The Public GalleryToronto

Toronto Parking Authority · 2021-11-08 · 2021.PA27.10

The filed record

Toronto Parking Authority/Toronto Hydro-Electric System Limited Electric Vehicle Charging Pilot Project Update

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2021-11-08 · Toronto Parking Authority · adopted

As filed

The Board of Directors of Toronto Parking Authority: 1. Authorized the President, Toronto Parking Authority to, negotiate, enter into, and execute on behalf of Toronto Parking Authority, two (2) agreements with Toronto Hydro-Electric System Limited to provide the goods and services necessary for Toronto Hydro-Electric System Limited to operate as a service provider to the Toronto Parking Authority for a three (3)-year

Show the rest of As filed, 484 more characters as filed

period, two separate collections of specific electric vehicle charging infrastructure stations within parking facilities operated by Toronto Parking Authority, in accordance with the updated terms and conditions contained in Attachment A to the report (November 4, 2021) from the President, Toronto Parking Authority, and any such other or amended terms and conditions as may be acceptable to the President, Toronto Parking Authority, and in a form satisfactory to the City Solicitor.

The vote

Adopt Item · Carried, 7-0

For (2)Brad Bradford, Mike Layton
The whole record, all 2 members

Every name opens that member’s record.

On the agenda

As the city filed it

Toronto Parking Authority seeks to retain Toronto Hydro-Electric System Limited to deploy and operate thirty-two electric vehicle chargers at Toronto Parking Authority-operated facilities. Toronto Parking Authority is requesting authority to enter into two (2) agreements, one (1) for the retention of Toronto Hydro-Electric System Limited with respect to nine (9) Electric Vehicle chargers that will replace the existing Electric Vehicle charging equipment that Toronto Parking Authority has in place at three (3) Toronto Parking Authority facilities; and the other for Toronto Hydro-Electric System Limited 's retention with respect to twenty-three (23) Electric Vehicle charges at other locations within Toronto Parking Authority facilities.

Show the rest of As the city filed it, 1,580 more characters as filed

The purpose of this report is to provide Toronto Parking Authority Board of Directors with an update on the status of Toronto Parking Authority's Electric Vehicle Charging Pilot Project and to seek authority to include new and amended terms and conditions in the agreements needed to enable Toronto Parking Authority 's retention of Toronto Hydro-Electric System Limited to provide the necessary goods and services to install the Electric Vehicle charging stations and operate for a three (3)-year period, the Electric Vehicle charging stations as a Toronto Parking Authority service provider. Key changes to the terms and conditions include the removal of a licence for Toronto Hydro-Electric System Limited to access the Toronto Parking Authority facilities to operate the Electric Vehicle charging infrastructure as an independent amenity operated by a third-party, along with the restructuring of the agreement to retain Toronto Hydro-Electric System Limited as a service provider to operate the Electric Vehicle charging infrastructure; and the incorporation of actual installation costs as the basis for calculating Toronto Parking Authority's option to purchase the electric vehicle charging units and/or related infrastructure at the end of the term. Should Toronto Parking Authority Board of Directors adopt the recommendations of this report, Toronto Parking Authority will work with Toronto Hydro-Electric System Limited to finalize and execute the necessary agreements before the end of 2021 with installation and operation of the thirty-two chargers expected in 2022.

Staff recommended

The President, Toronto Parking Authority recommends that: 1. The Board of Directors of Toronto Parking Authority grant authority for the President, Toronto Parking Authority to, negotiate, enter into, and execute on behalf of Toronto Parking Authority, two (2) agreements with Toronto Hydro-Electric System Limited to provide the goods and services necessary for Toronto Hydro-Electric System Limited to operate as a service

Show the rest of Staff recommended, 483 more characters as filed

provider to the Toronto Parking Authority for a three (3)-year period, two separate collections of specific electric vehicle charging infrastructure stations within parking facilities operated by Toronto Parking Authority, in accordance with the updated terms and conditions contained in Attachment A to this report, and any such other or amended terms and conditions as may be acceptable to the President, Toronto Parking Authority, and in a form satisfactory to the City Solicitor.

    On the record

    The item as the City filed it

    More from this meeting

    The whole meeting