TE23.26deferred
1 Bloor Street West (Yonge Street at Bloor Street West) - Construction Staging Area Time Extension
As the Toronto Transit Commission (TTC) operates a transit service on Yonge Street, City Council approval of this report is required. Mizrahi Development Group (The One) Inc. (the "developer") is currently the owner of a mixed-use development at 1 Bloor Street West (Mizrahi Project). The site is located on the southwest corner of Yonge Street and Bloor Street West. The development will consist of an eight-storey high retail podium and an 86-storey high residential tower. By way of background, Toronto and East York Community Council, at its meeting on November 25 and 26, 2020, approved the construction staging area on Balmuto Street from November 30, 2020 to November 30, 2022. In a separate meeting on March 10, 2021, Toronto and East York Community Council approved an extension of the construction staging areas on Yonge Street and Bloor Street West from September 1, 2020 to December 31, 2021. In a meeting on December 14 and 15, 2022, City Council approved an extension of the construction staging areas on Yonge Street, Bloor Street West and Balmuto Street, from December 14, 2022 to March 31, 2023. At the time, the developer indicated they would require the staging areas until June 30, 2025. At its meeting on March 29, 2023, City Council approved an extension of the construction staging areas on Yonge Street, and Bloor Street West, from April 1, 2023 to June 30, 2025, however for Balmuto Street an extension was approved for only one year from April 1, 2023 to April 1, 2024. At a later meeting on July 24 and 25, 2024, City Council approved an extension request for the construction staging area on Balmuto Street from August 1, 2024 to February 1, 2026. The developer is now requesting an extension for the duration of the construction staging on Yonge Street, as the development has experienced delays due to the project going into receivership and has undergone a transition of both development manager and construction manager. Transportation Services is requesting authorization to extend the duration of the construction staging area on Yonge Street for an additional 36 months, from June 30, 2025 to June 30, 2028 to allow for the construction of the development to be completed. It should be noted that the temporary covered and protected walkways within the closed southbound curb lane on Yonge Street and eastbound curb lane on Bloor Street West have been removed. Currently, pedestrian movements are maintained within the existing sidewalks, abutting the site.
The Toronto and East York Community Council: 1. Deferred consideration of the Item until the July 8, 2025 meeting of the Toronto and East York Community Council.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize, for purposes of construction at 1 Bloor Street West the temporary closure to pedestrian traffic of the west sidewalk and to vehicular traffic of a 3 metre wide portion of the southbound curb lane, on Yonge Street, between Bloor Street West and a point 66 metres south, from June 30, 2025 to June 30, 2028, inclusive. 2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 4. City Council direct the applicant to continue sweeping the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe. 5. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night. 6. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 7. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 8. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Traffic Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 9. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. City Council direct that, Bloor Street West and Yonge Street be returned to their pre-construction traffic regulations and lane configurations when the project is completed.
TE23.27adopted
30 Merton Street - Construction Staging Area
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. QuadReal Property Group is constructing a 37-storey residential rental building at 30 Merton Street. The site is located on the northeast corner of Merton Street and Al Green Lane. Transportation Services is requesting authorization to temporarily close a portion of the westbound curb lane and the north sidewalk on Merton Street for a period of 25 months, from June 6, 2025 to June 30, 2027, in order to enable construction staging operations for the development. Pedestrians will be redirected into a 1.8 metre wide covered and protected walkway within the closed portion of the westbound lane on the north side of Merton Street.
The Toronto and East York Community Council: 1. Authorized the closure of the north sidewalk and a 4.3 metre-wide portion of the westbound curb lane on Merton Street, between Al Green Lane and a point 57 metres east, and a provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from June 6, 2025 to June 30, 2027 inclusive. 2. Rescinded the existing parking prohibition in effect at all times on the north side of Merton Street, between Yonge Street and a point 83.8 metres east. 3. Prohibited stopping at all times on the north side of Merton Street, between a point 53 metres east of Yonge Street and a point 72 metres further east. 4. Rescinded the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m. Sunday at a rate of $4.25 per hour and for a maximum of 3 hours, on the south side of Merton Street, between a point 83.8 metres east of Yonge Street and a point 41 metres further east. 5. Rescinded the existing parking prohibition in effect at all times on the south side of Merton Street, between a point 53 metres east of Yonge Street and a point 98 metres further east. 6. Prohibited stopping at all times on the south side of Merton Street, between a point 53 metres east of Yonge Street and a point 98 metres further east. 7. Directed the applicant to pressure wash or sweep (weather permitting) the construction site, adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 8. Directed the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act. 9. Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 10. Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local Business Improvement Areas and resident associations in advance of any physical road modifications. 11. Directed the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 12. Directed the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 13. Directed the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and the Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 14. Directed the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 15. Directed the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 16. Directed the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 17. Directed the applicant to provide monthly community meetings to discuss any concerns raised by the community. 18. Directed that the traffic median on the south side of Merton Street at a point 79.5 metres east of Yonge Street be reconstructed when the project is complete. 19. Directed that Merton Street be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. Toronto and East York Community Council authorize the closure of the north sidewalk and a 4.3 metre-wide portion of the westbound curb lane on Merton Street, between Al Green Lane and a point 57 metres east, and a provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from June 6, 2025 to June 30, 2027 inclusive. 2. Toronto and East York Community Council rescind the existing parking prohibition in effect at all times on the north side of Merton Street, between Yonge Street and a point 83.8 metres east. 3. Toronto and East York Community Council prohibit stopping at all times on the north side of Merton Street, between a point 53 metres east of Yonge Street and a point 72 metres further east. 4. Toronto and East York Community Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 9:00 p.m., Monday to Saturday; and 1:00 p.m. to 9:00 p.m. Sunday at a rate of $4.25 per hour and for a maximum of 3 hours, on the south side of Merton Street, between a point 83.8 metres east of Yonge Street and a point 41 metres further east. 5. Toronto and East York Community Council rescind the existing parking prohibition in effect at all times on the south side of Merton Street, between a point 53 metres east of Yonge Street and a point 98 metres further east. 6. Toronto and East York Community Council prohibit stopping at all times on the south side of Merton Street, between a point 53 metres east of Yonge Street and a point 98 metres further east. 7. Toronto and East York Community Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 8. Toronto and East York Community Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act. 9. Toronto and East York Community Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 10. Toronto and East York Community Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 11. Toronto and East York Community Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 12. Toronto and East York Community Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 13. Toronto and East York Community Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 14. Toronto and East York Community Council direct the applicant to install cane detection within the covered and protected walkway to guide pedestrians who are visually impaired. 15. Toronto and East York Community Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 16. Toronto and East York Community Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 17. Toronto and East York Community Council direct the applicant to provide monthly community meetings, to discuss any concerns raised by the community. 18. Toronto and East York Community Council direct that the traffic median on the south side of Merton Street at a point 79.5 metres east of Yonge Street be reconstructed when the project is complete. 19. Toronto and East York Community Council direct that Merton Street be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.
