777 Victoria Park Avenue - Construction Staging Area
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2026-02-19 · Scarborough Community Council · deferred
As filed
The Scarborough Community Council: 1. Deferred consideration of the item until the April 30, 2026 meeting of the Scarborough Community Council and directed the Director, Congestion and Network Management, Transportation Services to report back on the feasibility of alternative options for the proposed northbound curb lane closure on Victoria Park Avenue, working in consultation with the local Councillor, and considering
Show the rest of As filed, 134 more characters as filed
options which mitigate adverse impacts on traffic flow and take the safety all users of the road and adjoining sidewalks into account.
On the agenda
As the city filed it
As the Toronto Transit Commission (TTC) operates a transit service on Victoria Park Avenue, City Council approval of this report is required. Ontario Limited is constructing a 36-storey rental tower and a 12-storey affordable housing tower at 777 Victoria Park Avenue. The site is located on the northeast corner of Victoria Park Avenue and Denton Avenue. Transportation Services is requesting authorization to temporarily close the east sidewalk and a portion of the northbound lane in Victoria Park Avenue; and the north sidewalk and a portion of the westbound lane on Denton Avenue for a period of 40 months, from March 26, 2026 to June 30, 2029, in order to enable construction staging operations for the development.
Show the rest of As the city filed it, 376 more characters as filed
Pedestrians will be redirected into a 1.8 metre wide covered and protected walkway within the closed portion of the northbound lane on Victoria Park Avenue. As a result of the sidewalk closure on the north side of Denton Avenue, pedestrians will be redirected to the south side of the roadway, at the all-way stop control at the intersection of Denton Avenue and Macey Avenue.
Staff recommended
The Director, Congestion and Network Management, Transportation Services, recommends that: 1. City Council authorize the closure of the east sidewalk and an 8.2 metre wide portion of the northbound lane on Victoria Park Avenue, between Denton Avenue and a point 150 metres north, and provision of a temporary pedestrian walkway within the closed portion of the northbound lane, from March 26, 2026 to June 30, 2029 inclusive.
Show the rest of Staff recommended, 3,968 more characters as filed
2. City Council authorize the closure of the north sidewalk and a 6.6 metre wide portion of the westbound lane on Denton Avenue, between Victoria Park Avenue and a point 61 metres further east, from March 26, 2026 to June 30, 2029 inclusive. 3. City Council rescind the existing parking prohibition in effect at all times on the east side of Victoria Park Avenue, between Denton Avenue and a point 150 metres north. 4. City Council prohibit stopping at all times on the east side of Victoria Park Avenue, between Denton Avenue and a point 150 metres north. 5. City Council prohibit stopping at all times on the north side of Denton Avenue, between Victoria Park Avenue and a point 61 metres east. 6. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 7. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 8. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 9. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 10. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 11. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 13. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 14. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 16. City Council direct the applicant to cooperate with and provide all necessary assistance to the City Engineers, staff and representatives carrying out operation, maintenance, and construction activities to municipal infrastructure with the vicinity of the construction staging area, and at no cost to the City to remove any staging to accommodate the necessary municipal infrastructure work. 17. City Council direct the applicant to provide monthly community meetings, to discuss any concerns raised by the community. 18. City Council direct that Victoria Park Avenue and Denton Avenue be returned to its pre-construction traffic and parking regulations when the project is complete.
On the record
More from this meeting
- 3718 and 3730 Kingston Road - Zoning By-law Amendment - Decision Report - ApprovalFiled record
- 2650 Lawrence Avenue East - Official Plan Amendment Application and Zoning By-law Amendment Application - Appeal ReportFiled record
- 17 Bellehaven Crescent - Fence Exemption ReportFiled record
- 1072 McCowan Road - Residential Demolition ApplicationFiled record
- 1505 Danforth Road - Residential Demolition ApplicationFiled record
- Faircroft Boulevard - Traffic Calming (Speed Humps)Filed record