Toronto and East York Community Council
The full agenda, as filed
All 105 items in the clerk’s order. Each carries the city’s own words: the staff recommendation, what the body decided, and its status. Nothing below is written by us.
Items 26 to 50 of 105Show 2550100all
TE32.26adopted
45 The Esplanade - Official Plan and Zoning By-law Amendment Applications - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Official Plan and Zoning By-law Amendment application for a 36 and 35 storey mixed-use development containing 682 units, an 8,042 square metre hotel use, and 585 sqaure metres of retail at-grade. Staff are currently reviewing the application. It has been circulated to all appropriate agencies and City divisions for comment. Staff will proceed to schedule a community consultation meeting for the application with the Ward Councillor. Staff do not support this proposal as currently submitted. Substantial revisions are required to meet the built form, public realm, and non-residential use protection policies of the Official Plan, as well as regulations for tall buildings, and other area-specifc design criteria.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the application located at 45 The Esplanade together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 45 The Esplanade together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.27adopted
778-788 King Street West - Zoning By-law Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Zoning By-law Amendment application for an 18 storey mixed-use building comprised of 714 square metres of retail space on the ground floor and 373 residential units above. The application has been circulated to all appropriate City divisions and public agencies for comment. In consultation with the Ward Councillor.
The Toronto and East York Community Council: 1. Received the report (March 31, 2022) from the Director, Community Planning, Toronto and East York District, for information.
Staff recommendation as filed
The City Planning Division recommends that: 1. The City Planning Division recommends that this report be received for information.
TE32.28adopted
This report provides information and identifies a preliminary set of issues regarding the Zoning By-law Amendment application for a 39-storey mixed-use building with commercial uses on the ground floor and 394 residential dwelling units above. A new 1,000 square metre City park is proposed on the northern portion of the site at the southeast corner of Spadina Avenue and Adelaide Street West with a public parking garage beneath. A total of 70 of the 149 parking spaces proposed are to be owned and operated by the Toronto Parking Authority (TPA). The application has been circulated to all appropriate City divisions and public agencies for comment. In consultation with the Ward Councillor, City Planning staff have scheduled a Community Consultation Meeting for the application on April 4, 2022.
The Toronto and East York Community Council: 1. Received the report (March 28, 2022) from the Director, Community Planning, Toronto and East York District, for information.
Staff recommendation as filed
The City Planning Division recommends that this report be received for information.
TE32.29adopted
109-127 Strachan Avenue - Official Plan and Zoning By-law Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Official Plan and Zoning By-law Amendment application for a mixed-use building that ranges in height from 2 to 14 storeys, comprised of 339 square metres of retail space within the existing 3-storey building and 314 total residential units. The application has been circulated to all appropriate City divisions and public agencies for comment. Staff will proceed to schedule a community consultation meeting for the application in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the application located at 109-127 Strachan Avenue together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 109-127 Strachan Avenue together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.30adopted
452 Bathurst Street - Zoning By-law Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Zoning By-law Amendment application for a 6-storey mixed-use building comprised of 365.70 square metres of retail space on the ground floor and 49 residential units above. The application has been circulated to all appropriate City divisions and public agencies for comment. Staff will proceed to schedule a community consultation meeting for the application in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the application located at 452 Bathurst Street together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 452 Bathurst Street together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.31adopted
83-95A Bloor Street West - Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the application located at 83-95A Bloor Street West for a 79-storey mixed-use development consisting of retail located at grade, and residential units within the tower above. Staff are currently reviewing the application. It has been circulated to all appropriate agencies and City divisions for comment. Staff will proceed to schedule a community consultation meeting for the application with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the application located at 83-95A Bloor Street West together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 83-95A Bloor Street West together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.32amended
15 Charles Street East and 16 Isabella Street - Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the application located at 15 Charles Street East & 16 Isabella Street for a 54-storey mixed-use development consisting of retail uses located on the ground floor and residential uses above. Staff are currently reviewing the application. It has been circulated to all appropriate agencies and City divisions for comment. Staff will proceed to schedule a community consultation meeting for the application with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the lands pertaining to 15 Charles Street East and 16 Isabella Street, together with the Ward Councillor as soon as possible in the new term of Council: a. If hosted in-person, includes the provision of light refreshments and, when required, childcare and accessibility resources including sign language interpretation at the sole cost of the applicant. b. If hosted virtually, includes the provision of accessibility resources including closed captioning and, upon request, sign language interpretation at the sole cost of the applicant. The meeting notice should clearly articulate who community members should contact to access these resources. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. Staff conduct strategic outreach with various community stakeholders including but not limited to the local residents' association and business improvement area prior to the community consultation meeting, should time permit. 4. The Director, Community Planning, Toronto and East York District and the applicant, in consultation with City Planning, Transportation Services, Parks, Forestry and Recreation and any other necessary City officials, create a working group and consult with the local community as part of the Site Plan process, including the local residents association and other stakeholders, on the following prior to the issuance of Final Site Plan Approval pursuant to Section 114 of the City of Toronto Act: a construction and traffic management plan, landscape and public realm plans, building materials and lighting, and other issues as identified by the Ward Councillor.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 15 Charles Street East and 16 Isabella Street together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.33adopted
22-32 Scollard Street and 21-25 Davenport Road -Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the application located at 22-32 Scollard Street and 21-25 Davenport Road for a 61-storey mixed-use building with 79 dwelling units. The proposal is not acceptable in its current form, the tower does not respond appropriately to the existing and planned context including setbacks, separation distances, and height. Staff are currently reviewing the applications, which have been circulated to all appropriate agencies and City divisions for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the applications, in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 22-32 Scollard Street and 21-25 Davenport Road, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 22-32 Scollard Street and 21-25 Davenport Road, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.34adopted
906 Yonge Street and 25 McMurrich Street - Zoning By-law Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Zoning By-law Amendment application for a mixed-use complex with two tall buildings connected by a 2-storey base building. The tall building fronting Yonge Street is 33 storeys, containing 213 dwelling units and 75 square metres of grade-related retail space. The tall building fronting McMurrich Street is 19 storeys containing 188 dwelling units. Staff are currently reviewing the application. It has been circulated to all appropriate agencies and City divisions for comment. Together with the Ward Councillor, City Planning staff held a Community Consultation Meeting on February 1, 2022.