TE23.28deferred
1134 Queen Street East - Construction Staging Area
As the Toronto Transit Commission (TTC) operates a transit service on Queen Street East, City Council approval of this report is required. Elcium Construction Management Corp. is constructing a 3-storey condominium with ground floor retail at 1134 Queen Street East. The site is located on the north side of Queen Street East, between Bertmount Avenue and Coady Avenue. Transportation Services is requesting authorization to temporarily close a portion of the westbound curb lane with the provision of a temporary pedestrian walkway on the north side of Queen Street East for a period of 15 months, from July 1, 2025 to September 30, 2026, in order to facilitate constructions staging operations. Traffic control persons will be directing pedestrians on the north side during construction hours and a temporary pedestrian walkway will be maintained outside of construction hours.
The Toronto and East York Community Council: 1. Deferred consideration of the Item until the July 8, 2025 meeting of the Toronto and East York Community Council.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services, recommends that: 1. City Council authorize the closure of the north sidewalk and a 2.2-metre-wide portion of the westbound curb lane on Queen Street East, between a point 17 metres west of Bertmount Avenue and Coady Avenue, and a provision of a temporary pedestrian walkway within the closed portion of the westbound curb lane, from July 1, 2025 to September 30, 2026 inclusive. 2. City Council rescind the existing stopping prohibition in effect from 7:00 a.m. to 9:00 a.m., Monday to Friday, except public holidays, on the north side of Queen Street East, between a point 17 metres west of Bertmount Avenue and Coady Avenue. 3. City Council rescind the existing parking machine regulation in effect from 9:00 a.m. to 9:00 p.m., Monday to Friday, 8:00 a.m. to 9:00 p.m., Saturday; 1:00 p.m. to 9:00 p.m., Sunday at a rate of $3.00 per hour and for a maximum of three hours, on the north side of Queen Street East between a point 17 metres west of Bertmount Avenue and Coady Avenue. 4. City Council prohibit stopping at all times on the north side of Queen Street East, between a point 17 metres west of Bertmount Avenue and Coady Avenue. 5. City Council direct the applicant to pressure wash or sweep (weather permitting) the construction site and adjacent sidewalks and roadways daily, or more frequently as needed to be cleared of any construction debris and made safe. 6. City Council direct the applicant to construct and maintain a fully covered, protected and unobstructed walkway for all pedestrians, including for those with mobility devices, for the entire duration of the construction staging area permit to the satisfaction of the City engineer and ensure it is compliant with the Accessibility for Ontarians with Disabilities Act (AODA). 7. City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper enhanced lighting to ensure safety and visibility at all times of the day and night. 8. City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications. 9. City Council direct the applicant to install appropriate signage and request the applicant to install converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times. 10. City Council direct the applicant to provide a sufficient number of traffic control persons as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, on a daily basis to control construction vehicle access and egress to and from the site and maintain a safe environment for the public. 11. City Council direct the applicant to provide a sufficient number of pay-duty Police Officers as determined by the Work Zone Coordinator and Toronto Police Construction Liaison Officer, during large scale concrete pours and large-scale material deliveries to control vehicle access and egress to and from the site and maintain a safe environment for the public. 12. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site. 13. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor. 14. City Council direct that Queen Street East be returned to its pre-construction traffic and parking regulations (except with parking rates and hours of operation being consistent to the rates and hours of operation at the time of completion) when the project is complete.
TE23.29amended
Ontario Line - Construction Update - Second Quarter 2025
The purpose of this report is to provide updates on the status of construction activities on the Ontario Line project within the boundaries of Toronto and East York Community Council (TEYCC). This report includes updates on: - Station specific construction issues and status of the four major packages of work Metrolinx has awarded to deliver the Ontario Line (Rolling Stock, Systems, Operations and Maintenance; Southern Civil, Stations and Tunnel; Elevated Guideway and Stations; and Pape Tunnel and Underground Stations). - A summary of Metrolinx's responses and actions to implement the Subcommittee on Metrolinx's Ontario Line Construction Recommendations. - A summary of Metrolinx's outreach for residents that require a Pre-condition survey/Building Condition Assessment and the uptake rate for the assessments. - Other items related to the Ontario Line, including heavy truck safety plans and haul routes, station-naming, business supports and community engagement.
The Toronto and East York Community Council recommends that: 1. City Council direct the Deputy City Manager, Infrastructure Services, in consultation with the Executive Director, Transit Expansion, the General Manager, Transportation Services and the Chief Executive Officer, Toronto Transit Commission, to ensure that the Strategic Capital Coordination Office assume primary internal responsibility for coordination between City divisions and agencies on interfacing City capital projects to mitigate congestion and ensure efficient coordination of projects related to Ontario Line construction. 2. City Council direct the General Manager, Transportation Services and the Executive Director, Transit Expansion to work with Metrolinx to assess opportunities as part of the implementation of the Truck Haul Route Plan for Exhibition Station, and report back to the July 8, 2025 meeting of the Toronto and East York Community Council with recommendations and details on: a. avoiding onward northbound heavy truck traffic on Dufferin Street beyond Queen Street West; b. ensuring that future changes are coordinated with the planned implementation of transit priority measures on Dufferin Street and measures in the Congestion Management Plan; and c. an expanded map to show the full onward direction of travel for the Haul Route. 3. City Council direct the General Manager, Transportation Services, the Executive Director, Transit Expansion and the Chief Engineer and Executive Director, Engineering and Construction Services to work with Metrolinx to ensure that, prior to any haul route use, Metrolinx completes a detailed structural assessment of the Dufferin Street Bridge over the GO rail corridor, a temporary modular bridge that has exceeded its intended service life, to determine the number of construction trucks, truck loading and overall structural capacity in light of the anticipated use for the Ontario Line construction haulage, and further, that Metrolinx completes any necessary strengthening or interim remedial work identified through the assessment to ensure the bridge remains safe for general traffic and haul route operations until a full replacement or rehabilitation of the bridge can be undertaken. 4. City Council direct the Executive Director, Transit Expansion to request Metrolinx to immediately install an acoustic shelter for the south construction site of the Ontario Line Queen-Spadina Station, to address the significant noise and dust impacts to the surrounding community. 5. City Council direct the Executive Director, Transit Expansion to reiterate City Council's requests to Metrolinx on Community Benefits through Items 2023.TM2.1 and 2024.TE10.40, and furthermore request Metrolinx take the follow actions: a. identify concrete actions and opportunities to increase rates of local hiring for the construction of the Ontario Line; b. increase transparency and public reporting for Metrolinx's Community Benefits and Supports Program by releasing data that is broken down by project and provided semi-annually; and c. establish clear governance for the Toronto Stakeholder Working Group and convene meetings on a quarterly basis.
