Award of Doc5008094921 to various Suppliers to provide Asphalt and Concrete Paving Services for Parks and Recreation

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2025-06-18 · Bid Award Panel · adopted

As filed

The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (June 12, 2025) from the Chief Procurement Officer: Solicitation Number: Request for Quotation Doc5008094921 Description: For the supply, delivery, installation and warranty required to provide Asphalt and Concrete Paving Services at various Parks and Recreation locations throughout the City of Toronto's Parks and Recreation for a period of eighteen (18) months for Capital Projects and Parks Operations.

Show the rest of As filed, 1,698 more characters as filed

Recommended Suppliers: Lincoln Paving and Contracting (Capital Projects and Parks Operations - North District) Tony Battista Paving Inc. (Capital Projects and Parks Operations - West District) Bond Paving & Construction Inc. (Capital Projects and Parks Operations - East District) Four Seasons Site Development Ltd. (Capital Projects and Parks Operations - South District) Mopal Construction Limited (Capital Projects and Parks Operations - City-wide) Contract Award Value: Lincoln Paving and Contracting $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Tony Battista Paving Inc. $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Bond Paving & Construction Inc. $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Four Seasons Site Development Ltd. $5,000,000 net of all applicable taxes and charges $5,650,000 including HST and all applicable charges $5,088,000 net of HST recoveries Mopal Construction Limited $5,000,000 net of all applicable taxes and charges $5,650,000 including HST and all applicable charges $5,088,000 net of HST recoveries The contract is expected to start on the date of award and end by December 31, 2028. This includes a two (2) year warranty period. The combined total potential contract award identified in this report is $37,000,000 net of all applicable taxes and charges, $41,810,000 including HST and applicable charges. The combined total potential cost to the City is $37,651,200 net of HST recoveries.

On the agenda

As the city filed it

Solicitation Issued: March 26, 2025 Solicitation Closed: April 23, 2025 Number of Addenda Issued:One (1) Number of Bids: Five (5) Table 2: Summary of Bids Received including bid price Category 1 - Capital Projects Supplier Name Bid Price (excluding H.S.T.) 1. Lincoln Paving and Contracting $3,347,005.00 2. Tony Battista Paving Inc. $3,530,460.00 3. Bond Paving & Construction Inc. $3,640,500.00 4. Four Seasons Site Development Ltd.

Show the rest of As the city filed it, 834 more characters as filed

$4,156,250.00 5. Mopal Construction Limited $4,874,484.50 Pursuant to the Request for Quotation document, the Contract Award Value for Category 1 - Capital Projects is $8,000,000 to the compliant lowest, second lowest and third lowest bid Suppliers, and $4,000,000 contract to the compliant fourth lowest and fifth lowest bid Suppliers. Category 2 - Parks Operations Supplier Name Bid Price (excluding H.S.T.) 1. Bond Paving & Construction Inc. $2,991,550.00 2. Lincoln Paving and Contracting $3,252,315.00 3. Tony Battista Paving Inc. $3,318,550.00 4. Four Seasons Site Development Ltd. $4,030,250.00 5. Mopal Construction Limited $4,914,329.50 Pursuant to the Request for Quotation document, the Contract Award Value for Category 2 - Parks Operations, the five (5) Operations contracts will be at a value of $1,000,000 per Supplier.

Staff recommended

The Chief Procurement Officer recommends that the Bid Award Panel grant authority to award the following contract: Solicitation Number: Request for Quotation Doc5008094921 Description: For the supply, delivery, installation and warranty required to provide Asphalt and Concrete Paving Services at various Parks and Recreation locations throughout the City of Toronto's Parks and Recreation for a period of eighteen (18) months for Capital Projects and Parks Operations.

Show the rest of Staff recommended, 1,698 more characters as filed

Recommended Suppliers: Lincoln Paving and Contracting (Capital Projects and Parks Operations - North District) Tony Battista Paving Inc. (Capital Projects and Parks Operations - West District) Bond Paving & Construction Inc. (Capital Projects and Parks Operations - East District) Four Seasons Site Development Ltd. (Capital Projects and Parks Operations - South District) Mopal Construction Limited (Capital Projects and Parks Operations - City-wide) Contract Award Value: Lincoln Paving and Contracting $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Tony Battista Paving Inc. $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Bond Paving & Construction Inc. $9,000,000 net of all applicable taxes and charges $10,170,000 including HST and all applicable charges $9,158,400 net of HST recoveries Four Seasons Site Development Ltd. $5,000,000 net of all applicable taxes and charges $5,650,000 including HST and all applicable charges $5,088,000 net of HST recoveries Mopal Construction Limited $5,000,000 net of all applicable taxes and charges $5,650,000 including HST and all applicable charges $5,088,000 net of HST recoveries The contract is expected to start on the date of award and end by December 31, 2028. This includes a two (2) year warranty period. The combined total potential contract award identified in this report is $37,000,000 net of all applicable taxes and charges, $41,810,000 including HST and applicable charges. The combined total potential cost to the City is $37,651,200 net of HST recoveries.

    On the record