The Toronto and East York Community Council: 1. Endorsed the arrangements made between City Planning staff and the applicant to give notice for the February 1, 2022, Community Consultation Meeting to landowners and residents within 120 metres of the site, and to additional residents, institutions and owners as was determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that 1. Toronto and East York Community Council endorse the arrangements made between City Planning staff and the applicant to give notice for the February 1, 2022, Community Consultation Meeting to landowners and residents within 120 metres of the site, and to additional residents, institutions and owners as was determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.35adopted
This report provides information and identifies a preliminary set of issues regarding the Official Plan Amendment, Zoning By-law Amendment, and Rental Housing Demolition applications to demolish 40 rental dwelling units and allow for the construction of a 13-storey (45.5-metre excluding the mechanical penthouse) mixed-use building, containing 110 dwelling units (including 40 replacement rental units) and 600 square metres of grade-related retail space. Staff are currently reviewing the applications. It has been circulated to all appropriate agencies and City divisions for comment. City Planning staff have tentatively scheduled a Community Consultation Meeting for the application with the Ward Councillor on April 26, 2022.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the applications pertaining to 1233 Yonge Street and 9 Woodlawn Street East together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the applications pertaining to 1233 Yonge Street and 9 Woodlawn Street East together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.36adopted
1-13 St Clair Avenue West - Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the application located at 1-13 St. Clair Avenue West for a 49-storey mixed-use building with 340 dwelling units, and incorporating the existing 12-storey office building. Staff are currently reviewing the application, which have been circulated to all appropriate agencies and City divisions for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the application, in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 1-13 St. Clair Avenue West, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 1-13 St. Clair Avenue West, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.37adopted
This report provides information and identifies a preliminary set of issues regarding the Zoning By-law Amendment and Rental Housing Demolition applications submitted for the lands at 1910, 1920 and 1944 Yonge Street. The proposal is to demolish a 7-storey 102-unit rental apartment building at 1944 Yonge Street and an 8-storey non-residential building containing commercial-retail, and office uses at 1910 and 1920 Yonge Street. The demolition will facilitate the construction of two 45-storey residential towers inclusive of an 8-10 storey shared base building containing ground floor retail, office uses and 102 rental replacement dwelling units. Staff are currently reviewing the applications, which have been circulated to all appropriate agencies and City divisions for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the applications, in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 1910, 1920 and 1944 Yonge Street, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 1910, 1920 and 1944 Yonge Street, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.38adopted
This report provides information and identifies a preliminary set of issues regarding the Official Plan and Zoning By-law Amendment applications submitted for the lands at 2039-2049 Yonge Street and 40-50 Tullis Drive. The proposal is to demolish 3 two-storey commercial buildings along Yonge Street and 4 two-storey semi-detached dwellings along Tullis Drive. The demolition will facilitate the construction of an 11-storey mixed-use building with grade related retail fronting Yonge Street and a row of 7 three-storey townhouses fronting Tullis Drive. Staff are currently reviewing the applications, which have been circulated to all appropriate agencies and City divisions for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the applications, in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 2039-2049 Yonge Street and 40-50 Tullis Drive, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the development application located at 2039-2049 Yonge Street and 40-50 Tullis Drive, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.39amended
550 Adelaide Street East - Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the application located at 550 Adelaide Street East for a 29-storey mixed-use development consisting of an automotive dealership located at grade, and residential units within the tower above. Staff are currently reviewing the application. It has been circulated to all appropriate agencies and City divisions for comment. Staff will proceed to schedule a community consultation meeting for the application with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the lands pertaining to 550 Adelaide Street East, together with the Ward Councillor as soon as possible in the new term of Council: a. If hosted in-person, includes the provision of light refreshments and, when required, childcare and accessibility resources including sign language interpretation at the sole cost of the applicant. b. If hosted virtually, includes the provision of accessibility resources including closed captioning and, upon request, sign language interpretation at the sole cost of the applicant. The meeting notice should clearly articulate who community members should contact to access these resources. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. Staff conduct strategic outreach with various community stakeholders including but not limited to the local residents' association and business improvement area prior to the community consultation meeting, should time permit. 4. The Director, Community Planning, Toronto and East York District and the applicant, in consultation with City Planning, Transportation Services, Parks, Forestry and Recreation and any other necessary City officials, to create a working group and to consult with the local community as part of the Site Plan process, including the local residents association and other stakeholders, on the following prior to the issuance of Final Site Plan Approval pursuant to Section 114 of the City of Toronto Act: a construction and traffic management plan, landscape and public realm plans, building materials and lighting, and other issues as identified by the Ward Councillor.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 550 Adelaide Street East together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.40amended
