The decision

2022-02-02 · Toronto City Council · adopted

As filed

City Council on February 2 and 3, 2022, adopted the following: 1. City Council amend the existing heavy vehicle prohibition in effect at all times on Renforth Drive, between Bloor Street West and Highway 401 to be in effect from Bloor Street West and Eglinton Avenue West, from February 6, 2022 to October 31, 2024. 2. City Council direct that Renforth Avenue be returned to its pre-construction traffic and parking regulations when the Eglinton Crosstown West Extension project is complete.

The vote

Adopt Item · Carried, 24-1

For (24)Ana Bailão, Anthony Perruzza, Brad Bradford, Cynthia Lai, Denzil Minnan-Wong, Frances Nunziata, Gary Crawford, Gord Perks, James Pasternak, Jaye Robinson, Jennifer McKelvie, Joe Cressy, John Filion, John Tory, Josh Matlow, Kristyn Wong-Tam, Michael Ford, Michael Thompson, Mike Colle, Mike Layton, Nick Mantas, Paul Ainslie, Shelley Carroll, Stephen Holyday
Against (1)Paula Fletcher
Absent (1)Mark Grimes
The whole record, all 26 members

Every name opens that member’s record.

On the agenda

As the city filed it

As the Toronto Transit Commission (TTC) operates a transit service on Renforth Drive, City Council approval of this report is required. Metrolinx's contractor West End Connectors ("the Project Co.") is responsible for designing and building the tunnel section of the Eglinton Crosstown West Extension (ECWE) project. The Project Co. is currently preparing the tunnel boring machine (TBM) launch site for the TBM arrival in January 2022.

Show the rest of As the city filed it, 1,032 more characters as filed

The tunnel launch site is located in the northwest quadrant of Renforth Drive and Eglinton Avenue West. The TBM is expected to start excavation in Spring 2022 and complete in Fall 2024. The excavation is expected to generate multiple truck trips (17 truck trips per hour) over 12 hours per day. To minimize traffic impacts on the City road network, the Project Co. has identified a direct haul route to nearby Highway 401, which requires a temporary exemption of heavy truck prohibition currently in effect on Renforth Drive, between Highway 401 and Eglinton Avenue West. The proposed haul route provides the shortest connection between the launch site and Highway 401 and minimizes impacts on the local road network and adjacent communities during the tunnel excavation operations. Therefore, this report requests Council approval for a temporary exemption of the heavy vehicle prohibition on Renforth Drive, between Highway 401 and Eglinton Avenue West to facilitate efficient and less impactful hauling of the excavated material.

Staff recommended

The Director, Transportation Planning and Capital Program, Transportation Services recommends that: 1. City Council amend the existing heavy vehicle prohibition in effect at all times on Renforth Drive, between Bloor Street West and Highway 401 to be in effect from Bloor Street West and Eglinton Avenue West, from February 6, 2022 to October 31, 2024. 2. City Council direct that Renforth Avenue be returned to its pre-construction traffic and parking regulations when the Eglinton Crosstown West Extension project is complete.

Considered

  • 2022-01-05 · Etobicoke York Community Council · adopted

    Decision as filed

    The Etobicoke York Community Council recommends that: 1. City Council amend the existing heavy vehicle prohibition in effect at all times on Renforth Drive, between Bloor Street West and Highway 401 to be in effect from Bloor Street West and Eglinton Avenue West, from February 6, 2022 to October 31, 2024. 2. City Council direct that Renforth Avenue be returned to its pre-construction traffic and parking regulations when the Eglinton Crosstown West Extension project is complete.

  • 2022-02-02 · Toronto City Council · adopted

On the record

The item as the City filed it

More from this meeting

The whole meeting