Staff recommendation as filed
The Executive Director, Transit Expansion recommends that: 1. Toronto and East York Community Council receive this report for information.
TE23.30deferred
Geary Avenue Mobility and Public Realm Strategy Update
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. The Geary Works Planning Study, concluded in 2021, was a comprehensive interdivisional study and community vision for Geary Avenue, and included a Mobility and Public Realm Strategy and provided ten (10) strategic directions for the right-of-way and streetscape on Geary Avenue. This report contains a status update and outline of the pathway for implementation of all ten strategic directions, in response to a request from Toronto and East York Community Council.
The Toronto and East York Community Council: 1. Deferred consideration of the Item until the July 8, 2025 meeting of the Toronto and East York Community Council.
Staff recommendation as filed
The Director, Planning, Design and Management, Transportation Services recommends that: 1. Toronto and East York Community Council receive this report for information.
TE23.31adopted
Accessible Parking Spaces - June 2025 (Delegated)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is requesting approval for the installation/removal of on-street accessible parking spaces for persons with disabilities.
The Toronto and East York Community Council: 1. Authorized the installation/removal of on-street accessible parking spaces at the locations identified in Attachment 1 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the installation/removal of on-street accessible parking spaces at the locations identified in Attachment 1 and attached to the report entitled "Accessible Parking Spaces - June 2025 (Delegated)", dated May 20, 2025, from the Director, Traffic Management, Transportation Services.
TE23.32adopted
Dundas Street West - Accessible Loading Zone
As the Toronto Transit Commission (TTC) operates a transit service on Dundas Street West, City Council approval of this report is required. Transportation Services is requesting approval for the installation of a designated on-street accessible loading zone on the north side of Dundas Street West, between Keele Street and Pacific Avenue. The accessible loading zone will operate at all times except from 4:00 p.m. to 6:00 p.m., Monday to Friday. The establishment of this accessible loading zone will provide unimpeded curbside access for the Wheel-Trans users and accessible permit holders visiting the Community Junction located at 2934 Dundas Street West. During the investigation, Transportation Services discovered a discrepancy between the by-lawed parking regulations and the posted signage on the north side of Dundas Street West. Recommendation 5 will rectify this inconsistency.
The Toronto and East York Community Council recommends that: 1. City Council designate an accessible loading zone to be in effect at all times, except from 4:00 p.m. to 6:00 p.m., Monday to Friday, on the north side of Dundas Street West, between a point 86 metres east of Pacific Avenue and a point 11 metres further east. 2. City Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 4:00 p.m., and from 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours, on the north side of Dundas Street West, between Quebec Avenue and Indian Grove. 3. City Council authorize the installation of parking machines on the north side of Dundas Street West, between Quebec Avenue and a point 86 metres east of Pacific Avenue, to be in effect from 8:00 a.m. to 4:00 p.m., and from 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours. 4. City Council authorize the installation of parking machines on the north side of Dundas Street West, between a point 97 metres east of Pacific Avenue and Indian Grove, to be in effect from 8:00 a.m. to 4:00 p.m., and 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours. 5. City Council rescind the existing parking prohibition in effect from 7:00 a.m. to 6:00 p.m., except Sunday, and public holidays, on the north side of Dundas Street West, between Keele Street and a point 32 metres west.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council designate an accessible loading zone to be in effect at all times, except from 4:00 p.m. to 6:00 p.m., Monday to Friday, on the north side of Dundas Street West, between a point 86 metres east of Pacific Avenue and a point 11 metres further east. 2. City Council rescind the existing parking machine regulation in effect from 8:00 a.m. to 4:00 p.m., and from 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours, on the north side of Dundas Street West, between Quebec Avenue and Indian Grove. 3. City Council authorize the installation of parking machines on the north side of Dundas Street West, between Quebec Avenue and a point 86 metres east of Pacific Avenue, to be in effect from 8:00 a.m. to 4:00 p.m., and from 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours. 4. City Council authorize the installation of parking machines on the north side of Dundas Street West, between a point 97 metres east of Pacific Avenue and Indian Grove, to be in effect from 8:00 a.m. to 4:00 p.m., and 6:00 p.m. to 12:00 a.m., Monday to Friday, from 8:00 a.m. to 9:00 p.m., Saturday, and from 1:00 p.m. to 9:00 p.m., Sunday, at a rate of $3.00 per hour and for a maximum period of three hours. 5. City Council rescind the existing parking prohibition in effect from 7:00 a.m. to 6:00 pm., except Sunday, and public holidays, on the north side of Dundas Street West, between Keele Street and a point 32 metres west.
TE23.33adopted
Pay-and-Display Parking - Various Streets - June 2025 (Delegated)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Toronto Parking Authority (TPA) has worked with Transportation Services to identify new on-street paid parking opportunities in Wards 9 and 14 that will support the local community and area businesses by encouraging a regular turnover in the on-street parking supply. Through this review, Transportation Services is requesting approval for the installation of on-street paid parking at various locations in Wards 9 and 14. The proposed parking changes will replace the existing parking restrictions currently in effect, including no parking, no stopping, and restricted one-hour or unpaid parking. The proposed changes will not impact the flow of traffic and will encourage parking turnover. While this report seeks Community Council approval for the installation of on-street paid parking in various locations in Wards 9 and 14, this is an ongoing initiative, and Transportation Services and TPA will continue to review and report on potential new on-street paid parking opportunities throughout the City of Toronto. A companion report, titled "Pay-and-Display Parking - Various Streets - June 2025 (Non-Delegated)" outlines the non-delegated parking amendments for streets in Wards 9 and 14.