This report provides information and identifies a preliminary set of issues regarding the Official Plan Amendment and Zoning By-law Amendment applications at 295-349 George Street. The applications propose a building envelope which would permit an institutional building no higher than 57 metres (62 metres to the top of the mechanical penthouse) with a maximum non-residential gross floor area of 53,000 square metres. The building design and articulation is proposed to be further refined through the site plan control application. The proposal includes a 378-bed long term care facility, a 130 bed transitional shelter, 21 units of transitional housing, a 100 bed emergency shelter and a community service hub. Official Plan Amendment and Zoning By-law amendments were approved for this site on November 7, 2017 for a 37 metre high institutional building (with similar uses to this proposal) with a gross floor area of 44,068 square metres. The application has been circulated to all appropriate City divisions and public agencies for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the application, in consultation with the Ward Councillor.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the lands pertaining to 295-349 George Street, together with the Ward Councillor as soon as possible in the new term of Council: a. If hosted in-person, includes the provision of light refreshments and, when required, childcare and accessibility resources including sign language interpretation at the sole cost of the applicant. b. If hosted virtually, includes the provision of accessibility resources including closed captioning and, upon request, sign language interpretation at the sole cost of the applicant. The meeting notice should clearly articulate who community members should contact to access these resources. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. Staff conduct strategic outreach with various community stakeholders including but not limited to the local residents' association and business improvement area prior to the community consultation meeting, should time permit. 4. The Director, Community Planning, Toronto and East York District and the applicant, in consultation with City Planning, Transportation Services, Parks, Forestry and Recreation and any other necessary City officials, to create a working group and to consult with the local community as part of the Site Plan process, including the local residents association and other stakeholders, on the following prior to the issuance of Final Site Plan Approval pursuant to Section 114 of the City of Toronto Act: a construction and traffic management plan, landscape and public realm plans, building materials and lighting, and other issues as identified by the Ward Councillor.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 295-349 George Street together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.41amended
10 Huntley Street - Official Plan Amendment and Zoning Amendment Application - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Official Plan Amendment and Zoning By-law Amendment application for a 29-storey apartment building, containing 213 dwelling units. The application has been circulated to all appropriate City divisions and public agencies for comment. City Planning staff will proceed to schedule a Community Consultation Meeting for the application, in consultation with the Ward Councillor. Staff do not support this proposal in its current form. Substantial revisions are required to meet the policies of the Official Plan and Downtown Plan.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the lands pertaining to 10 Huntley Street, together with the Ward Councillor as soon as possible in the new term of Council: a. If hosted in-person, includes the provision of light refreshments and, when required, childcare and accessibility resources including sign language interpretation at the sole cost of the applicant. b. If hosted virtually, includes the provision of accessibility resources including closed captioning and, upon request, sign language interpretation at the sole cost of the applicant. The meeting notice should clearly articulate who community members should contact to access these resources. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. City Planning staff to undertake a study of the Upper Jarvis area, generally located between Bloor Street East, Sherbourne Street, Wellesley Street East, and Church Street, to investigate the implications of the current development applications on the Neighbourhoods and Apartment Neighbourhoods designated lands within this area and to develop a planning framework, as appropriate, to assist in evaluating development proposals in the area and report back to Toronto and East York Community Council in the first quarter of 2023. 4. Staff conduct strategic outreach with various community stakeholders including but not limited to the local residents' association and business improvement area prior to the community consultation meeting, should time permit. 5. The Director, Community Planning, Toronto and East York District and the applicant, in consultation with City Planning, Transportation Services, Parks, Forestry and Recreation and any other necessary City officials, to create a working group and to consult with the local community as part of the Site Plan process, including the local residents association and other stakeholders, on the following prior to the issuance of Final Site Plan Approval pursuant to Section 114 of the City of Toronto Act: a construction and traffic management plan, landscape and public realm plans, building materials and lighting, and other issues as identified by the Ward Councillor.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the application located at 10 Huntley Street, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. Council direct City Planning staff to undertake a study of the Upper Jarvis area, generally located between Bloor Street East, Sherbourne Street, Wellesley Street East, and Church Street, to investigate the implications of the current development applications on the Neighbourhoods and Apartment Neighbourhoods designated lands within this area and to develop a planning framework, as appropriate, to assist in evaluating development proposals in the area and report back to Toronto and East York Community Council in Q1 of 2023.
