Amendment to Purchase Order Number 6050859 with Sanscon Construction Limited for the Reconstruction of the King Street West, Queen Street West, The Queensway and Roncesvalles Avenue Intersection
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2023-07-10 · General Government Committee · adopted
As filed
The General Government Committee: 1. In accordance with Section 71-11.1.C of the Toronto Municipal Code Chapter 71 (Financial Control), authorized the amendment of Purchase Order Number 6050859 with Sanscon Construction Limited, Reconstruction of the King Street West, Queen Street West, The Queensway and Roncesvalles Avenue Intersection: a. In the amount of $523,363 net of all taxes and charges ($532,574 net of Harmonized Sales Tax recoveries).
Show the rest of As filed, 160 more characters as filed
This revises the current purchase order value from $25,518,224 to $26,041,586 net of all taxes and charges ($26,499,918 net of Harmonized Sales Tax recoveries).
On the agenda
As the city filed it
The purpose of this report is to request authority to amend Purchase Order Number 6050859 with Sanscon Construction Limited for the reconstruction of the King Street West, Queen Street West, The Queensway and Roncesvalles Avenue (KQQR) intersection. The project includes the reconstruction of the TTC track allowance and platforms, roads and sidewalks; the construction of new streetscaping; the replacement of watermains; the relining of sewers; and the rehabilitation of The Queensway bridge over Parkside Drive.
Show the rest of As the city filed it, 1,232 more characters as filed
As noted, part of this project included the reconstruction of the TTC streetcar platforms. In the process of completing this work in April, crews encountered challenges related to the underground structure of the tree pits located beside the platforms. As a result, the pedestrian areas between the streetcar platforms and the tree pits became compromised. The remediation of the tree pit structures is highly detailed and specialized work which is further complicated because they are adjacent to active streetcar platforms, requiring the work to be completed in very confined spaces, with crews needing to temporarily halt work with each streetcar to allow passengers to board. The Purchase Order Amendment is being requested to remediate the tree pit structures adjacent to TTC platforms on Roncesvalles Avenue, adjacent to the TTC platforms at Marion Street, Garden Avenue, High Park, Grenadier and Howard Park. The total value of the Purchase Order Amendment being requested is $523,363 net of all taxes and charges ($532,574 net of Harmonized Sales Tax recoveries). This revises the current purchase order value from $25,518,224 to $26,041,586 net of all taxes and charges ($26,499,918 net of Harmonized Sales Tax recoveries).
Staff recommended
The Interim Chief Engineer and Executive Director, Engineering and Construction Services and the Chief Procurement Officer, Purchasing and Materials Management, recommend that: 1. General Government Committee, in accordance with Section 71-11.1.C of the Toronto Municipal Code Chapter 71 (Financial Control Purchasing By-Law), grant authority to amend Purchase Order Number 6050859 with Sanscon Construction Limited, Reconstruction of the King Street West, Queen Street West, The Queensway and Roncesvalles Avenue Intersection: a.
Show the rest of Staff recommended, 266 more characters as filed
In the amount of $523,363 net of all taxes and charges ($532,574 net of Harmonized Sales Tax recoveries). This revises the current purchase order value from $25,518,224 to $26,041,586 net of all taxes and charges ($26,499,918 net of Harmonized Sales Tax recoveries).
On the record
More from this meeting
- Apportionment of Property Taxes - July 10, 2023 HearingFiled record
- Cancellation, Reduction or Refund of Property Taxes -July 10, 2023 HearingFiled record
- Amendment to Purchase Order No. 6054015 with Clearway Construction Incorporated for Emergency Non-Competitive Contract to Retrieve a Micro-Tunneling Boring Machine on Old Mill Drive for Assignment 5-01 Under the Basement Flooding Protection Program Phase 4 for Engineering and Construction ServicesFiled record
- Amendment to Non-Competitive Blanket Contract Number 47024284 with Canadian Red Cross SocietyFiled record
- Request for Renewal of the Master Services Agreement with Salesforce.com Canada Corporation for Cloud-Based Services and to Amend Non-Competitive Blanket Contract Number 47023379Filed record
- Non-Competitive Contract with Kone Inc. for Escalator Maintenance and Repair Work at Union StationFiled record