Midtown Infrastructure Implementation Strategy - Final Report
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2022-06-15 · Toronto City Council · amended
As filed
City Council on June 15 and 16, 2022, adopted the following: 1. City Council adopt the Midtown Infrastructure Implementation Strategy included as Attachment 1 to the report (May 10, 2022) from the Chief Planner and Executive Director, City Planning, the General Manager, Parks, Forestry and Recreation, the General Manager, Transportation Services and the General Manager, Toronto Water, and City Council direct City staff to utilize the Midtown Infrastructure Implementation Strategy in the review of development applications, future capital planning processes and advancing partnership opportunities with City Agencies and Boards.
Show the rest of As filed, 2,142 more characters as filed
2. City Council adopt the Public Realm Implementation Strategy as found in Attachment 2 to the report (May 10, 2022) from the Chief Planner and Executive Director, City Planning, the General Manager, Parks, Forestry and Recreation, the General Manager, Transportation Services and the General Manager, Toronto Water, and City Council direct City staff to utilize the concept plans in: a. assessing development applications and securing development-related public realm improvements in the Yonge-Eglinton Secondary Plan area; and b. advancing the future detailed design and evaluation of the Public Realm Moves, subject to feasibility analysis, public consultation and City Council approval, using standards and best practices current at the time of implementation. 3. City Council reiterate its support for addressing the community infrastructure needs (including parks, community centres etc.) in the Yonge and Eglinton community and City Council request that City staff use the Midtown Infrastructure Implementation Strategy to focus efforts on addressing this critical deficit expeditiously, including allocating the necessary capital funding required for these projects to achieve complete communities. 4. City Council direct the appropriate City staff to undertake a robust and broad community consultation and communications process as the Midtown Infrastructure Implementation Strategy moves forward, including as part of development review and on-going City-led projects. 5. City Council direct the Chief Planner and Executive Director, City Planning to consult with the Toronto Transit Commission on existing and anticipated pressures on local transit infrastructure for consideration in future updates to the Midtown Infrastructure Implementation Strategy. 6. City Council request the Chief Planner and Executive Director, City Planning to report to the Planning and Housing Committee in first quarter of 2023 on identification of new community amenities, including parks, childcare, recreation spaces and social services, in the Yonge-Eglinton Secondary Plan Area, in consultation with the local Councillors for Wards 8, 12 and 15.
The vote
Amend Item (Additional) · Carried, 21-0
The whole record, all 25 members
- Ana BailãoAbsent
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiAbsent
- Denzil Minnan-WongFor
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonFor
- Jennifer McKelvieFor
- Joe MihevcFor
- John FilionFor
- John ToryFor
- Josh MatlowFor
- Mark GrimesFor
- Michael ThompsonAbsent
- Mike ColleFor
- Mike LaytonAbsent
- Nick MantasFor
- Paul AinslieFor
- Paula FletcherFor
- Robin Buxton PottsFor
- Shelley CarrollFor
- Stephen HolydayFor
Every name opens that member’s record.
On the agenda
As the city filed it
This report recommends adopting the Midtown Infrastructure Implementation Strategy (Attachment 1) and Public Realm Implementation Strategy (Attachment 2) to support improved capital project planning and delivery in one of the City's significant growth areas - the Yonge-Eglinton Secondary Plan area, known as Midtown. In recent years, Midtown has experienced the most development projects of any secondary plan area in the city outside of the Downtown.
Show the rest of As the city filed it, 4,180 more characters as filed
The area is expected to continue experiencing significant growth over the next 30 years. Over the period of 2016-2051, Midtown is expected to become home to approximately 93,000 new people, which is equivalent to adding more than the 2016 population of the City of Peterborough to the area. The Implementation Strategy is based on the principle that growth in Midtown will be matched with investment in community facilities, parks, the public realm, local transportation facilities and municipal servicing over time, so that the area grows and evolves as a complete community. The Strategy supports more effective capital planning and development review in Midtown by creating a shared understanding of project needs and priorities, as well as available funding tools, coordination opportunities, delivery mechanisms, and project phasing. The Strategy outlined in this report: - focuses on near (2021-2026) and mid-term (2027-2031) projects that align with the City's 10-year window for capital planning and current development-related delivery opportunities; - identifies long-term (2032-2051) projects that will need to be considered and advanced through future annual updates to the capital plan and ongoing development review; - identifies key actions to advance near and mid-term projects, and prepare for advancing key long-term projects in the future. Notably, nearly half (47 percent) of planned projects in Midtown will be delivered through City capital programs, funded through a mix of growth funding tools, such as Development Charges, Parkland Dedication and Section 37, and non-growth related funding tools such as taxes, user fees and debt. The private sector is also expected to play a significant role in delivering over a third of projects through development, either as a base requirement or in-kind contribution. The School Boards and the Toronto Public Library are expected to deliver a small, but important, share of the projects, as well. The near and mid-term projects identified in the Strategy fall within the current 10-year capital planning horizon, and the majority (71 percent) have funding identified within a capital plan approved by the City, Toronto Public Library, or School Boards, or within an approved development application. Projects that currently have partial or no funding identified will need to be further assessed and brought forward in future budget submissions or as part of future development approval processes. The Strategy recognizes that concurrent infrastructure and facility improvements will be implemented over time by multiple parties, and that coordination across infrastructure types and with development will be critical to optimizing investment dollars and project outcomes. For this reason, the Strategy identifies opportunities for greater coordination across Divisions, Agencies and Boards as part of annual capital planning and ongoing development review. Nine key actions are identified in the Strategy that provide direction on infrastructure coordination, improving and expanding parkland and the public realm, and identifying sites with potential to accommodate new community facilities. Several of these key actions are already underway, while others represent new initiatives and approaches that should be advanced to support a more coordinated approach to project delivery in Midtown. The Strategy concludes with a monitoring framework for tracking implementation progress and ensuring infrastructure requirements and priorities reflect changing conditions over time. It is anticipated that the first five-year monitoring report will be released by 2027. The Public Realm Implementation Strategy (Appendix 1 to the Strategy and Attachment 2 to the report) complements the broader Infrastructure Implementation Strategy for Midtown and provides preliminary concept plans to guide the future design of nine of the eleven Public Realm Moves identified in the Yonge-Eglinton Secondary Plan, including the Eglinton Green Line, Park Street Loop, Davisville Community Street, Merton Street Promenade, Pailton Crescent Connector, Balliol Green Street, Midtown Greenways, Redpath Revisited, and Yonge Street Squares.