TE32.42adopted
This report provides information and identifies a preliminary set of issues regarding the Official Plan and Zoning By-law Amendment and Rental Housing Demolition applications to redevelop the subject lands, which are currently occupied by a mix of low-rise residential buildings that collectively contain 25 rental dwelling units and 31 dwelling rooms, with 48-storey and 59-storey mixed-use buildings, together containing 1,297 dwelling units, and a 3-storey institutional building planned for a childcare facility. The applications have been circulated to all appropriate City divisions and public agencies for comment. City Planning staff will proceed to schedule a Community Consultation Meeting on the Official Plan and Zoning By-law Amendment application, in consultation with the Ward Councillor. Staff do not support this proposal in its current form. Substantial revisions are required to meet the policies of the Official Plan and Downtown Plan.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the lands pertaining to 47-65 Huntley Street, 2-18, 24, and 26 Linden Street, and 1-11 Selby Stree, together with the Ward Councillor as soon as possible in the new term of Council: a. If hosted in-person, includes the provision of light refreshments and, when required, childcare and accessibility resources including sign language interpretation at the sole cost of the applicant. b. If hosted virtually, includes the provision of accessibility resources including closed captioning and, upon request, sign language interpretation at the sole cost of the applicant. The meeting notice should clearly articulate who community members should contact to access these resources. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. City Planning staff to undertake a study of the Upper Jarvis area, generally located between Bloor Street East, Sherbourne Street, Wellesley Street East, and Church Street, to investigate the implications of the current development applications on the Neighbourhoods and Apartment Neighbourhoods designated lands within this area and to develop a planning framework, as appropriate, to assist in evaluating development proposals in the area and report back to Toronto and East York Community Council in Q1 of 2023. 4. Staff conduct strategic outreach with various community stakeholders including but not limited to the local residents' association and business improvement area prior to the community consultation meeting, should time permit. 5. The Director, Community Planning, Toronto and East York District and the applicant, in consultation with City Planning, Transportation Services, Parks, Forestry and Recreation and any other necessary City officials, to create a working group and to consult with the local community as part of the Site Plan process, including the local residents association and other stakeholders, on the following prior to the issuance of Final Site Plan Approval pursuant to Section 114 of the City of Toronto Act: a construction and traffic management plan, landscape and public realm plans, building materials and lighting, and other issues as identified by the Ward Councillor. 6. The Director, Community Planning, Toronto and East York District to review and consider the written submissions from community members, adjacent neighbours and resident associations on this item as a part of the planning review process.
Staff recommendation as filed
The City Planning Division recommends that: 1. City Planning staff schedule a Community Consultation Meeting for the applications located at 47-65 Huntley Street, 2-18, 24, and 26 Linden Street, and 1-11 Selby Street, together with the Ward Councillor. 2. Notice for the Community Consultation Meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions, and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant. 3. Council direct City Planning staff to undertake a study of the Upper Jarvis area, generally located between Bloor Street East, Sherbourne Street, Wellesley Street East, and Church Street, to investigate the implications of the current development applications on the Neighbourhoods and Apartment Neighbourhoods designated lands within this area and to develop a planning framework, as appropriate, to assist in evaluating development proposals in the area and report back to Toronto and East York Community Council in Q1 of 2023.
TE32.43adopted
2721 Danforth Ave - Official Plan and Zoning By-law Amendment Applications - Preliminary Report
This report provides information and identifies a preliminary set of issues regarding the Official Plan Amendment and Zoning By-law Amendment application for a mixed use building with two towers at 35- and 55-storeys, containing 1,139 dwelling units. Staff are currently reviewing the application. The application has been circulated to all appropriate agencies and City divisions for comment. Staff will proceed to schedule a community consultation meeting for the application, in consultation with the Ward Councillor. Staff do not support this proposal as currently submitted. Substantial revisions are required to meet the policies in Site and Area Specific Policy (SASP) No. 577.
The Toronto and East York Community Council directed: 1. Staff schedule a community consultation meeting for the application located at 2721 Danforth Avenue together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
Staff recommendation as filed
The City Planning Division recommends that: 1. Staff schedule a community consultation meeting for the application located at 2721 Danforth Avenue together with the Ward Councillor. 2. Notice for the community consultation meeting be given to landowners and residents within 120 metres of the application site, and to additional residents, institutions and owners to be determined in consultation with the Ward Councillor, with any additional mailing costs to be borne by the applicant.
TE32.44adopted
Construction Staging Area Time Extension - 99 Blue Jays Way (Mercer Street)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. BJW Residences Limited Partnership is constructing a 47-storey residential development building at 99 Blue Jays Way. The site is located on the southeast corner of Blue Jays Way and Mercer Street. A three-metre-wide portion of the eastbound curb lane on Mercer Street, between Blue Jays Way and a point 62 metres east, and a one-metre-wide portion of the westbound curb lane on the first lane south of Mercer Street, are currently closed to accommodate construction staging operations for the development. Toronto and East York Community Council, at its meeting on December 2, 2020, approved the subject construction staging areas on Mercer Street and on the first lane south of Mercer Street from December 3, 2020 to May 31, 2022. At the time that the initial report was prepared, a permit period of only 18 months was supported by Transportation Services due to planned Capital Work by Toronto Water. The developer is requesting an extension of the duration of the construction staging area as construction is ongoing, and the Capital Work is not scheduled to commence until June 2023. Transportation Services is requesting authorization to extend the duration of the construction staging areas on Mercer Street and on the first lane south of Mercer Street for an additional 12 months, from June 1, 2022 to May 31, 2023, to allow for the construction of the development to be completed.