The Toronto and East York Community Council: 1. Authorized amendments to parking regulations required to establish new on-street paid parking locations as set out in Attachments 2 and 3 to the revised report (May 29, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the amendments to parking regulations required to establish new on-street paid parking locations, as set out in Attachments 2 and 3, to the report "Pay-and-Display Parking - Various Streets - June 2025 (Delegated)", dated May 20, 2025 from the Director, Traffic Management, Transportation Services.
TE23.34adopted
Pay-and-Display Parking - Various Streets - June 2025 (Non-Delegated)
As the Toronto Transit Commission (TTC) operates a transit service on the streets in this report, City Council approval of this report is required. Toronto Parking Authority (TPA) has worked with Transportation Services to identify new on-street paid parking opportunities in Wards 9 and 14 that will support the local community and area businesses, by encouraging a regular turnover in the on-street parking supply. Through this review, Transportation Services is requesting approval for the installation of on-street paid parking at various locations in Wards 9 and 14. The proposed parking changes will replace the existing parking restrictions currently in effect, including no stopping. The proposed changes will not impact the flow of traffic and will encourage parking turnover. While this report seeks Community Council approval for the installation of on-street paid parking in various locations in Ward 14, this is an ongoing initiative; Transportation Services and TPA will continue to review and report on potential new on-street paid parking opportunities throughout the City of Toronto. Additionally, this report seeks the removal of existing paid parking on St. Clair Avenue West in Ward 9 at the request of the Ward Councillor, based on community feedback. A companion report, titled "Pay and Display Parking - Various Streets - June 2025 (Delegated)" outlines the delegated parking amendments for streets in Wards 9 and 14.
The Toronto and East York Community Council recommends that: 1. City Council authorize the amendments to parking regulations required to remove existing on-street paid parking or establish new on-street paid parking locations as set out in Attachments 2 and 3 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize the amendments to parking regulations required to remove existing on-street paid parking or establish new on-street paid parking locations, as set out in Attachments 2 and 3, to the report "Pay-and-Display Parking - Various Streets - June 2025 (Non-Delegated)", dated May 20, 2025 from the Director, Traffic Management, Transportation Services.
TE23.35amended
Draper Street - Streetscape Improvements and Parking By-law Amendments
Draper Street between Front Street West and Wellington Street West is scheduled for watermain replacement, road reconstruction, and streetscape improvements in 2025. Transportation Services is recommending shifting on-street parking from the east side of Draper Street to the west side in order to accommodate various streetscape improvements planned along the length of Draper Street. The proposed amendment would not result in the loss of any on-street parking spaces.
The Toronto and East York Community Council: 1. Approved amendments to the Traffic and Parking By-laws for Draper Street between Wellington Street West and Front Street West as described in Attachment 1 to motion by Deputy Mayor Ausma Malik.
Staff recommendation as filed
The Director, Planning, Design and Management, Transportation Services recommends that: 1. Toronto and East York Community Council approve amendments to the Traffic and Parking By-laws for Draper Street between Wellington Street West and Front Street West as described in Attachment 2 to the report (April 10, 2025) from the Director, Planning, Design and Management, Transportation Services.
TE23.36adopted
Front Street West - Parking Amendments
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of on-street paid parking within the newly constructed lay-bys on the north side of Front Street West, between Spadina Avenue and Draper Street. These changes will formalize the parking regulations following the completion of The Well development and reinstate short-term parking in the area. Paid parking will be permitted within the lay-bys only, with a standing prohibition at anytime applying outside of the lay-bys, allowing for passenger pick-up and drop-off activities.
The Toronto and East York Community Council: 1. Authorized amendments to parking regulations on Front Street West as described in Attachment 1 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the amendments to parking regulations on Front Street West, as described in "Attachment 1 - Parking Amendments - Front Street West".
TE23.37amended
Lippincott Street - Parking Amendments
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. The Ward Councillor has received numerous complaints from area residents and local businesses regarding vehicles parking on both sides of Lippincott Street, between Bloor Street West and Lennox Street. This activity negatively impacts sightlines, traffic flow and pedestrian safety. In particular, tour buses are parking long-term at Lippincott Street and Bloor Street West, impacting traffic operations at this intersection and pedestrian safety. Transportation Services recommends enhancing the current parking regulations on this section of Lippincott Street to further deter on-street parking. In addition, staff are recommending the establishment of a Commercial Loading Zone on the west side of Lippincott Street, south of Bloor Street West, to accommodate the necessary loading/unloading requirements for local businesses.
The Toronto and East York Community Council: 1. Rescinded the existing parking prohibition in effect at all times on both sides of Lippincott Street, between Bloor Street West and Lennox Street. 2. Prohibited stopping at all times on the west side of Lippincott Street, between Bloor Street West and a point 35 metres south. 3. Prohibited stopping at all times on the east side of Lippincott Street, between Bloor Street West and a point 58 metres south. 4. Designated a commercial loading zone to be in effect at all times on the west side of Lippincott Street, between a point 35 metres south of Bloor Street West and a point 9 metres further south. 5. Prohibited standing at all times on the east side of Lippincott Street, between a point 58 metres south of Bloor Street West and Lennox Street. 6. Prohibited standing at all times on the west side of Lippincott Street, between a point 44 metres south of Bloor Street West and Lennox Street.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council rescind the existing parking prohibition in effect at all times on both sides of Lippincott Street, between Bloor Street West and Lennox Street. 2. Toronto and East York Community Council prohibit stopping at all times on the west side of Lippincott Street, between Bloor Street West and a point 15 metres south. 3. Toronto and East York Community Council prohibit stopping at all times on the east side of Lippincott Street, between Bloor Street West and a point 58 metres south. 4. Toronto and East York Community Council designate a commercial loading zone to be in effect at all times on the west side of Lippincott Street, between a point 15 metres south of Bloor Street West and a point 15 metres further south. 5. Toronto and East York Community Council prohibit standing at all times on the east side of Lippincott Street, between a point 58 metres south of Bloor Street West and Lennox Street. 6. Toronto and East York Community Council prohibit standing at all times on the west side of Lippincott Street, between a point 30 metres south of Bloor Street West and Lennox Street.
