The decision
2023-10-25 · Bid Award Panel · adopted
As filed
The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (October 19, 2023) from the Chief Procurement Officer: Solicitation Number: Request for Tender, Ariba Document Number 4141341712, Contract Number 23ECS-BE-06BSE Description: Culvert Replacement of Martin Grove Road over Albion Creek (ID633) Recommended Supplier: Belor Construction Ltd.
Show the rest of As filed, 234 more characters as filed
Contract Award Value: $7,255,344 net of all applicable taxes and charges $8,198,539 including HST and all applicable charges $7,383,038 net of HST recoveries Contract is expected to start on date of award and end on December 31, 2025.
On the agenda
As the city filed it
Solicitation Issued: August 17, 2023 Solicitation Closed: September 18, 2023 Number of Addenda Issued: Five (5) Number of Bids: Nine (9) Table 2: Summary of Bids Received including bid price Supplier Bid Price (excluding H.S.T.) Belor Construction Ltd. $6,046,119.80* Alliance Verdi Civil Inc. $6,371,123.90 2220742 Ontario Ltd. o/a Bronte Construction $7,200,788.60 614128 Ontario Ltd. o/a Trisan Construction $7,798,161.30 Clearway Construction Inc.
Show the rest of As the city filed it, 268 more characters as filed
$7,985,165.60 Kapp Infrastructure Inc. $7,987,999.20 Drainstar Contracting Ltd. $8,282,464.95 EllisDon Civil Ltd $8,924,839.00 Brennan Paving & Construction Ltd. $9,669,129.65 * Pursuant to the Request for Tender document the contract award value includes contingency.
Staff recommended
The Chief Procurement Officer recommends that the Bid Award Panel grant authority to award the following contract: Solicitation Number: Request for Tender, Ariba Document Number 4141341712, Contract Number 23ECS-BE-06BSE Description: Culvert Replacement of Martin Grove Road over Albion Creek (ID633) Recommended Supplier: Belor Construction Ltd. Contract Award Value: $7,255,344 net of all applicable taxes and charges $8,198,539
Show the rest of Staff recommended, 150 more characters as filed
including HST and all applicable charges $7,383,038 net of HST recoveries Contract is expected to start on date of award and end on December 31, 2025.
On the record
More from this meeting
- Award of Ariba Document Number 3979244860 to Superior Boiler Works and Welding Limited for the Toronto Interceptors Real Time Control Implementation for Toronto WaterFiled record
- Award of Ariba Document Number 3951063187 to Phoenix Restoration Inc. for the East Bridge (Bay Street) Interior Connection at 61 Front Street West, Toronto, for Corporate Real Estate ManagementFiled record
- Award of Ariba Document Number 4104321075 to KAPP Infrastructure Inc. for Replacement of Culvert 840 at Huntingwood Drive and Replacement of Culvert 925 at Collingsbrook Boulevard for Engineering and Construction ServicesFiled record
- Award of Ariba Document Number 4011687155 to AECOM Canada Ltd. for Professional Services for Highland, Dorset Park, Fairfield and Avenue Manor Trunk Sewer Rehabilitation Engineering for Engineering and Construction ServicesFiled record
- Award of Ariba Document Number 4131082400 to 3M Canada Company for the Non-Exclusive Supply, Delivery and Warranty of Reflective and Non-Reflective Sheeting for Transportation ServicesFiled record
- Award of Ariba Document Number 4150226092 to Joe Pace and Sons Contracting Inc. for Toronto Accessibility Upgrade Program (AODA) Tender Group 01, at 11 Various Buildings for Corporate Real Estate ManagementFiled record