Award of Ariba Doc Number 2203137711 to Aqua Tech Solutions Inc. for the Inlet Control Devices Installation Pilot Project - Fairbank Silverthorn Storm Trunk Sewer System
The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.
The decision
2020-04-01 · Bid Award Panel · adopted
As filed
The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (February 28, 2020) from the Chief Purchasing Officer: Call Number: Ariba Doc Number 2203137711, Contract Number 20ECS-LU-01TT (Request For Tender Number 8-2020) Description: Inlet Control Devices Installation Pilot Project - Fairbank Silverthorn Storm Trunk Sewer System.
Show the rest of As filed, 279 more characters as filed
Recommended Bidder or Proponent: Aqua Tech Solutions Inc. Contract Award Value: $554,811 net of all applicable taxes and charges $626,936 including HST and all applicable charges $564,575 net of HST recoveries Contract is expected to start in April 2020 and end in December 2021.
On the agenda
As the city filed it
Call Issued: February 4, 2020 Call Closed: February 18, 2020 Number of Addenda Issued: 0 Number of Bids: One (1) Table 2: Summary of Bids Received for Request for Proposal Including Bid Price Proponent Name Bid Price (including H.S.T.) Aqua Tech Solutions Inc. $626,936
Staff recommended
The Chief Purchasing Officer recommends that the Bid Award Panel grant authority to award the following contract: Call Number: Ariba Doc Number 2203137711, Contract Number 20ECS-LU-01TT (Request For Tender Number 8-2020) Description: Inlet Control Devices Installation Pilot Project - Fairbank Silverthorn Storm Trunk Sewer System. Recommended Bidder or Proponent: Aqua Tech Solutions Inc. Contract Award Value: $554,811
Show the rest of Staff recommended, 190 more characters as filed
net of all applicable taxes and charges $626,936 including HST and all applicable charges $564,575 net of HST recoveries Contract is expected to start in April 2020 and end in December 2021.
On the record
More from this meeting
- Award of Ariba Doc Number 2190370119 to M.J. Dixon Construction Ltd. for the Construction of a Net-Zero Energy Childcare Facility located at 1234 Weston RoadFiled record
- Award of Ariba Doc Number 2224344927 to Pave-Tar Construction Ltd. for Permanent Repairs to Utility Cuts and Milling and Paving on Yonge Street, Bay Street, and Gerrard Street East in the Toronto and East York DistrictFiled record
- Award of Ariba Doc Number 2224471306 to Maple Crete Inc. for Permanent Repairs to Utility Cuts in the Toronto and East York DistrictFiled record
- Award of Ariba Doc Number 2241509014 to Maple Crete Inc. for Permanent Repairs to Utility Cuts, Builders Files within North York DistrictFiled record
- Award of Request for Proposal Doc 2047288479 to WSP Canada Group Limited for Security Upgrades at Humber Wastewater Treatment PlantFiled record