TE23.38adopted
Front Street East and Jarvis Street - Parking Amendments
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. At the request of the Ward Councillor, in consultation with St. Lawrence Market North staff, Transportation Services reviewed commercial loading opportunities on Front Street East. These changes are intended to help facilitate this activity during events at the St. Lawrence Market North facility. In addition, staff reviewed enhancing the current parking regulations on the east side of Jarvis Street, between Front Street East and King Street East. These changes are intended to help minimise congestion and delays on this section of roadway for motorists entering/exiting the Toronto Parking Authority (TPA) underground parking facility, located on the west side of Jarvis Street. Transportation Services supports the requested changes and is recommending: - establishing a Commercial Loading Zone on the north side of Front Street East, west of Jarvis Street, that will operate at all times; and - prohibiting stopping at all times on the east side of Jarvis Street, between Front Street East and King Street East. The proposed parking amendments will help facilitate loading and unloading operations for businesses at St. Lawrence Market North on Front Street East and will deter all curbside activity from taking place on Jarvis Street, minimizing congestion during parking operations to/from the TPA underground parking facility. There will be no loss of on-street parking.
The Toronto and East York Community Council: 1. Rescinded the existing parking prohibition in effect at all times on the north side of Front Street East, between Jarvis Street and a point 72 metres west. 2. Amended the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., Monday to Friday, except public holidays, on the north side of Front Street East, between Jarvis Street and a point 88 metres west, to be in effect between a point 72 metres west of Jarvis Street and a point 16 metres further west. 3. Prohibited stopping at all times on the north side of Front Street East, between Jarvis Street and a point 30.5 metres west. 4. Designated a commercial loading zone to be in effect at all times on the north side of Front Street East, between a point 30.5 metres west of Jarvis Street and a point 17.5 metres further west. 5. Prohibited stopping at all times on the north side of Front Street East, between a point 48 metres west of Jarvis Street and a point 24 metres further west. 6. Amended the existing parking prohibition in effect at all times, except Sunday and public holidays, on the east side of Jarvis Street, between Front Street East and Adelaide Street East, to be in effect between King Street East and Adelaide Street East. 7. Amended the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., and from 3:30 p.m. to 6:30 p.m., Monday to Friday, except public holidays, on the east side of Jarvis Street, between Front Street East and Shuter Street, to be in effect between King Street East and Shuter Street. 8. Prohibited stopping at all times on the east side of Jarvis Street, between Front Street East and King Street East.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council rescind the existing parking prohibition in effect at all times on the north side of Front Street East, between Jarvis Street and a point 72 metres west. 2. Toronto and East York Community Council amend the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., Monday to Friday, except public holidays, on the north side of Front Street East, between Jarvis Street and a point 88 metres west, to be in effect between a point 72 metres west of Jarvis Street and a point 16 metres further west. 3. Toronto and East York Community Council prohibit stopping at all times on the north side of Front Street East, between Jarvis Street and a point 30.5 metres west. 4. Toronto and East York Community Council designate a commercial loading zone to be in effect at all times on the north side of Front Street East, between a point 30.5 metres west of Jarvis Street and a point 17.5 metres further west. 5. Toronto and East York Community Council prohibit stopping at all times on the north side of Front Street East, between a point 48 metres west of Jarvis Street and a point 24 metres further west. 6. Toronto and East York Community Council amend the existing parking prohibition in effect at all times, except Sunday and public holidays, on the east side of Jarvis Street, between Front Street East and Adelaide Street East, to be in effect between King Street East and Adelaide Street East. 7. Toronto and East York Community Council amend the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., and from 3:30 p.m. to 6:30 p.m., Monday to Friday, except public holidays, on the east side of Jarvis Street, between Front Street East and Shuter Street, to be in effect between King Street East and Shuter Street. 8. Toronto and East York Community Council prohibit stopping at all times on the east side of Jarvis Street, between Front Street East and King Street East.
TE23.39adopted
Ladysmith Avenue - Parking Amendments
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending that the existing school bus loading zone on the east side of Ladysmith Avenue be shifted 5.5 metres further south. This adjustment is being proposed to support safe student pick-up and drop-off operations, following the removal of an existing accessible parking space. As a result of this change, one additional on-street parking space will be gained.
The Toronto and East York Community Council: 1. Rescinded the existing accessible parking space on the east side of Ladysmith Avenue, between a point 15 metres north of Mountjoy Avenue and a point 5.5 metres further north. 2. Amended the existing school bus loading zone in effect from 8:00 a.m. to 5:00 p.m., Monday to Friday, on the east side of Ladysmith Avenue, between a point 20.5 metres north of Mountjoy Avenue and a point 30 metres further north, to be in effect between a point 15 metres north of Mountjoy Avenue and a point 30 metres further north. 3. Amended the existing maximum one-hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Saturday, on the east side of Ladysmith Avenue, between Danforth Avenue and a point 50.5 metres north of Mountjoy Avenue, to be in effect between Danforth Avenue and a point 45 metres north of Mountjoy Avenue. 4. Amended the existing maximum one-hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Saturday, on the east side of Ladysmith Avenue, between a point 20.5 metres north of Mountjoy Avenue and a point 30 metres further north, to be in effect between a point 15 metres north of Mountjoy Avenue and a point 30 metres further north. 5. Amended the existing permit parking regulation in effect from 12:01 a.m. to 7:00 a.m. daily on the odd (east) side of Ladysmith Avenue, from Mountjoy Avenue to Danforth Avenue, except no parking from a point 15 metres north of Mountjoy Avenue to a point 5.5 metres further north, to be in effect from Mountjoy Avenue to Danforth Avenue.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council rescind the existing accessible parking space on the east side of Ladysmith Avenue, between a point 15 metres north of Mountjoy Avenue and a point 5.5 metres further north. 2. Toronto and East York Community Council amend the existing school bus loading zone in effect from 8:00 a.m. to 5:00 p.m., Monday to Friday, on the east side of Ladysmith Avenue, between a point 20.5 metres north of Mountjoy Avenue and a point 30 metres further north, to be in effect between a point 15 metres north of Mountjoy Avenue and a point 30 metres further north. 3. Toronto and East York Community Council amend the existing maximum one-hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Saturday, on the east side of Ladysmith Avenue, between Danforth Avenue and a point 50.5 metres north of Mountjoy Avenue, to be in effect between Danforth Avenue and a point 45 metres north of Mountjoy Avenue. 4. Toronto and East York Community Council amend the existing maximum one-hour parking regulation in effect from 8:00 a.m. to 6:00 p.m., Monday to Saturday, on the east side of Ladysmith Avenue, between a point 20.5 metres north of Mountjoy Avenue and a point 30 metres further north, to be in effect between a point 15 metres north of Mountjoy Avenue and a point 30 metres further north. 5. Toronto and East York Community Council amend the existing permit parking regulation in effect from 12:01 a.m. to 7:00 a.m. daily on the odd (east) side of Ladysmith Avenue, from Mountjoy Avenue to Danforth Avenue, except no parking from a point 15 metres north of Mountjoy Avenue to a point 5.5 metres further north, to be in effect from Mountjoy Avenue to Danforth Avenue.
