Construction Staging Area - 75 Broadway Avenue
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2021-11-09 · Toronto City Council · adopted
As filed
City Council on November 9, 10 and 12, 2021, adopted the following: 1. City Council authorize the closure of the south sidewalk and a 2.7 metre-wide portion of the westbound south-side curb lane on Broadway Avenue, between a point 71.5 metres west of Redpath Avenue and a point 40.5 metres further west, for a period of 12 months from March 1, 2022 to February 28, 2023. 2. City Council direct the applicant to pressure-wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of As filed, 1,962 more characters as filed
3. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 5. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to install cane-detection within the covered and protected walkway to guide pedestrians who are visually impaired. 9. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 10. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
The vote
Adopt Item · Carried, 24-0
The whole record, all 26 members
- Ana BailãoFor
- Anthony PerruzzaFor
- Brad BradfordFor
- Cynthia LaiFor
- Denzil Minnan-WongFor
- Frances NunziataFor
- Gary CrawfordFor
- Gord PerksFor
- James PasternakFor
- Jaye RobinsonFor
- Jennifer McKelvieFor
- Joe CressyFor
- John FilionFor
- John ToryAbsent
- Josh MatlowFor
- Kristyn Wong-TamFor
- Mark GrimesFor
- Michael FordFor
- Michael ThompsonFor
- Mike ColleFor
- Mike LaytonFor
- Nick MantasAbsent
- Paul AinslieFor
- Paula FletcherFor
- Shelley CarrollFor
- Stephen HolydayFor
Every name opens that member’s record.
On the agenda
As the city filed it
This report is submitted to Infrastructure and Environment Committee as Broadway Avenue forms a shared boundary between the Toronto and East York Community Council and the North York Community Council. Hazelview Investments is demolishing a portion of the existing 10-storey building at 73-75 Broadway Avenue and constructing one 38-storey residential rental tower at 73 Broadway Avenue that will be connected to the remaining portion of 75 Broadway Avenue through the common first-floor and underground parking.
Show the rest of As the city filed it, 1,106 more characters as filed
The site is located on the south side of Broadway Avenue, mid-block between Yonge Street and Redpath Avenue. The developer's anticipated timeline to require a closure of the south sidewalk and a 2.7 metre-wide portion of the westbound south-side curb lane on Broadway Avenue, between a point 71.5 metres west of Redpath Avenue and a point 40.5 metres further west, is for a period of 42 months (i.e., March 1, 2022 to August 31, 2025) to accommodate a construction staging area. Transportation Services is recommending that we provide an initial construction staging permit for 12 months (i.e., March 1, 2022 to February 28, 2023). We will monitor the need for construction staging and will arrange to extend the permit duration in the future as we deem necessary. Pedestrian operations on the south side of Broadway Avenue will be maintained in a 2.1 metre-wide covered and protected walkway within the closed portion of the existing lane. The construction staging area on Broadway Avenue will result in the partial occupation of the westbound traffic lane, resulting in a 6.0 metre-wide lane for traffic.
Staff recommended
The General Manager, Transportation Services recommends that: 1. City Council authorize the closure of the south sidewalk and a 2.7 metre-wide portion of the westbound south-side curb lane on Broadway Avenue, between a point 71.5 metres west of Redpath Avenue and a point 40.5 metres further west, for a period of 12 months from March 1, 2022 to February 28, 2023. 2. City Council direct the applicant to pressure-wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of Staff recommended, 1,962 more characters as filed
3. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 5. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to install cane-detection within the covered and protected walkway to guide pedestrians who are visually impaired. 9. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 10. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
Considered
2021-10-26 · Infrastructure and Environment Committee · adopted
Decision as filed
The Infrastructure and Environment Committee recommends that: 1. City Council authorize the closure of the south sidewalk and a 2.7 metre-wide portion of the westbound south-side curb lane on Broadway Avenue, between a point 71.5 metres west of Redpath Avenue and a point 40.5 metres further west, for a period of 12 months from March 1, 2022 to February 28, 2023. 2. City Council direct the applicant to pressure-wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.
Show the rest of Decision as filed, 1,962 more characters as filed
3. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkways have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 4. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 5. City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 6. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 7. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to install cane-detection within the covered and protected walkway to guide pedestrians who are visually impaired. 9. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 10. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
2021-11-09 · Toronto City Council · adopted
On the record
More from this meeting
- Amendment to Purchase Order Number 6052180 with WSP Canada Incorporated for the Construction of Multiple Culverts at Various LocationsFiled record
- Amendment to Purchase Order Number 6047920, Tender Call Number 257-2018 to OJCR Construction Limited for Repairs of Sewer Service Connections, Catch Basins and Appurtenances for Various Locations Toronto, East York and Scarborough DistrictsFiled record
- Award of Request for Quotation Ariba Document Number 3047717744 to GFL Environmental Incorporated for Curbside Collection Services in Etobicoke Area (District 1)Filed record
- Non-Competitive Contract with Evoqua Water Technologies Limited for the Purchase of Proprietary Essential Parts for Maintenance of Process Equipment at Water Treatment PlantsFiled record
- Non-Competitive Contract with Forests Ontario to Implement the Tree Seed Diversity Program 2022-2031 for Parks, Forestry and RecreationFiled record
- Non-Competitive Contract with IBI Group Professional Services Canada Incorporated for the Support and Maintenance, Graphic User Interface Enhancements and Control Strategy Component Upgrades of the Transmission Operations Optimizer Proprietary System SoftwareFiled record