Staff recommended
The Chief Planner and Executive Director, City Planning, the General Manager, Parks, Forestry and Recreation, the General Manager, Transportation Services and the General Manager, Toronto Water recommend that: 1. City Council adopt the Midtown Infrastructure Implementation Strategy, included as Attachment 1 to this report, and direct City staff to utilize the Strategy in the review of development applications, future capital planning processes and advancing partnership opportunities with City Agencies and Boards.
Show the rest of Staff recommended, 522 more characters as filed
2. City Council adopt the Public Realm Implementation Strategy (Attachment 2 to this report) and direct City staff to utilize the concept plans in: a. assessing development applications and securing development-related public realm improvements in the Yonge-Eglinton Secondary Plan area; and b. advancing the future detailed design and evaluation of the Public Realm Moves, subject to feasibility analysis, public consultation and Council approval, using standards and best practices current at the time of implementation.
Considered
2022-05-25 · Infrastructure and Environment Committee · amended
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council adopt the Midtown Infrastructure Implementation Strategy, included as Attachment 1 to the report (May 10, 2022) from the Chief Planner and Executive Director, City Planning, the General Manager, Parks, Forestry and Recreation, the General Manager, Transportation Services and the General Manager, Toronto Water, and direct City staff to utilize the Strategy in the review of development applications, future capital planning processes and advancing partnership opportunities with City Agencies and Boards.
Show the rest of Decision as filed, 1,448 more characters as filed
2. City Council adopt the Public Realm Implementation Strategy as found in Attachment 2 to the report (May 10, 2022) from the Chief Planner and Executive Director, City Planning, the General Manager, Parks, Forestry and Recreation, the General Manager, Transportation Services and the General Manager, Toronto Water, and direct City staff to utilize the concept plans in: a. assessing development applications and securing development-related public realm improvements in the Yonge-Eglinton Secondary Plan area; and b. advancing the future detailed design and evaluation of the Public Realm Moves, subject to feasibility analysis, public consultation and Council approval, using standards and best practices current at the time of implementation. 3. City Council reiterate its support for addressing the community infrastructure needs (including parks, community centres etc.) in the Yonge and Eglinton community and request that City staff use the Midtown Infrastructure Implementation Strategy to focus efforts on addressing this critical deficit expeditiously, including allocating the necessary capital funding required for these projects to achieve complete communities. 4. City Council direct the appropriate City Staff to undertake a robust and broad community consultation and communications process as the Midtown Infrastructure Implementation Strategy moves forward, including as part of development review and on-going City-led projects.
2022-06-15 · Toronto City Council · amended
On the record
More from this meeting
- Amendment to Purchase Order Number 6052605 with Moose Power Incorporated for Design and Construction of Solar Photovoltaic Rooftop SystemsFiled record
- Amendment to Purchase Order Number 6045927 for Detailed Design Services for the Sheppard Avenue and Leslie Street Sanitary Sewer Upgrades ProjectFiled record
- Amendment to Purchase Order Number 6045265 with Morrison Hershfield Limited for Professional Services for Scarlett Road Underpass Bridge Replacement and Road Network Improvements at Canadian Pacific Railway / Metrolinx Rail CorridorFiled record
- Contract Award of Negotiable Request for Proposal Document 3166773834 for the Construction of WatermainsFiled record
- Contract Award for Professional Engineering Services to WSP Canada Incorporated - Ariba Document Number 3151539512Filed record
- Amendments to Purchase Order Number 6042338 and 6042339 for Project Management and Engineering Services for the Detailed Design of the Integrated Pumping Station at the Ashbridges Bay Treatment PlantFiled record