TE23.40adopted
Springhurst Avenue and Close Avenue - All-Way Stop Control
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is requesting approval to install all-way stop control at the intersection of Springhurst Avenue and Close Avenue. Based on the assessment undertaken, the installation of all-way stop control is recommended and should enhance safety for all road users.
The Toronto and East York Community Council: 1. Authorized all-way compulsory stop control at the intersection of Springhurst Avenue and Close Avenue.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community authorize all-way compulsory stop control at the intersection of Springhurst Avenue and Close Avenue.
TE23.41deferred
As the Toronto Transit Commission (TTC) operates a transit service on Sherbourne Street North, Elm Avenue and Maple Avenue, City Council approval of this report is required. Transportation Services is requesting approval to install traffic control signals at the intersection of Sherbourne Street North and Elm Avenue/Maple Avenue. The traffic control signals will provide enhanced safety for all road users and is justified based on the assessment undertaken. Due to the complex geometry of this intersection, for the traffic control signal to operate safely, it will also be necessary to: - Prohibit northbound right turns on red at all times from Sherbourne Street North to Elm Avenue; and - Designate Maple Avenue, between Sherbourne Street North and Glen Road (west intersection) one-way for eastbound traffic only.
The Toronto and East York Community Council: 1. Deferred consideration of the Item until the July 8, 2025 meeting of the Toronto and East York Community Council.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council authorize the installation of traffic control signals at the intersection of Sherbourne Street North and Elm Avenue/Maple Avenue. 2. Subject to approval of Recommendation 1 above and in conjunction with the installation of traffic control signals at Sherbourne Street North and Elm Avenue/Maple Avenue: a. City Council rescind the existing all-way compulsory stop control at the intersection of Sherbourne Street North and Elm Avenue/Maple Avenue. b. City Council prohibit northbound right turns on a red signal at all times, on Sherbourne Street North at Elm Avenue. c. City Council designate Maple Avenue, between Sherbourne Street North and Glen Road (west intersection), as one-way for eastbound traffic only.
TE23.42adopted
Vehicle Width Restriction - Lane south of Bloor Street West, Shaw Street to Ossington Avenue
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is seeking authority to prohibit vehicles greater than two metres in width from travelling on the first lane south of Bloor Street West, between Shaw Street and Ossington Avenue. Prohibiting vehicles which have a width of two metres or more from travelling on the subject lane section would be beneficial in reducing the incidence of damage to the surrounding private properties.
The Toronto and East York Community Council: 1. Prohibited vehicles over two metres in width from travelling on the first lane south of Bloor Street West, between Roxton Road and Shaw Street. 2. Prohibited vehicles over two metres in width from travelling on the first lane south of Bloor Street West, between Ossington Avenue and Roxton Road.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council prohibit vehicles over two metres in width from travelling on the first lane south of Bloor Street West, between Roxton Road and Shaw Street. 2. Toronto and East York Community Council prohibit vehicles over two metres in width from travelling on the first lane south of Bloor Street West, between Ossington Avenue and Roxton Road.
TE23.43adopted
Conger Coal Lane, between Church Street and Market Street - Speed Bumps
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of speed bumps in Conger Coal Lane, between Church Street and Market Street.
The Toronto and East York Community Council: 1. Authorized the installation of speed bumps in Conger Coal Lane, between Church Street and Market Street, at the locations shown on Attachment 1 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the installation of speed bumps in Conger Coal Lane, between Church Street and Market Street, at the locations shown on Attachment 1, Drawing TC-495, dated April 2025 attached to the report titled "Speed Bumps - Conger Coal Lane, between Church Street and Market Street" from the Director, Traffic Management, Transportation Services.
TE23.44amended
Charles Street West, between Queen's Park and Bay Street - Traffic Calming (Speed Humps)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services has reviewed the need for speed humps on Charles Street West, between Queen's Park and Bay Street. The assessment indicates the warrant criteria as set out in the updated Traffic Calming Policy has not been satisfied. Therefore, staff do not recommend the installation of speed humps on Charles Street West.
The Toronto and East York Community Council: 1. Authorized the installation of speed humps on Charles Street West, between Queen's Park and Bay Street. 2. Directed the City Solicitor to prepare a By-law to alter the roadway for the installation of seven speed humps on Charles Street West, between Queen's Park and Bay Street, generally as shown on Attachment 2 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council not authorize the installation of speed humps on Charles Street West, between Queen's Park and Bay Street.
TE23.45adopted
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of speed humps on Elgin Avenue, between Bedford Road and Avenue Road. Staff's assessment indicates the criteria as set out in the updated Traffic Calming Policy has been satisfied. Therefore, speed humps should be installed on Elgin Avenue. Transportation Services is also recommending enhancing the existing parking prohibition at anytime on the south side of Elgin Avenue, between Bedford Road and Avenue Road, to a no standing at anytime. This change will further deter parking and maintain unobstructed two-way traffic flow on this street.