The Toronto and East York Community Council: 1. Authorized the continuation of the closure of the south sidewalk and a three-metre-wide portion of the eastbound curb lane on Mercer Street, between Blue Jays Way and a point 62 metres east from June 1, 2022 to May 31, 2023. 2. Authorized the continuation of the closure of a one-metre-wide portion of the most northerly westbound curb lane on the first lane south of Mercer Street, east of Blue Jays Way, between Blue Jays Way Mercer Street and a point 62 metres east, from June 1, 2022 to May 31, 2023. 3. Continued to designate the public lane system bounded by Blue Jays Way, Mercer Street, John Street and Wellington Street West as one-way eastbound/northbound. 4. Directed the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 5. Directed the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. Directed the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. Directed the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Directed the applicant to continue providing a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Directed the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. Directed that Mercer Street and the public lane system bounded by Blue Jays Way, Mercer Street, John Street and Wellington Street West be returned to pre-construction traffic and parking regulations when the project is completed.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continuation of the closure of the south sidewalk and a three-metre-wide portion of the eastbound curb lane on Mercer Street, between Blue Jays Way and a point 62 metres east from June 1, 2022 to May 31, 2023. 2. Toronto and East York Community Council authorize the continuation of the closure of a one-metre-wide portion of the most northerly westbound curb lane on the first lane south of Mercer Street, east of Blue Jays Way, between Blue Jays Way Mercer Street and a point 62 metres east, from June 1, 2022 to May 31, 2023. 3. Toronto and East York Community Council continue to designate the public lane system bounded by Blue Jays Way, Mercer Street, John Street and Wellington Street West as one-way eastbound/northbound. 4. Toronto and East York Community Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 5. Toronto and East York Community Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 6. Toronto and East York Community Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 7. Toronto and East York Community Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 8. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 9. Toronto and East York Community Council direct the applicant to continue providing a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 10. Toronto and East York Community Council direct the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 12. Toronto and East York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 13. Toronto and East York Community Council direct that Mercer Street and the public lane system bounded by Blue Jays Way, Mercer Street, John Street and Wellington Street West be returned to pre-construction traffic and parking regulations when the project is completed.
TE32.45adopted
Construction Staging Area Time Extension - 15-35 Mercer Street
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Madison Group is constructing a residential development (Nobu Residences) consisting of two 45-storey condominium buildings at 15-35 Mercer Street. The site is located midway on Mercer Street, between John Street and Blue Jays Way. A portion of the City's right-of-way on the south side of Mercer Street abutting the site is currently closed to accommodate a construction staging area for the development. Toronto and East York Community Council, at its meeting on July 4, 2018, approved the temporary closure of a 3.3 metre-wide portion of the westbound lane on Mercer Street from July 20, 2018 to May 31, 2022. The temporary closure of the south sidewalk on Mercer Street was also approved for a shorter period of time from July 20, 2018 to May 31, 2020; however, continued closure has been required to accommodate two construction hoists. At the time that the initial report was prepared, Capital Work by Toronto Water was reported as being planned; however, as the exact dates were not yet available, the developer was advised that the proposed construction staging area would need to be modified to accommodate the Capital Work. Based on the information provided by the developer, the site has experienced delays due to COVID-19. The developer was informed that the planned Capital Work by Toronto Water is scheduled to commence June 2023. The developer is requesting an extension of the duration of the construction staging area on Mercer Street, from June 1, 2022 to May 31, 2023, in order to complete the construction of the development. Transportation Services is requesting authorization to extend the duration of the construction staging area on Mercer Street for an additional 12 months, from June 1, 2022 to May 31, 2023, to allow for the construction of the development to be completed.
The Toronto and East York Community Council: 1. Authorized the continued closure of the south sidewalk on Mercer Street, between a point 46.8 metres west of John Street and a point 86.2 metres further west, from June 1, 2022 to May 31, 2023. 2. Authorized the continued closure of a 3.3 metre-wide portion of the westbound lane on the south side of Mercer Street, between a point 46.8 metres west of John Street and a point 66.2 metres further west, from June 1, 2022 to May 31, 2023. 3. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. At a minimum, the developer will be required to continue to provide traffic control persons to be stationed at the east and west ends of the construction staging area during daily work hours from June 1, 2022 to May 31, 2023, who will safely direct pedestrians across Mercer Street. 4. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 5. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 6. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 7. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 8. Directed the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. Directed the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. Directed that Mercer Street be returned to pre-construction traffic and parking regulations when the project is completed.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the continued closure of the south sidewalk on Mercer Street, between a point 46.8 metres west of John Street and a point 86.2 metres further west, from June 1, 2022 to May 31, 2023. 2. Toronto and East York Community Council authorize the continued closure of a 3.3 metre-wide portion of the westbound lane on the south side of Mercer Street, between a point 46.8 metres west of John Street and a point 66.2 metres further west, from June 1, 2022 to May 31, 2023. 3. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. At a minimum, the developer will be required to continue to provide traffic control persons to be stationed at the east and west ends of the construction staging area during daily work hours from June 1, 2022 to May 31, 2023, who will safely direct pedestrians across Mercer Street. 4. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 5. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 6. Toronto and East York Community Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 7. Toronto and East York Community Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 8. Toronto and East York Community Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 9. Toronto and East York Community Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 11. Toronto and East York Community Council direct that Mercer Street be returned to pre-construction traffic and parking regulations when the project is completed.
