrastructure. Construction of the new barrier system is expected to be complete in late 2022. The concrete barriers currently in place will be removed once the new system is installed.
Staff recommended
The Executive Director, Corporate Real Estate Management, recommends that: 1. The General Government and Licensing Committee receive this report for information.
On the record
More from this meeting
- Largest Property Tax Debtors with Tax Arrears Greater than $500,000 as at December 31, 2020Filed record
- Business Licence Deferral Program ReviewFiled record
- Administrative Penalty System - 2020 ActivityFiled record
- 2020 Annual Report Parking Enforcement Unit - Parking Ticket IssuanceFiled record
- Administrative Penalty Tribunal Chair's 2020 Annual ReportFiled record
- Grace Period for Permit Parking and the City's Administrative Penalty SystemFiled record