The Toronto and East York Community Council: 1. Authorized the installation of speed humps on Elgin Avenue, between Bedford Road and Avenue Road. 2. Directed the City Solicitor to prepare a By-law to alter the roadway for the installation of three speed humps on Elgin Avenue, between Bedford Road and Avenue Road, generally as shown on Attachment 2 to the revised report (June 4, 2025) from the Director, Traffic Management, Transportation Services. 3. Rescinded the existing parking prohibition in effect at all times on the south side of Elgin Avenue, between Avenue Road and Bedford Road. 4. Prohibited standing at all times on the south side of Elgin Avenue, between Avenue Road and Bedford Road.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the installation of speed humps on Elgin Avenue, between Bedford Road and Avenue Road. 2. Toronto and East York Community Council direct the City Solicitor to prepare a by-law to alter the roadway for the installation of three speed humps on Elgin Avenue, between Bedford Road and Avenue Road, generally as shown on Attachment 2, Drawing TC-498 dated April 2025, attached to the report entitled "Traffic Calming (Speed Humps) and Parking Amendments - Elgin Avenue, between Bedford Road and Avenue Road" from the Director, Traffic Management, Transportation Services. 3. Toronto and East York Community Council rescind the existing parking prohibition in effect at all times on the south side of Elgin Avenue, between Avenue Road and Bedford Road. 4. Toronto and East York Community Council prohibit standing at all times on the south side of Elgin Avenue, between Avenue Road and Bedford Road.
TE23.46amended
Lippincott Street, between Harbord Street and Ulster Street - Traffic Calming (Speed Humps)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services has reviewed the need for speed humps on Lippincott Street, between Harbord Street and Ulster Street. The assessment indicates the warrant criteria as set out in the updated Traffic Calming Policy has not been satisfied. Therefore, staff do not recommend the installation of speed humps on Lippincott Street.
The Toronto and East York Community Council: 1. Authorized the installation of speed humps on Lippincott Street, between Harbord Street and Ulster Street. 2. Directed the City Solicitor to prepare a By-law to alter the roadway for the installation of three speed humps on Lippincott Street, between Harbord Street and Ulster Street, generally as shown on Attachment 2 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council not authorize the installation of speed humps on Lippincott Street, between Harbord Street and Ulster Street.
TE23.47adopted
Montrose Avenue, between Bloor Street West and Harbord Street - Traffic Calming (Speed Humps)
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is recommending the installation of speed humps on Montrose Avenue, between Bloor Street West and Harbord Street. Staff's assessment indicates the criteria as set out in the updated Traffic Calming Policy has been satisfied. Therefore, speed humps should be installed on Montrose Avenue.
The Toronto and East York Community Council: 1. Authorized the installation of speed humps on Montrose Avenue, between Bloor Street West and Harbord Street. 2. Directed the City Solicitor to prepare a By-law to alter the roadway for the installation of seven speed humps on Montrose Avenue, between Bloor Street West and Harbord Street, generally as shown on Attachment 2 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council authorize the installation of speed humps on Montrose Avenue, between Bloor Street West and Harbord Street. 2. Toronto and East York Community Council direct the City Solicitor to prepare a by-law to alter the roadway for the installation of seven speed humps on Montrose Avenue, between Bloor Street West and Harbord Street, generally as shown on Attachment 2, Drawing TC-508 dated April 2025, attached to the report entitled "Traffic Calming (Speed Humps) - Montrose Avenue, between Bloor Street West and Harbord Street" from the Director, Traffic Management, Transportation Services.
TE23.48amended
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services has reviewed the need for speed humps on Rathnelly Avenue, between Macpherson Avenue and Poplar Plains Crescent. The assessment indicates the warrant criteria as set out in the updated Traffic Calming Policy has not been satisfied. Therefore, staff do not recommend the installation of speed humps on Rathnelly Avenue.
The Toronto and East York Community Council: 1. Authorize the installation of speed humps on Rathnelly Avenue, between Macpherson Avenue and Poplar Plains Crescent. 2. Direct the City Solicitor to prepare a By-law to alter the roadway for the installation of five speed humps on Rathnelly Avenue, between Macpherson Avenue and Poplar Plains Crescent, generally as shown on Attachment 2 to the report (May 20, 2025) from the Director, Traffic Management, Transportation Services.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. Toronto and East York Community Council not authorize the installation of speed humps on Rathnelly Avenue, between Macpherson Avenue and Poplar Plains Crescent.
TE23.49adopted
This staff report is about a matter that Community Council has delegated authority from City Council to make a final decision. Transportation Services is requesting approval to convert Macdonell Avenue from Rideau Avenue to Fern Avenue from one-way southbound for motor vehicles to one-way northbound for motor vehicles, while maintaining two-way travel for cyclists. The purpose of this change is to address neighbourhood traffic infiltration concerns as part of the West Parkdale Cycling Connections project. In conjunction with this change, on-street parking is recommended to be moved from the west side of Macdonell Avenue to the east side between Rideau Avenue and Fern Avenue. Transportation Services is recommending the installation of speed humps on Wabash Avenue between Sorauren Avenue and Macdonell Avenue in the West Parkdale neighbourhood. Staff's assessment indicates the criteria as set out in the updated Traffic Calming Policy has been satisfied. Transportation Services is also recommending the prohibition of on-street parking on the west side of Macdonell Avenue between Wabash Avenue and a point 40 metres south of Wabash Avenue, due to the narrowing of the roadway required to facilitate construction of a missing sidewalk on the east side of Macdonell Avenue. It is also recommended that on-street parking be added on the south side of Wabash Avenue from a point 16 metres west of Macdonell Avenue to a point six (6) metres west of Macdonell Avenue to offset the removal of the noted parking spaces on Macdonell Avenue.
The Toronto and East York Community Council: 1. Amended traffic and parking regulations required in Toronto Municipal Code Chapters 925 and 950, as generally described in Attachment 1 to the report (May 20, 2025) from the Director, Planning, Design and Management, Transportation Services. 2. Authorized the installation of speed humps on Wabash Avenue between Sorauren Avenue and MacDonell Avenue. 3. Directed the City Solicitor to prepare a By-law to alter the roadway for the installation of speed humps, generally as shown on Attachment 3 to the report (May 20, 2025) from the Director, Planning, Design and Management, Transportation Services.
