The filed record
Award of Tender Call No. 29-2018 to Sanscon Construction Limited for Highland Crescent Road Reconstruction and Storm Sewer Installation
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2018-12-05 · Bid Award Panel · adopted
As filed
The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (October 31, 2018) from the Chief Purchasing Officer: Call Number: Tender Call No. 29-2018 Description: Contract No. 18ECS-TI-17LR For Highland Crescent Road Reconstruction and Storm Sewer Installation. Recommended Bidder: Sanscon Construction Ltd. Contract Award
Show the rest of As filed, 230 more characters as filed
Value: $2,356,448 net of all applicable taxes and charges $2,662,786 including HST and all applicable charges $2,397,921 net of HST recoveries Contract is expected to start on the data of award and end no later than July 19, 2019.
On the agenda
As the city filed it
Call Issued: September 24, 2018 Call Closed: October 12, 2018 Number of Addenda Issued: Three (3) Number of Bids: Twelve (12) Table 2: Summary of Bids Received for Tender Call No 29-2018 including bid price Bidder Name Bid Price (including H.S.T.) Sanscon Construction Limited $2,662,786 * D. Martino Construction Limited $2,863,493 Mar-King Construction Company Limited $2,893,419 IL Duca Contracting Incorporated $2,960,416 * Gazzola Paving Limited $2,995,940 Grascan Construction Limited $3,387,000 * CRCE Construction Limited $3,430,755 * Kapp Infrastructure Incorporated $3,575,246 Rafat General Contractor Incorporated $3,675,446 2489960 ONTARIO INCORPORATED $3,753,619 * Trisan Construction $4,483,007 Midome Construction Services Limited $5,724,015 * Tender prices were corrected for mathematical errors.
Show the rest of As the city filed it, 93 more characters as filed
Purchasing and Materials Management has verified that the mathematical errors were corrected.
Staff recommended
The Chief Purchasing Officer recommends that the Bid Award Panel grant authority to award the following contract: Call Number: Tender Call No. 29-2018 Description: Contract No. 18ECS-TI-17LR For Highland Crescent Road Reconstruction and Storm Sewer Installation. Recommended Bidder: Sanscon Construction Ltd. Contract Award Value: $2,356,448 net of all applicable taxes and charges $2,662,786 including HST and all applicable
Show the rest of Staff recommended, 128 more characters as filed
charges $2,397,921 net of HST recoveries Contract is expected to start on the data of award and end no later than July 19, 2019.
On the record
More from this meeting
- Award of Request for Proposal No. 3405-18-0150 to Abledent Incorporated for Dental Clinic Management SystemFiled record
- Award of Request for Proposal No. 9150-18-0145 to AECOM Canada Limited for Design, Contract Administration and Post Construction for Dufferin Waste Facility Site ImprovementFiled record
- Award of Request for Quotation No. 6114-18-0302 to Metro Freightliner Hamilton and Tallman Truck Centre Limited for the Supply and Delivery of Twenty-Four (24) Latest Model Various Types Truck Chassis and Cab, 60,000 LBS (27,216 KG) GVWR, Tandem Axle Complete with Various BodiesFiled record
- Award of Request for Quotation No. 6125-18-0282 to Kal Tire for the Non-exclusive Provision of 24/7 Mobile Roadside and On-site Tire ServicesFiled record
- Award of Tender Call No. 244-2018 to Pine Valley Corporation for Streetscape Construction for Transportation Services - Ryerson Avenue and Wolseley Street and Ryerson Avenue and Carr StreetFiled record