Financial and Major Projects Update for the Year Ended December 31, 2025
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2026-04-16 · Toronto Transit Commission Board · amended
As filed
The TTC Board: 1. Approved the 2025 Capital Budget in-year budget adjustments to offset projects that have had accelerated spending by $61.9 million with projects that have experienced delays and lower spending by $61.9 million, with no debt impact, as outlined in Appendix 4 of this report. 2. Approved expenditure and funding adjustments to the TTC's 2025 Capital Budget for the Equipment program (CTT012) by increasing the 2025 Budget by $0.3 million to reflect the incremental third-party funding received from PowerON, with no debt impact, as outlined in Appendix 4 of this report.
Show the rest of As filed, 1,130 more characters as filed
3. Approve expenditure and funding adjustments to the TTC's 2025 Capital Budget for the Bridges and Tunnels program (CTT020) by increasing the 2025 Budget by $0.6 million to reflect the incremental third-party funding received from Crosslinx, with no debt impact, as outlined in Appendix 4 of this report. 4. Authorized the recommended budget adjustments noted in Recommendations 1, 2 and 3 above, and in the TTC's 2025-2034 Capital Budget and Plan, be included in the TTC's Capital Variance Report submission for the 12 months ended December 31, 2025, for City Council consideration and approval. 5. Adopted the action taken in-camera and authorized that the information contained in Confidential Attachment 1 remain confidential as it contains information about a trade secret or scientific, technical, commercial, financial or labour relations information, supplied in confidence to the City or local board, which, if disclosed, could reasonably be expected to prejudice significantly the competitive position or interfere significantly with the contractual or other negotiations of a person, group of persons, or organization.
On the agenda
As the city filed it
This report sets out the operating and capital financial results for TTC Conventional and Wheel-Trans services and provides a status update of the TTC's major capital projects for the year ended December 31, 2025. Preliminary year-end results indicate a net favourable operating variance of $0.1 million, with a $120.6 million (8.2%) revenue shortfall, fully offset by $120.7 million (4.2%) in under-expenditures. The unfavourable revenue variance was driven by lower Provincial Funding due to the deferred opening of Lines 5 and 6, lower-than-anticipated ridership driving reduced passenger revenue, and reduced draws from the TTC Stabilization Reserve, partially offset by higher ancillary revenues from third-party recoveries.
Show the rest of As the city filed it, 1,055 more characters as filed
The favourable expenditure variance was primarily due to the delayed opening of Line 5 and Line 6, lower than anticipated service costs resulted from project delays, diesel savings, labour and benefits savings associated with workforce vacancies, and lower PRESTO fees consistent with reduced passenger revenue. Based on year-end results, the capital expenditures incurred for the TTC's base capital program totalled $1.640 billion, representing a year-end spending rate of 92.0% of the 2025 Approved Capital Budget. In addition, the TTC also incurred $20.7 million or 96.9% of the 2025 Approved Capital Budget to continue the capital work program for transit-expansion related initiatives. Combined, the TTC's preliminary year-end spending reached $1.661 billion, representing a 92.1% spending rate overall as noted in Table 3. The preliminary financial results are subject to the year-end audit process, and the audited financial statements will be presented to the Audit and Risk Management Committee on May 26, 2026, and the TTC Board on June 3, 2026.
Staff recommended
It is recommended that the TTC Board: 1. Approve the 2025 Capital Budget in-year budget adjustments to offset projects that have had accelerated spending by $61.9 million with projects that have experienced delays and lower spending by $61.9 million, with no debt impact, as outlined in Appendix 4 of this report. 2. Approve expenditure and funding adjustments to the TTC's 2025 Capital Budget for the Equipment program (CTT012) by increasing the 2025 Budget by $0.3 million to reflect the incremental third-party funding received from PowerON, with no debt impact, as outlined in Appendix 4 of this report.
Show the rest of Staff recommended, 1,089 more characters as filed
3. Approve expenditure and funding adjustments to the TTC's 2025 Capital Budget for the Bridges and Tunnels program (CTT020) by increasing the 2025 Budget by $0.6 million to reflect the incremental third-party funding received from Crosslinx, with no debt impact, as outlined in Appendix 4 of this report. 4. Authorize the recommended budget adjustments noted in Recommendations 1, 2 and 3 above, and in the TTC's 2025-2034 Capital Budget and Plan, be included in the TTC's Capital Variance Report submission for the 12 months ended December 31, 2025, for City Council consideration and approval. 5. Authorize that the information contained in Confidential Attachment 1 remain confidential as it contains information about a trade secret or scientific, technical, commercial, financial or labour relations information, supplied in confidence to the City or local board, which, if disclosed, could reasonably be expected to prejudice significantly the competitive position or interfere significantly with the contractual or other negotiations of a person, group of persons, or organization.
On the record
More from this meeting
- Chief Executive Officer’s Report - April 2026Filed record
- Approved Minutes of the Advisory Committee on Accessible Transit (ACAT) General Monthly Meeting of January 29 and February 26, 2026Filed record
- Improving LRT and Streetcar Speed and ReliabilityFiled record
- TTC Special Constable Service 2025 Annual ReportFiled record
- Updates to the CEO’s Delegated AuthorityFiled record
- Fare Collection UpdateFiled record