Staff recommendation as filed
The Director, Planning, Design and Management, Transportation Services recommends that: 1. Toronto and East York Community Council amend traffic and parking regulations required in Toronto Municipal Code Chapters 925 and 950, as generally described in Attachment 1 to the report entitled "Traffic Circulation Changes, Traffic Calming (Speed Humps) and Parking Amendments - West Parkdale Neighbourhood " from the Director, Planning, Design and Management, Transportation Services. 2. Toronto and East York Community Council authorize the installation of speed humps on Wabash Avenue between Sorauren Avenue and MacDonell Avenue. 3. Toronto and East York Community Council direct the City Solicitor to prepare a by-law to alter the roadway for the installation of speed humps, generally as shown on Attachment 3, Drawing TC-WA01 dated May 2025, attached to the report entitled "Traffic Circulation Changes, Traffic Calming (Speed Humps) and Parking Amendments - West Parkdale Neighbourhood" from the Director, Planning, Design and Management, Transportation Services.
TE23.50adopted
Parking and Traffic Amendments - Dundas Street West - Findings Report on Pilot Initiative
As the Toronto Transit Commission (TTC) operates a transit service on Dundas Street West, City Council approval of this report is required. In May 2024, Transportation Services recommended temporary parking and traffic amendments on Dundas Street West, between Spadina Avenue and McCaul Street, to enhance transit service. These changes were in support of the closure of the 510 Spadina streetcar right-of-way, initially scheduled from June until December of 2024. The Toronto Transit Commission (TTC) required alternate ways to support customers accessing the Chinatown neighbourhood during this time. To support the 505 Dundas streetcar travelling through Chinatown, the on-street paid parking in this section of Dundas Street West was to be removed during the construction period. This was generally replaced with regulations that prohibited stopping during the daytime periods and parking during the overnight periods. Additionally, areas were identified through consultation with the Chinatown BIA for on-street commercial and accessible loading activities. Finally, the existing weekday peak period turn prohibitions at Dundas Street West and Spadina Avenue were also amended to include weekends. As the TTC's construction on Spadina Avenue was not completed by the end of December 2024, Transportation Services subsequently recommended extending the temporary parking and traffic amendments on Dundas Street West to be in effect until the end of March 2025. Based on the TTC's findings and community consultation, adjustments were made to the parking and stopping prohibitions at this time to restore some paid parking outside the daytime peak period on the south side. As part of the extension approval, Transportation Services were also directed to report back by the second quarter of 2025 on the results of the temporary changes and the feasibility of making the changes permanent. Through consultation with the TTC, the data indicates that travel times have improved, with the following results: - In the eastbound direction, TTC saw improvements of up to 7% on the weekdays and 6% on the weekends in September. There was no impact major impact to the travel times when the parking signs were restored on the south side when looking at the January 2025 travel time numbers. - In the westbound direction, TTC saw improvements of up to 21% on weekdays and 10% on weekends in September. In January after signage changes on the south side were made, these improvements continued to be similar with improvements of up to 21% on weekdays and 12% on weekends. The TTC have reviewed the ridership numbers and there was no noticeable increase along the corridor, but the travel time and reliability improvement did impact the 14,000 daily customers who take the 505 streetcar on this stretch from Bathurst Street to University Avenue. The TTC are in favour of maintaining the current conditions permanently. The pilot project has resulted in the loss of approximately 81 on-street paid parking spaces and four parking machines, as well as a 94% decrease in transactions. If the spaces were to close permanently, the Toronto Parking Authority (TPA) assessed that the financial impact would be a loss of $322,000.00 in annual gross revenue (estimate), plus $6,780.00 for the pay machines (including tax). However, there is still alternative parking available for customers at nearby on-street paid parking locations (about 269 spaces within a 300-metre radius) and off-street Green P facilities including Car Park 150 at 40 Larch Street (capacity of 332 spaces), where TPA is currently pursuing state of good repair and wayfinding capital improvements. The average daily peak utilization at these parking locations indicates that there is capacity to absorb additional parking demand. There was consultation through Councillor's Saxe's office to advise the impacted business on this corridor to ensure there was general support for the changes made through the pilot period. As the pilot initiative on Dundas Street West achieves the goals of the Congestion Management plan in moving more people through the City, Transportation Services recommends that the temporary changes be made permanent.
The Toronto and East York Community Council recommends that: 1. City Council direct that the following amendments to parking and traffic regulations currently in place on Dundas Street West between Spadina Avenue and McCaul Street approved in Item TE13.42, as amended by MM23.35, be made permanent: a. prohibit stopping from 9:00 a.m. to 7:00 p.m., Monday to Friday and 12:00 p.m. to 9:00 p.m., Saturday and Sunday; b. prohibit parking from 7:00 p.m. to 9:00 a.m., Monday to Friday and 9:00 p.m. to 12:00 p.m., Saturday and Sunday; c. designate an Accessible loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 34.5 metres east of Huron Street and a point 12.5 metres further east, on the north side of Dundas Street West; d. designate Pay Parking, 6:30 p.m. to 9:00 p.m., Monday to Friday and 1:00 p.m. to 12:00 a.m., Sunday, on the south side of Dundas Street West; e. designate a 20-minute loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 55 metres east of Huron Street and a point 13.5 metres further east, on the south side of Dundas Street West; and f. designate a Bus loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 9 metres east of Beverley Street and a point 86 metres further east, on the south side of Dundas Street West.
Staff recommendation as filed
The Director, Traffic Management, Transportation Services recommends that: 1. City Council direct that the following amendments to parking and traffic regulations currently in place on Dundas Street West between Spadina Avenue and McCaul Street approved in Item TE13.42, as amended by MM23.35, be made permanent: a. prohibit stopping from 9:00 a.m. to 7:00 p.m., Monday to Friday and 12:00 p.m. to 9:00 p.m., Saturday and Sunday b. prohibit parking from 7:00 p.m. to 9:00 a.m., Monday to Friday and 9:00 p.m. to 12:00 p.m., Saturday and Sunday c. designate an Accessible loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 34.5 metres east of Huron Street and a point 12.5 metres further east, on the north side of Dundas Street West d. designate Pay Parking, 6:30 p.m. to 9:00 p.m., Monday to Friday and 1:00 p.m. to 12:00 a.m., Sunday, on the south side of Dundas Street West e. designate a 20-minute loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 55 metres east of Huron Street and a point 13.5 metres further east, on the south side of Dundas Street West f. designate a Bus loading zone, 9:30 a.m. to 3:30 p.m., daily, between a point 9 metres east of Beverley Street and a point 86 metres further east, on the south side of Dundas Street West