The filed record
Riverdale Park East Top of Bank Improvements
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-10-26 · Infrastructure and Environment Committee · adopted
As filed
The Infrastructure and Environment Committee received the report (October 6, 2021) from the General Manager, Parks, Forestry and Recreation for information.
On the agenda
As the city filed it
This report responds to the request from City Council at its meeting of April 28, 2021, for the General Manager, Parks, Forestry and Recreation to report on options for the scope of work for improvements to the top of the bank in Riverdale Park East. The Riverdale Park East hill is a popular all-season destination for Torontonians, and top of bank and sidewalk improvements have been identified to address congestion and erosion issues, enhance user experience, and improve access to one of Toronto's most outstanding viewpoints.
Show the rest of As the city filed it, 2,320 more characters as filed
Improvements to Broadview Avenue along Riverdale Park East would also support recommendations within the Lower Don Trail Master Plan Refresh which identifies Broadview Avenue as the "Eastern Parallel Route", an alternate route for the Lower Don Trail. PFR staff conducted a preliminary site analysis and prepared preliminary concept sketches to determine an appropriate scope of work for future improvements to the top of the bank in the park and other related circulation issues in proximity to this area. Through this work it was determined that improvements to the Riverdale Park East top of bank would aim to remediate erosion, expand the pedestrian pathway adjacent to the sidewalk, and define activity zones for different uses of the top of bank and hill (e.g. walking, exercising, sitting, etc.), including by creating stepped seating zones that would serve as both gathering and viewing areas. Accessibility will be addressed through design development. Efforts will be made to ensure the future design minimizes impacts on the hill's current appearance, and includes materials that reflect the industrial and natural characteristics of the Don Valley. This project will require additional technical investigations, pre-engineering work, and public engagement activities prior to initiating design. Staff will begin carrying out this work through 2022 with the aim of issuing a Request for Proposals for detailed design works in late 2022, beginning design in 2023, and targeting construction for 2024. This schedule avoids conflict with Toronto Water works along Broadview Avenue, which are anticipated to be completed in early summer 2022 and Toronto Transit Commission track work that is planned for construction and completion in 2023. Moving forward with improvements to the Riverdale top of bank prior to the completion of the above-noted works in the road right-of-way by Toronto Water and the Toronto Transit Commission is not recommended. Proceeding with top of bank construction work which will also extend into the pedestrian zone of the road right-of-way concurrently with other road right-of-way works poses a number of issues that would be difficult to mitigate and are likely to cause project delays, increased project costs and safety issues for both pedestrian and vehicular traffic circulation.
Staff recommended
The General Manger, Parks, Forestry and Recreation recommends that: 1. The Infrastructure and Environment Committee receive this report for information.
On the record
More from this meeting
- Amendment to Purchase Order Number 6052180 with WSP Canada Incorporated for the Construction of Multiple Culverts at Various LocationsFiled record
- Amendment to Purchase Order Number 6047920, Tender Call Number 257-2018 to OJCR Construction Limited for Repairs of Sewer Service Connections, Catch Basins and Appurtenances for Various Locations Toronto, East York and Scarborough DistrictsFiled record
- Award of Request for Quotation Ariba Document Number 3047717744 to GFL Environmental Incorporated for Curbside Collection Services in Etobicoke Area (District 1)Filed record
- Non-Competitive Contract with Evoqua Water Technologies Limited for the Purchase of Proprietary Essential Parts for Maintenance of Process Equipment at Water Treatment PlantsFiled record
- Non-Competitive Contract with Forests Ontario to Implement the Tree Seed Diversity Program 2022-2031 for Parks, Forestry and RecreationFiled record
- Non-Competitive Contract with IBI Group Professional Services Canada Incorporated for the Support and Maintenance, Graphic User Interface Enhancements and Control Strategy Component Upgrades of the Transmission Operations Optimizer Proprietary System SoftwareFiled record