TE32.46adopted
Construction Staging Area - 838-880 Dupont Street and 1080 Shaw Street
As the Toronto Transit Commission (TTC) operates a transit service on Dupont Street, City Council approval of this report is required. Deltera Inc. is constructing a nine-storey mixed-use residential condominium with 329 residential units and ground floor retail, at 838-880 Dupont Street and 1080 Shaw Street. The site is located on the north side of Dupont Street between Shaw Street and Ossington Avenue. Transportation Services is requesting approval to close a section of the north sidewalk on Dupont Street and a portion of the west sidewalk on Shaw Street for a period of 37 months, from May 12, 2022 to May 31, 2025 to accommodate a construction staging area. Pedestrian movements on the north side of Dupont Street abutting the site will be restricted and pedestrians will be directed to the south side sidewalk of Dupont Street. No long-term roadway occupation is being requested for this development.
The Toronto and East York Community Council recommends that: 1. City Council authorize the closure of the north sidewalk on Dupont Street, between Shaw Street and a point 144 metres west, from May 12, 2022 to May 31, 2025. 2. City Council authorize the closure of a 1.1 metre wide portion of the west sidewalk on Shaw Street, between Dupont Street and a point 74 metres north, from May 12, 2022 to May 31, 2025. 3. City Council rescind the existing no parking prohibition in effect at all times on the north side of Dupont Street between Shaw Street and a point 144 metres west. 4. City Council rescind the existing no stopping regulation in effect from 4:00 p.m. to 6:00 p.m. Monday to Friday except public holidays on the north side of Dupont Street between Shaw Street and a point 144 metres west. 5. City Council prohibit stopping at all times on the north side of Dupont Street, between Shaw Street and a point 144 metres west. 6. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed, to keep clear of any construction debris and made safe. 7. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 8. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 9. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 11. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 13. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 14. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 15. City Council direct that Dupont Street and Shaw Street be returned to their pre-construction traffic and parking regulations when the project is complete.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the north sidewalk on Dupont Street, between Shaw Street and a point 144 metres west, from May 12, 2022 to May 31, 2025. 2. City Council authorize the closure of a 1.1 metre wide portion of the west sidewalk on Shaw Street, between Dupont Street and a point 74 metres north, from May 12, 2022 to May 31, 2025. 3. City Council rescind the existing no parking prohibition in effect at all times on the north side of Dupont Street between Shaw Street and a point 144 metres west. 4. City Council rescind the existing no stopping regulation in effect from 4:00 p.m. to 6:00 p.m. Monday to Friday except public holidays on the north side of Dupont Street between Shaw Street and a point 144 metres west. 5. City Council prohibit stopping at all times on the north side of Dupont Street, between Shaw Street and a point 144 metres west. 6. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed, to keep clear of any construction debris and made safe. 7. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 8. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 9. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 11. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 13. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 14. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 15. City Council direct that Dupont Street and Shaw Street be returned to their pre-construction traffic and parking regulations when the project is complete.
TE32.47adopted
Construction Staging Area - 1365 - 1375 Yonge Street
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Daniels Corporation is constructing a 17-storey mixed-use building with ground floor at retail 1365-1375 Yonge Street. The site is located on the northeast corner of Yonge Street and Rosehill Avenue. Construction of the development will be undertaken in two phases. Phase 1 of the construction includes excavation, piling and shoring operations. Transportation Services is requesting authorization to close a portion of the north-south laneway, abutting the site, for a period of 41 months, from May 1, 2022 to September 30, 2025, in order to accommodate construction activities. The requested construction staging area will result in closure of laneway access/egress for vehicular traffic at Rosehill Avenue. However, laneway access/egress at Pleasant Boulevard will be maintained. Pedestrian operations within the laneway will be maintained, including an emergency egress for pedestrians at Rosehill Avenue. The development will be constructed from grade level to completion of the project in Phase 2 and involves the closure of the north sidewalk and a portion of the westbound lane on Rosehill Avenue for a period of 35 months, from November, 2022 to September 30, 2025. A report will be submitted Q4 2022 for the aforementioned closure.
The Toronto and East York Community Council: 1. Authorized the closure a portion of the public laneway, between Rosehill Avenue and a point 50 metres north, from May 1, 2022 to September 30, 2025. 2. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 3. Directed the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 4. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. Directed the applicant to install appropriate temporary construction signage and to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 8. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 10. Directed that the public laneway be returned to pre-construction traffic and parking regulations when the project is complete.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the closure a portion of the public laneway, between Rosehill Avenue and a point 50 metres north, from May 1, 2022 to September 30, 2025. 2. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 3. Toronto and East York Community Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 4. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. Toronto and East York Community Council direct the applicant to install appropriate temporary construction signage and to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 8. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 9. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 10. Toronto and East York Community Council direct that the public laneway be returned to pre-construction traffic and parking regulations when the project is complete.
TE32.48amended
Construction Staging Area - 284 King Street East
As the Toronto Transit Commission (TTC) operates a transit service on King Street East, City Council approval of this report is required. Lamb Bauhaus Inc. is constructing a 32-storey mixed use residential condominium with ground floor retail at 284 King Street East. The site is located on the north side of King Street East, mid-block between Ontario Street and Berkeley Street. The developer is requesting varying degrees of sidewalk occupation on the north side King Street East during two Phases, from May 12, 2022 to December 31, 2025; however there is a conflict with planned Capital Work in 2025. Therefore, the developer may need to temporarily remove or modify their staging areas after December 31, 2024 to accommodate the City's planned Capital Work. For Phase 1, Transportation Services is requesting authorization to close a 1.5 metre-wide portion of the north side sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, for a period of 7 months from May 12, 2022 to November 30, 2022, to accommodate a construction staging area. For Phase 2, Transportation Services is requesting authorization to close a 0.7 metre-wide portion of the north side sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, for a period of 25 months from December 1, 2022 to December 31, 2024, to accommodate a construction staging area.
