Award of Ariba Document Number 3668065184 to 614128 Ontario Ltd., o/a Trisan Construction for Basement Flooding Protection Program, Phase 4, Assignments 19-03, 19-06A, 19-07 and 19-16 Westgate for Engineering and Construction Services

The Public Gallery wrote no story on this item. What follows is the city’s own record of what happened to it, as filed: nothing on this page is summarised or scored by us.

The decision

2022-12-14 · Bid Award Panel · adopted

As filed

The Bid Award Panel adopted the following: 1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (December 8, 2022) from the Chief Procurement Officer: Solicitation Number: Request for Tender, Ariba Document Number 3668065184, Contract Number 21ECS-LU-04FP Description: Construction of sewer upgrades and related improvements for Basement Flooding Protection Program Phase 4, Assignments 19-03, 19-06A, 19-07 and 19-16 on Edinburgh Drive, Southgate Avenue, Westgate Boulevard, Delhi Avenue, Wendy Crescent, Garratt Boulevard, Wilson Avenue, Faywood Boulevard, King High Avenue, Laurelcrest Avenue, Palm Drive, Banton Road, Bonnacord Drive, Clanton Park Road, Clanton Park Trail, Collinson Boulevard, Delia Court, Erica Avenue and Midvale Road.

Show the rest of As filed, 304 more characters as filed

Recommended Supplier: 614128 Ontario Ltd., o/a Trisan Construction Contract Award Value: $44,966,572 net of all applicable taxes and charges $50,812,226 including all applicable taxes and charges $45,757,983 net of HST recoveries Contract is expected to start on January 16, 2023 and end on July 4, 2025.

On the agenda

As the city filed it

Solicitation Issued: September 23, 2022 Solicitation Closed: November 10, 2022 Number of Addenda Issued: Seven (7) Number of Bids: Seven (7) Table 2: Summary of Bids Received Supplier Name Bid Price (Excluding H.S.T) 614128 Ontario Ltd. o/a Trisan Construction $38,975,130.80* Varcon Construction Corporation $41,688,354.16 Green Infrastructure Partners Inc. $42,944,537.26 Clearway Construction Inc. $44,707,662.00 Memme Excavation Company Limited** $52,190,226.00 Drainstar Contracting Ltd.

Show the rest of As the city filed it, 211 more characters as filed

$52,837,941.00 KAPP Infrastructure Inc. $56,677,000.50 *Pursuant to the Request for Tender document the contract award value includes contingency. **Supplier found to be non-compliant with mandatory requirements

Staff recommended

The Acting Chief Procurement Officer recommends that the Bid Award Panel, pursuant to Section 195-8.3.A(2) of the Municipal Code, Chapter 195, Purchasing, exercise the power of a Standing Committee to grant authority to award the following contract: Solicitation Number: Request for Tender, Ariba Document Number 3668065184, Contract Number 21ECS-LU-04FP Description: Construction of sewer upgrades and related improvements

Show the rest of Staff recommended, 722 more characters as filed

for Basement Flooding Protection Program Phase 4, Assignments 19-03, 19-06A, 19-07 and 19-16 on Edinburgh Drive, Southgate Avenue, Westgate Boulevard, Delhi Avenue, Wendy Crescent, Garratt Boulevard, Wilson Avenue, Faywood Boulevard, King High Avenue, Laurelcrest Avenue, Palm Drive, Banton Road, Bonnacord Drive, Clanton Park Road, Clanton Park Trail, Collinson Boulevard, Delia Court, Erica Avenue and Midvale Road. Recommended Supplier: 614128 Ontario Ltd., o/a Trisan Construction Contract Award Value: $44,966,572 net of all applicable taxes and charges $50,812,226 including all applicable taxes and charges $45,757,983 net of HST recoveries Contract is expected to start on January 16, 2023 and end on July 4, 2025.