Award of Ariba Doc Number 2629175955 to OJCR Construction Ltd., for Part A and Part B for Repairs of Sewer Systems and Appurtenances at Various Locations for Toronto Water Division

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2020-11-10 · Bid Award Panel · adopted

As filed

The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (November 5, 2020) from the Chief Procurement Officer: Solicitation Number: Tender Call Number DOC 2629175955 (195-2020); Contract Number 20TW-DC-311OCS (Part A) and 20TW-DC-312OCS (Part B) Description: Request for Tender (RFT) Number 195-2020, for Repairs of Sewer Systems and Appurtenances for Various Locations within the City of Toronto 20TW-DC-311OCS (Part A) and 20TW-DC-312OCS (Part B) Initial award shall be from date of award to October 31, 2021 with the option to renew the contract for one (1) additional year period.

Show the rest of As filed, 2,015 more characters as filed

Should the option period be exercised, then the General Manager of Toronto Water will request the Chief Procurement Officer to process the renewal under the same terms and conditions. Recommended Supplier: Part A: OJCR Construction Ltd. Part B: OJCR Construction Ltd. Contract Award Value: Part A: From the date of award to October 31, 2021 $2,925,150 net of all applicable taxes and charges $3,305,419 including all applicable taxes and charges $2,976,633 net of HST recoveries Option Period 1 - November 1, 2021 to October 31, 2022 $3,012,904 net of all applicable taxes and charges $3,404,582 including all applicable taxes and charges $3,065,932 net of HST recoveries The total potential cost for Part A including the option period is $6,042,564 net of HST recoveries, $5,938,054 net of all taxes and charges and $6,710,002 including all applicable taxes and charges. Part B: From the date of award to October 31, 2021 $2,621,650 net of all applicable taxes and charges $2,962,464 including all applicable taxes and charges $2,667,791 net of HST recoveries Option Period 1 - November 1, 2021 to October 31, 2022 $2,700,299 net of all applicable taxes and charges $3,051,338 including all applicable taxes and charges $2,747,825 net of HST recoveries The total potential cost for Part B including the optional period is $5,415,616 net of HST recoveries, $5,321,949 net of all taxes and charges and $6,013,803 including all applicable taxes and charges. The total potential cost to the City including the optional period for both parts is $11,458,180 net of HST recoveries. The total potential contract award is $12,723,805 including all applicable taxes and charges, $11,260,003 net of all applicable taxes and charges. Contracts are expected to start on date of award and end on October 31, 2021 with the option to renew the Contract for one (1) additional separate one (1) year period. The above cost calculations for the Option Period(s) reflect an estimated 3% increase as per the Consumer Price Index (CPI).

On the agenda

As the city filed it

Solicitation Issued: September 25, 2020 Solicitation Closed: October 21, 2020 Number of Addenda Issued: One (1) Number of Bids: Six (6) Table 2: Summary of Bids Received for Tender Call Number DOC 2629175955 (Part A) including bid price Supplier Name Bid Price (including H.S.T.)* OJCR Construction Ltd. $3,022,919 614128 Ontario Ltd. o/a Trisan Construction $3,545,277 Rafat General Contractor Inc. $3,594,643 Vipe Construction Ltd.

Show the rest of As the city filed it, 653 more characters as filed

$4,218,572 Utility Force Construction Inc. $4,575,455 CRCE Construction Ltd. $5,321,452 *Pursuant to the Request for Tender document the contract award value includes contingency. Table 3: Summary of Bids received for Tender Call No. DOC2629175955 (Part B) including bid price Supplier Name Bid Price (including H.S.T.)* OJCR Construction Ltd. $2,679,964 Rafat General Contractor Inc. $2,974,499 614128 Ontario Ltd. o/a Trisan Construction $3,283,795 Vipe Construction Ltd. $4,055,287 Utility Force Construction Inc. $4,577,883 CRCE Construction Ltd. $4,797,697 *Pursuant to the Request for Tender document the contract award value includes contingency.

Staff recommended

The Chief Procurement Officer recommends that the Bid Award Panel grant authority to award the following contracts: Solicitation Number: Tender Call Number DOC 2629175955 (195-2020); Contract Number 20TW-DC-311OCS (Part A) and 20TW-DC-312OCS (Part B) Description: Request for Tender (RFT) Number 195-2020, for Repairs of Sewer Systems and Appurtenances for Various Locations within the City of Toronto 20TW-DC-311OCS (Part A) and 20TW-DC-312OCS (Part B) Initial award shall be from date of award to October 31, 2021 with the option to renew the contract for one (1) additional year period.

Show the rest of Staff recommended, 2,015 more characters as filed

Should the option period be exercised, then the General Manager of Toronto Water will request the Chief Procurement Officer to process the renewal under the same terms and conditions. Recommended Supplier: Part A: OJCR Construction Ltd. Part B: OJCR Construction Ltd. Contract Award Value: Part A: From the date of award to October 31, 2021 $2,925,150 net of all applicable taxes and charges $3,305,419 including all applicable taxes and charges $2,976,633 net of HST recoveries Option Period 1 - November 1, 2021 to October 31, 2022 $3,012,904 net of all applicable taxes and charges $3,404,582 including all applicable taxes and charges $3,065,932 net of HST recoveries The total potential cost for Part A including the option period is $6,042,564 net of HST recoveries, $5,938,054 net of all taxes and charges and $6,710,002 including all applicable taxes and charges. Part B: From the date of award to October 31, 2021 $2,621,650 net of all applicable taxes and charges $2,962,464 including all applicable taxes and charges $2,667,791 net of HST recoveries Option Period 1 - November 1, 2021 to October 31, 2022 $2,700,299 net of all applicable taxes and charges $3,051,338 including all applicable taxes and charges $2,747,825 net of HST recoveries The total potential cost for Part B including the optional period is $5,415,616 net of HST recoveries, $5,321,949 net of all taxes and charges and $6,013,803 including all applicable taxes and charges. The total potential cost to the City including the optional period for both parts is $11,458,180 net of HST recoveries. The total potential contract award is $12,723,805 including all applicable taxes and charges, $11,260,003 net of all applicable taxes and charges. Contracts are expected to start on date of award and end on October 31, 2021 with the option to renew the Contract for one (1) additional separate one (1) year period. The above cost calculations for the Option Period(s) reflect an estimated 3% increase as per the Consumer Price Index (CPI).