The Toronto and East York Community Council recommends that: 1. City Council authorize the closure of a 1.5 metre-wide portion of the north sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, from May 12, 2022 to November 30, 2022. 2. City Council authorize the closure of a 0.7 metre-wide portion of the north sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, from December 1, 2022 to December 31, 2023. 3. City Council rescind the existing parking machine regulation in effect from 9:00 a.m. to 4:00 p.m. , 6:00 p.m. to 9:00 p.m. Monday to Friday, 8:00 a.m. to 9:00 p.m. Saturday, 1:00 p.m. to 9:00 p.m. Sunday at a rate of $3.00 per hour and for a maximum period of 3 hours, on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 4. City Council rescind the existing parking machine regulation in effect from 9:00 a.m. to 4:00 p.m. and 6:00 p.m. to 9:00 p.m. Monday to Friday, 8:00 a.m. to 9:00 p.m. Saturday, 1:00 p.m. to 9:00 p.m. Sunday at a rate of $3.00 per hour and for a maximum period of 3 hours, on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 5. City Council rescind the existing no stopping regulation in effect from 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. Monday to Friday, except public holidays, on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 6. City Council rescind the existing no stopping regulation in effect from 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. Monday to Friday, except public holidays, on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 7. City Council prohibit stopping at all times on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 8. City Council prohibit stopping at all times on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 9. City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed, to keep clear of any construction debris and made safe. 10. City Council direct the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrian, cyclist and motorist safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct that King Street East be returned to its pre-construction traffic and parking regulations when the project is complete. 19. City Council direct the applicant to construct and maintain a fully covered, protected, unobstructed, and wheelchair accessible pedestrian walkway for the entire duration of the construction staging area permit, at their sole cost. 20. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 21. City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 22. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes. 23. City Council direct the Director, Traffic Management, Transportation Services and the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, local resident groups, local BIAs, and local school administration. 24. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents' association, and Business Improvement Area Board of Management.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of a 1.5 metre-wide portion of the north sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, from May 12, 2022 to November 30, 2022. 2. City Council authorize the closure of a 0.7 metre-wide portion of the north sidewalk on King Street East, between a point 58.6 metres west of Berkeley Street and a point 24.5 metres further west, from December 1, 2022 to December 31, 2024. 3. City Council rescind the existing parking machine regulation in effect from 9:00 a.m. to 4:00 p.m. , 6:00 p.m. to 9:00 p.m. Monday to Friday, 8:00 a.m. to 9:00 p.m. Saturday, 1:00 p.m. to 9:00 p.m. Sunday at a rate of $3.00 per hour and for a maximum period of 3 hours, on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 4. City Council rescind the existing parking machine regulation in effect from 9:00 a.m. to 4:00 p.m. and 6:00 p.m. to 9:00 p.m. Monday to Friday, 8:00 a.m. to 9:00 p.m. Saturday, 1:00 p.m. to 9:00 p.m. Sunday at a rate of $3.00 per hour and for a maximum period of 3 hours, on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 5. City Council rescind the existing no stopping regulation in effect from 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. Monday to Friday, except public holidays, on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 6. City Council rescind the existing no stopping regulation in effect from 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. Monday to Friday, except public holidays, on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 7. City Council prohibit stopping at all times on the north side of King Street East, between a point 37.8 metres west of Berkeley Street and a point 57.4 metres further west. 8. City Council prohibit stopping at all times on the south side of King Street East, between a point 67.5 metres west of Berkeley Street and a point 12.5 metres further west. 9. City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways daily, or more frequently as needed, to keep clear of any construction debris and made safe. 10. City Council direct the applicant to ensure that the existing sidewalks and/or any proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 11. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 12. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrian, cyclist and motorist safety is considered at all times. 13. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 14. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 15. City Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 16. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 17. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 18. City Council direct that King Street East be returned to its pre-construction traffic and parking regulations when the project is complete.
TE32.49amended
Construction Staging Area Time Extension - 6-16 Wellesley Street West and 5-7 St. Nicholas Street
As the Toronto Transit Commission (TTC) operates a transit service on Wellesley Street West, City Council approval of this report is required. In addition, this report proposes extending the duration of the temporary removal of the cycle track on the north side of Wellesley Street West abutting the development. Based on these conditions, this matter requires final approval by City Council. Wellesley Street Nicholas Residences Limited Partnership is constructing a 55-storey residential development building at 6-16 Wellesley Street West and 5-7 St. Nicholas Street. The site is located on the north side of Wellesley Street West, west of Yonge Street between Bistro Lane and St. Nickolas Street. The north sidewalk and a 2.3-metre-wide portion of the westbound curb lane/cycle track on Wellesley Street West, between Bistro Lane and St. Nicholas Street is currently closed to accommodate construction staging operations for the development. In addition, St. Nicholas Street is closed in its entirety, between Wellesley Street West and a point 43 metres north. City Council, at its meeting on June 8, 2021, approved the subject construction staging areas from July 1, 2021 to June 30, 2022. At the time, the developer indicated they would require the staging area for a total of 54 months, from July 1, 2021 to December 31, 2025. As the previous permit was only approved for a 12-month period, the developer has requested an extension of the duration of the construction staging areas on Wellesley Street West and St. Nicholas Street in order to complete the construction of the development. Transportation Services is requesting authorization to extend the duration of the construction staging areas on Wellesley Street West and St. Nicholas Street for an additional 31 months, from July 1, 2022 to January 31, 2025, to allow for the construction of the development to be completed.
The Toronto and East York Community Council recommends that: 1. City Council authorize the continuation of the closure of the north sidewalk and a 2.3-metre-wide portion of the westbound curb lane on Wellesley Street West, between Bistro Lane and St. Nicholas Street, and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane from July 1, 2022 to June 30, 2023. 2. City Council authorize the continuation of the closure of all of St. Nicholas Street, between Wellesley Street West and a point 43 metres north, from July 1, 2022 to June 30, 2023. 3. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 4. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. City Council direct the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 9. City Council direct the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 10. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 11. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 12. City Council direct the applicant to continue construction management working group monthly meetings, and inviting local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, and local resident groups. 13. City Council direct that Wellesley Street West and St. Nicholas Street be returned to its pre-construction traffic and parking regulations when the project is complete. 14. City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the construction site hoarding, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 15. City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe. 16. City Council direct the applicant to mitigate light pollution by installing a shield/barrier on any lighting standards in close proximity to adjacent residential properties, such as cranes. 17. City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, install sharrow markings onto the roadway, and display appropriate signage to inform drivers and cyclists to safely share the road. 18. City Council direct the applicant to email monthly construction progress reports to the local Councillor, local residents' association, and Business Improvement Area Board of Management.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the continuation of the closure of the north sidewalk and a 2.3-metre-wide portion of the westbound curb lane on Wellesley Street West, between Bistro Lane and St. Nicholas Street, and provision of a temporary pedestrian walkway within the closed portion of the eastbound curb lane from July 1, 2022 to January 31, 2025. 2. City Council authorize the continuation of the closure of all of St. Nicholas Street, between Wellesley Street West and a point 43 metres north, from July 1, 2022 to January 31, 2025. 3. City Council direct the applicant to pressure wash (or sweep during winter weather conditions) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 4. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 5. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 6. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 7. City Council direct the applicant to continue providing a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 9. City Council direct the applicant to continue installing cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 10. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 11. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 12. City Council direct the applicant to continue construction management working group monthly meetings, and inviting local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Buildings, adjacent neighbours, and local resident groups. 13. City Council direct that Wellesley Street West and St. Nicholas Street be returned to its pre-construction traffic and parking regulations when the project is complete.
TE32.50adopted
As the Toronto Transit Commission (TTC) operates a transit service on Cherry Street, City Council approval of this report is required. As part of the Port Lands Flood Protection Project and Enabling Infrastructure Project, Waterfront Toronto has undertaken the construction of the Cherry Street re-alignment, between Lake Shore Boulevard East and Polson Street. A construction staging area has been set-up on the west side of Cherry Street and the north side of Polson Street. In addition, a temporary detour (diversion) roadway has been fully constructed within the existing northbound lanes, east boulevard on Cherry Street, and within the additional lands on the east side of Cherry Street (leased from City of Toronto Economic Development Corporation) to accommodate northbound and southbound traffic around the construction staging area. City Council, at its meeting on May 28, 2020, authorized the subject construction staging area on Cherry Street, from June 29, 2020 to February 28, 2022. At the time, Waterfront Toronto indicated they would require the construction staging area for a total of 34 months. At its meetings on February 2, 2022, City Council subsequently authorized extending the duration of the construction staging area until May 31, 2022. Waterfront Toronto has requested an extension of the duration of the construction staging area on Cherry Street, in order to complete the construction of the Cherry Street re-alignment. Based on the information provided by Waterfront Toronto, the site has experienced additional construction delays due to dewatering challenges. Transportation Services is requesting authorization to extend the duration of the construction staging area and temporary detour (diversion) roadway until July 31, 2022 in order to complete the construction of the re-alignment.
The Toronto and East York Community Council: 1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic on the west sidewalk and two southbound lanes on Cherry Street between a point 55 metres south of Commissioners Street and a point 393.5 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 2. City Council authorize the continuation of the temporary closure to pedestrian traffic on the east sidewalk on Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 3. City Council authorize the continuation of the temporary closure to pedestrian and cycling traffic Martin Goodman Trail on the east side of Cherry Street, between a point 195 metres south of Commissioners Street and a point 263 metres further south, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 4. City Council authorize the continuation of the temporary closure to vehicular and pedestrian traffic each of the north boulevard and the 5.5 metre wide portion of the westbound lane on Polson Street, between Cherry Street and a point 83.5 metres west, from June 1, 2022 to July 31, 2022, inclusive, for purposes of the Port Lands Flood Protection Project and Enabling Infrastructure Project. 5. City Council direct that Waterfront Toronto continue to be responsible for all costs incurred with respect to road repairs and traffic signage modifications.